PropertyLensBengaluru · invest
← Project pageFull investment reportChoose “Save as PDF” in the print dialog.
PropertyLensBengaluru · invest
Financial & legal due diligence · public record · 18 Oct 2026

Century Novus

Century Real Estate · Yelahanka / Jakkur / Airport corridor · BBMP Khatha No.1305/10/2, Sy.no.10/2, , Jakkur Village, Yelahanka Hobli, Bangalore North Taluk

Promoter entityTALREJA REALTY LLP
Entity type · PANOther · AATFT3639D
Developer brandCentury Real Estate · #25 in Bengaluru by RERA registrations
RERA registrationsRegistration: PRM/KA/RERA/1251/309/PR/100423/005853
Planning authorityBBMP - Bruhat Bengaluru Mahanagara Palike
Sanctioned planLP No. BBMP/Addl.Dir/JDNORTH/0039/21-22 (PRJ No. PRJ/2992/21-22) · 2023-02-13
Escrow bankDCB Bank, MG Road, Bangalore
Land2.34 acres · 32 land owners on record
Court cases declared1
Complaints at K-RERA0 on this project · 0 on the promoter
Record fetchedSep 2026
0 red flags3 to watch4 positive

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/100423/005853 and 3 quarterly filings. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.

Financial & legal due diligence

What the public record says

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/100423/005853 and 3 quarterly filings. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.

0 red3 watch4 positive
Delivery timeline9/10
no extensions, no overdue dates on the RERA file
Legal & complaints7.5/10
1 court case declared in filings (−1.5)
Money to finish9/10
finance cost is 0% of the registered budget; last quarter: collected ₹7.09 cr, withdrew ₹4.30 cr; 94% of homes booked (+1)
Developer strength2.6/10
Acuité B-/Stable (Century Joint Developments)

Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.

Registration
PRM/KA/RERA/1251/309/PR/100423/005853 · TALREJA REALTY LLP
On original date
RegisteredMar 2023TodaySep 2026Original completionAug 2027
Construction82%
quarterly filing Q1 2026-27 (submitted 2026-07-14)
Homes booked219 / 234
15 still available
Sold vs built94% vs 82%
Sales and construction are broadly in step.
Money through the RERA account
Collected ₹8.98 CrWithdrawn ₹6.40 CrQ3 2025-268.98 Cr6.40 CrCollected ₹1.29 CrWithdrawn ₹90.5 LQ4 2025-261.29 Cr90.5 LCollected ₹7.09 CrWithdrawn ₹4.30 CrQ1 2026-277.09 Cr4.30 Cr
Collected from buyersWithdrawn for construction
Latest milestones
  • Electrification, Water supply and Sanitary
    0%
  • Fire prevention and fire fighting fitting
    0%
  • Weather Proof work
    0%
  • Internal and External work including lands
    0%
  • Painting
    45%
  • Basic work of Water supply, Sanitary and E
    50%
1 court case declaredNo complaintsEscrow: DCB BankJoint-development land
Credit ratings of the people behind it
AAAAAABBBBBBCDinvestment grade ◀▶ speculative gradeAcuité B- / Stable ▲ · Century Joint Developments · Aug 2025
Complaints & disputes on record
On this project00 open
On the promoter entity0all projects
Court cases declared1no stay recorded
At a glance
On its original RERA date

On its original RERA completion date: 2027-08-31

82% built, 94% booked

82% built per the latest filing; 219/234 homes booked

No complaints on this project

No RERA complaints on this project; 0 on the promoter overall

1 court case declared

1 court case declared in RERA filings (no stay recorded)

