Financial & legal due diligence · public record · 18 Oct 2026

Concorde Neo

Concorde · Yelahanka / Jakkur / Airport corridor · Sy No.5/1C & 7, Chikkasandra Village,Yeshwanthpura Hobli

Promoter entityConcorde Housing Corporation Pvt Ltd
Entity type · PANCompany · AADCC4087F
Developer brandConcorde · #20 in Bengaluru by RERA registrations
RERA registrationsRegistration: PRM/KA/RERA/1251/309/PR/270924/007088
Planning authorityBBMP - Bruhat Bengaluru Mahanagara Palike
Sanctioned planBBMP/Addl.Dir/JDNorth/0105/23-24 · 2024-05-16
Escrow bankHDFC, Kasturba Gandhi Marg
Land4.34 acres
Court cases declared0
Complaints at K-RERA0 on this project · 2 on the promoter
Record fetchedSep 2026
0 red flags0 to watch6 positive

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/270924/007088 and 3 quarterly filings. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.

Financial & legal due diligence

What the public record says

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/270924/007088 and 3 quarterly filings. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.

0 red0 watch6 positive
Delivery timeline9/10
no extensions, no overdue dates on the RERA file
Legal & complaints9/10
no litigation and no complaints on the RERA file
Money to finish8/10
finance cost is 12% of the registered budget; last quarter: collected ₹10.18 cr, withdrew ₹10.18 cr
Developer strength5/10
no public credit rating for the promoter

Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.

Registration
PRM/KA/RERA/1251/309/PR/270924/007088 · Concorde Housing Corporation Pvt Ltd
On original date
RegisteredOct 2024TodaySep 2026Original completionOct 2029
Construction27%
quarterly filing Q1 2026-27 (submitted 2026-07-15)
Homes booked202 / 424
222 still available
Sold vs built48% vs 27%
Sales and construction are broadly in step.
Money through the RERA account
Collected ₹8.13 CrWithdrawn ₹8.13 CrQ3 2025-268.13 Cr8.13 CrCollected ₹11.23 CrWithdrawn ₹11.23 CrQ4 2025-2611.23 Cr11.23 CrCollected ₹10.18 CrWithdrawn ₹10.18 CrQ1 2026-2710.18 Cr10.18 Cr
Collected from buyersWithdrawn for construction
Latest milestones
  • Joinery: Doors, Windows, Ventilators etc
    0%
  • Basic work of Water supply, Sanitary and E
    0%
  • Dadoing, Skirting, Flooring, Tiles work
    0%
  • Railing and Grill fixing
    0%
  • Painting
    0%
  • Fire prevention and fire fighting fitting
    0%
No litigation declaredNo complaintsNBFC finance 12% of budgetEscrow: HDFC
Credit ratings of the people behind it

No public credit rating located for the promoter.

Concorde Housing Corporation Pvt Ltd: no public rating located

Complaints & disputes on record
On this project00 open
On the promoter entity2all projects
Court cases declared0no stay recorded
At a glance
On its original RERA date

On its original RERA completion date: 2029-10-31

27% built, 48% booked

27% built per the latest filing; 202/424 homes booked

No complaints on this project

No RERA complaints on this project; 2 on the promoter overall

No litigation declared

No litigation declared in RERA filings

The record, in pictures

RERA file · Registration

Registered project cost ₹341 cr — where it goes
Land ₹0 cr · 0%Approvals ₹9.9 cr · 3%Construction & on-site ₹267.4 cr · 78%Finance (NBFC) ₹40.3 cr · 12%Other / taxes ₹23.5 cr · 7%
Construction programme as filed (quarterly filing Q1 2026-27 (submitted 2026-07-15))
20252026202720282029Earth work and other leveling preparat95%Foundation footing work85%Upto Plinth Level75%Sub-structure flooring45%Retaining wall60%RCC or MS Framed structure45%Masonry Construction50%Plastering inside , outside & Ceiling50%Joinery: Doors, Windows, Ventilators e0%Basic work of Water supply, Sanitary a0%Dadoing, Skirting, Flooring, Tiles wor0%Railing and Grill fixing0%Electrification, Water supply and Sani20%Painting0%Fire prevention and fire fighting fitt0%Weather Proof work0%Internal and External work including l0%today
Bars are the filed schedule; filled part is reported progress. Red = past its scheduled end and not complete.
No litigation declaredBorrowing declared: NoEscrow at HDFCOwners’ association: not formed

Red flags to resolve in writing

Questions to put to the developer before you sign

  1. Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
  2. Confirm the price list, floor-rise and other charges for the exact unit.
  3. Which date is contractual — 2029-10-31 — and what is the per-month delay compensation?
  4. Confirm there is no litigation on the land or approvals beyond the RERA declaration.
  5. Is the land freehold with the developer, and is any part mortgaged?
Full record: every filed number, line by line1 sections · 12 items

RERA file · Registration

Registration
PRM/KA/RERA/1251/309/PR/270924/007088 · promoter Concorde Housing Corporation Pvt Ltd (Company) · U70102KA2008PTC046886
Dates
Start 2024-10-01 · original completion 2029-10-31 · no extensions
Progress
27% complete per quarterly filing Q1 2026-27 (submitted 2026-07-15) · 202 of 424 homes booked (222 available)
Registered cost
Total ₹341 cr · land ₹0.00 cr · construction ₹267 cr · NBFC principal+interest ₹40.32 cr (12%)
Borrowing / mortgage declared
Borrowing: No
RERA bank account
HDFC, Kasturba Gandhi Marg (70% construction account)
Plan sanction
BBMP/Addl.Dir/JDNorth/0105/23-24 dated 2024-05-16 · BBMP - Bruhat Bengaluru Mahanagara Palike
Land & towers
4.34 acres (17,559 sq m) · A 72 homes, 18 floors; B 72 homes, 18 floors; C 72 homes, 18 floors; D 72 homes, 18 floors; E 72 homes, 18 floors; F 64 homes, 18 floors
Litigation declared
None declared in filings
K-RERA complaints
0 on this registration (0 open) · 2 on the promoter entity across all its projects
Owners’ association
Not yet formed
Completion applied
19/12/2020

Source: Karnataka RERA project record PRM/KA/RERA/1251/309/PR/270924/007088, fetched 2026-09-15. Figures are the promoter’s own filings.

Sources & caveats2 sources
  • Karnataka RERA project record PRM/KA/RERA/1251/309/PR/270924/007088 (registration file, quarterly updates, complaint register), fetched 2026-09-15
  • PropertyLens locality model (market-level estimates)
  • Karnataka RERA project records PRM/KA/RERA/1251/309/PR/270924/007088 (registration file, quarterly updates, complaint register), fetched Sep 2026.

Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.

PropertyLens · property-lens.ai · Facts are transcribed from public records as filed by the promoter and the regulator; figures on RERA certificates are promoter numbers certified on unaudited books. Absence of a court case or insolvency filing in these sources is not proof that none exists. Verify title, approvals and encumbrances with a lawyer before you sign. Nothing here is legal, tax or investment advice.