Financial & legal due diligence · public record · 18 Oct 2026

Northern Lights by Puravankara KVN Phase 3

Puravankara · Devanahalli / Airport Road / Bagalur · Plot No. R-12 of Hitech, Defense and Aerospace Park, Bengaluru Comprised in Sy No. Part of 417,418,419,423,389,390,391,392,393 & 117 , Bagalur Village Jala Hobli, Bengaluru North Yelahanka Taluk, Bengaluru Urban District

Promoter entityKVN Property Holdings LLP
Entity type · PANPartnership Firm · AAUFK9764H
Developer brandPuravankara · #8 in Bengaluru by RERA registrations
RERA registrationsRegistration: PRM/KA/RERA/1251/309/PR/120326/008525
Planning authorityKIADB - Karnataka Industrial Areas Development Board
Sanctioned planDO3-KIADB-00190/25-26/BP · 2026-03-07
Escrow bankHDFC, Ulsoor Road Branch
Land6.3 acres · 2 land owners on record
Court cases declared0
Complaints at K-RERA0 on this project · 0 on the promoter
Record fetchedSep 2026
0 red flags1 to watch6 positive

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/120326/008525. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.

Financial & legal due diligence

What the public record says

Automated from the Karnataka RERA file PRM/KA/RERA/1251/309/PR/120326/008525. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.

0 red1 watch6 positive
Delivery timeline9/10
no extensions, no overdue dates on the RERA file
Legal & complaints9/10
no litigation and no complaints on the RERA file
Money to finish8/10
finance cost is 0% of the registered budget
Developer strength7.6/10
ICRA A-/Stable (Puravankara Ltd)

Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.

Registration
PRM/KA/RERA/1251/309/PR/120326/008525 · KVN Property Holdings LLP
On original date
TodaySep 2026RegisteredApr 2027Original completionDec 2031
No litigation declaredNo complaintsEscrow: HDFCJoint-development land
Credit ratings of the people behind it
AAAAAABBBBBBCDinvestment grade ◀▶ speculative gradeICRA A- / Stable · Puravankara Ltd · May 2025
Complaints & disputes on record
On this project00 open
On the promoter entity0all projects
Court cases declared0no stay recorded
At a glance
On its original RERA date

On its original RERA completion date: 2031-12-31

No complaints on this project

No RERA complaints on this project; 0 on the promoter overall

No litigation declared

No litigation declared in RERA filings

The record, in pictures

RERA file · Registration

Registered project cost ₹465 cr — where it goes
Land ₹0 cr · 0%Approvals ₹16.2 cr · 3%Construction & on-site ₹403.9 cr · 87%Other / taxes ₹44.8 cr · 10%
No litigation declaredBorrowing declared: NoEscrow at HDFC2 recorded land-owner shares

Red flags to resolve in writing

1
Legal

Joint-development land: confirm which units fall in the owners’ share.

Questions to put to the developer before you sign

  1. Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
  2. Confirm the price list, floor-rise and other charges for the exact unit.
  3. Which date is contractual — 2031-12-31 — and what is the per-month delay compensation?
  4. Confirm there is no litigation on the land or approvals beyond the RERA declaration.
  5. What is the land owners’ share of built area and is the unit in the developer’s share?
Full record: every filed number, line by line1 sections · 11 items

RERA file · Registration

Registration
PRM/KA/RERA/1251/309/PR/120326/008525 · promoter KVN Property Holdings LLP (Partnership Firm) · ACN-5553
Dates
Start 2027-04-15 · original completion 2031-12-31 · no extensions
Registered cost
Total ₹465 cr · land ₹0.00 cr · construction ₹404 cr
Borrowing / mortgage declared
Borrowing: No
RERA bank account
HDFC, Ulsoor Road Branch (70% construction account)
Plan sanction
DO3-KIADB-00190/25-26/BP dated 2026-03-07 · KIADB - Karnataka Industrial Areas Development Board
Land & towers
6.30 acres (25,476 sq m) · Wing 6 270 homes, 30 floors; Wing 7 270 homes, 30 floors
Land owners / co-promoters
EWS (100%, Sy 745); No. of Basement (1%, Sy Total No. of Parking)
Litigation declared
None declared in filings
K-RERA complaints
0 on this registration (0 open) · 0 on the promoter entity across all its projects (a project-specific LLP; group-level complaints sit under other entities)
Completion applied
19/12/2020

Source: Karnataka RERA project record PRM/KA/RERA/1251/309/PR/120326/008525, fetched 2026-09-15. Figures are the promoter’s own filings.

Sources & caveats2 sources
  • Karnataka RERA project record PRM/KA/RERA/1251/309/PR/120326/008525 (registration file, quarterly updates, complaint register), fetched 2026-09-15
  • PropertyLens locality model (market-level estimates)
  • Karnataka RERA project records PRM/KA/RERA/1251/309/PR/120326/008525 (registration file, quarterly updates, complaint register), fetched Sep 2026.

Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.

PropertyLens · property-lens.ai · Facts are transcribed from public records as filed by the promoter and the regulator; figures on RERA certificates are promoter numbers certified on unaudited books. Absence of a court case or insolvency filing in these sources is not proof that none exists. Verify title, approvals and encumbrances with a lawyer before you sign. Nothing here is legal, tax or investment advice.