The record, in pictures

RERA file · Registration

Registered project cost ₹158 cr — where it goes
Approvals ₹5.6 cr · 4%Construction & on-site ₹115.6 cr · 73%Other / taxes ₹36.5 cr · 23%
Construction programme as filed (quarterly filing Q1 2026-27 (submitted 2026-07-14))
2024202520262027Earth work and other leveling preparat100%Foundation footing work100%Upto Plinth Level100%Sub-structure flooring100%Retaining wall100%RCC or MS Framed structure96%Masonry Construction98%Plastering inside , outside & Ceiling95%Joinery: Doors, Windows, Ventilators e65%Basic work of Water supply, Sanitary a50%Dadoing, Skirting, Flooring, Tiles wor95%Railing and Grill fixing65%Electrification, Water supply and Sani0%Painting45%Fire prevention and fire fighting fitt0%Weather Proof work0%Internal and External work including l0%today
Bars are the filed schedule; filled part is reported progress. Red = past its scheduled end and not complete.
Regular First Appeal 85/2024 · The High Court of Karnataka · no stayBorrowing declared: NoEscrow at DCB Bank32 recorded land-owner sharesOwners’ association: not formed

Red flags to resolve in writing

1
Legal

1 court case declared in RERA filings (85/2024); check for stays and title impact.

2
Legal

Joint-development land: confirm which units fall in the owners’ share.

Questions to put to the developer before you sign

  1. Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
  2. Confirm the price list, floor-rise and other charges for the exact unit.
  3. Which date is contractual — 2027-08-31 — and what is the per-month delay compensation?
  4. What do the declared cases (85/2024) concern and is any stay in force?
  5. What is the land owners’ share of built area and is the unit in the developer’s share?
Full record: every filed number, line by line1 sections · 13 items

RERA file · Registration

Registration
PRM/KA/RERA/1251/309/PR/100423/005853 · promoter TALREJA REALTY LLP (Other) · AAY-1622
Dates
Start 2023-03-01 · original completion 2027-08-31 · no extensions
Progress
82% complete per quarterly filing Q1 2026-27 (submitted 2026-07-14) · 219 of 234 homes booked (15 available)
Registered cost
Total ₹158 cr · construction ₹116 cr
Borrowing / mortgage declared
Borrowing: No · mortgage: No
RERA bank account
DCB Bank, MG Road, Bangalore (70% construction account)
Plan sanction
LP No. BBMP/Addl.Dir/JDNORTH/0039/21-22 (PRJ No. PRJ/2992/21-22) dated 2023-02-13 · BBMP - Bruhat Bengaluru Mahanagara Palike
Land & towers
2.34 acres (9,475 sq m) · A 117 homes, 12 floors; B 117 homes, 12 floors
Land owners / co-promoters
No. of Basement (1%, Sy Total No. of Parking); 34.99 (1%, Sy 2); 34.99 (1%, Sy 3); 34.99 (1%, Sy 4); 50.2 (1%, Sy 5); 50.2 (1%, Sy 6); 34.14 (1%, Sy 7); 34.14 (1%, Sy 8) +24 more
Litigation declared
Regular First Appeal 85/2024, The High Court of Karnataka — no stay
K-RERA complaints
0 on this registration (0 open) · 0 on the promoter entity across all its projects (a project-specific LLP; group-level complaints sit under other entities)
Owners’ association
Not yet formed
Completion applied
19/12/2020

Source: Karnataka RERA project record PRM/KA/RERA/1251/309/PR/100423/005853, fetched 2026-09-15. Figures are the promoter’s own filings.

Sources & caveats2 sources
  • Karnataka RERA project record PRM/KA/RERA/1251/309/PR/100423/005853 (registration file, quarterly updates, complaint register), fetched 2026-09-15
  • PropertyLens locality model (market-level estimates)
  • Karnataka RERA project records PRM/KA/RERA/1251/309/PR/100423/005853 (registration file, quarterly updates, complaint register), fetched Sep 2026.

Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.

PropertyLens · property-lens.ai · Facts are transcribed from public records as filed by the promoter and the regulator; figures on RERA certificates are promoter numbers certified on unaudited books. Absence of a court case or insolvency filing in these sources is not proof that none exists. Verify title, approvals and encumbrances with a lawyer before you sign. Nothing here is legal, tax or investment advice.
Share on WhatsApp