Nitesh Melbourne Park
Nitesh Estates · KR Puram / Mahadevapura / Hoskote Road · Sy No-114(part), 119 & 159 situated at Byrathi Village, Bidarahalli Hobli, off Hennur Main Road
Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/170916/000224. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.
What the public record says
Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/170916/000224. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.
Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.
No public credit rating located for the promoter.
NITESH HOUSING DEVELOPERS PRIVATE LIMITED: no public rating located
- Reimbursement of dues and completion & possession of the property
- Reimbursement of dues and completion & possession of the property
- Reimbursement of dues and completion & possession of the property
- Inordinate delay in completion of project and handing over possession - Refund Request
Registration extended 1× — from 2022-03-31 to 2022-12-31 (already passed)
2% built per the latest filing
4 RERA complaints on this project (0 open); 74 on the promoter overall
No litigation declared in RERA filings
RERA file · Registration
Complaint log (K-RERA) · 4 on this project
- Jan 2020Reimbursement of dues and completion & possession of the propertydisposed
- Jan 2020Reimbursement of dues and completion & possession of the propertydisposed
- Jan 2020Reimbursement of dues and completion & possession of the propertydisposed
- May 2019Inordinate delay in completion of project and handing over possession - Refund Requestdisposed
Red flags to resolve in writing
RERA completion date 2022-12-31 has passed without a completion application.
Questions to put to the developer before you sign
- Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
- Confirm the price list, floor-rise and other charges for the exact unit.
- Which date is contractual — 2022-12-31 — and what is the per-month delay compensation?
- Confirm there is no litigation on the land or approvals beyond the RERA declaration.
- Is the land freehold with the developer, and is any part mortgaged?
Full record: every filed number, line by line2 sections · 13 items
RERA file · Registration
Source: Karnataka RERA project record PRM/KA/RERA/1251/446/PR/170916/000224, fetched 2026-09-15. Figures are the promoter’s own filings.
Complaint log (K-RERA) · 4 on this project
Complaint subjects are as filed by complainants; a disposed complaint may have been decided either way.
Sources & caveats2 sources
- Karnataka RERA project record PRM/KA/RERA/1251/446/PR/170916/000224 (registration file, quarterly updates, complaint register), fetched 2026-09-15
- PropertyLens locality model (market-level estimates)
- Karnataka RERA project records PRM/KA/RERA/1251/446/PR/170916/000224 (registration file, quarterly updates, complaint register), fetched Sep 2026.
Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.