Financial & legal due diligence · public record · 18 Oct 2026

Sumadhura Capitol Towers

Sumadhura · Whitefield (Hoodi / Varthur Road) · KATHA NO 2890 & 2891 SY NO 14 & 158 , PATTANDURU AGRAHARA VILLAGE K R PURAM HOBLI

Promoter entitySUMADHURA CAPITOL TOWERS PRIVATE LIMITED
Entity type · PANCompany · ABBCS1265Q
Developer brandSumadhura · #10 in Bengaluru by RERA registrations
RERA registrationsRegistration: PRM/KA/RERA/1251/446/PR/200226/003304
Planning authorityBBMP - Bruhat Bengaluru Mahanagara Palike
Sanctioned plannot filed
Escrow bankHDFC, RICHMOND ROAD
Land8.67 acres
Court cases declared0
Complaints at K-RERA0 on this project · 0 on the promoter
Record fetchedSep 2026
2 red flags0 to watch4 positive

Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/200226/003304. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.

Financial & legal due diligence

What the public record says

Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/200226/003304. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.

2 red0 watch4 positive
Delivery timeline5/10
1 extension on the registration (−2); a registration completion date has already passed (−2)
Legal & complaints9/10
no litigation and no complaints on the RERA file
Money to finish8/10
finance cost is 0% of the registered budget
Developer strength6.5/10
CRISIL BBB+/Stable (Sumadhura Infracon)

Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.

Registration
PRM/KA/RERA/1251/446/PR/200226/003304 · SUMADHURA CAPITOL TOWERS PRIVATE LIMITED
Past RERA date
RegisteredOct 2019Original completionJun 2022Section 6 ext.Mar 2024TodaySep 2026
Construction7%
registration-time status
Collected (at registration)₹15.00 Cr
Spent₹181.33 Cr
Balance with promoter₹0
Delay declaredNoNOT APPLICABLE
No litigation declaredNo complaintsEscrow: HDFC
Credit ratings of the people behind it
AAAAAABBBBBBCDinvestment grade ◀▶ speculative gradeCRISIL BBB+ / Stable · Sumadhura Infracon · May 2025
Complaints & disputes on record
On this project00 open
On the promoter entity0all projects
Court cases declared0no stay recorded
At a glance
Registration extended 1×

Registration extended 1× — from 2022-06-30 to 2024-03-30 (already passed)

7% built

7% built per the latest filing

No complaints on this project

No RERA complaints on this project; 0 on the promoter overall

No litigation declared

No litigation declared in RERA filings

The record, in pictures

RERA file · Registration

Registered project cost ₹713 cr — where it goes
Land ₹142.8 cr · 20%Construction & on-site ₹570.1 cr · 80%
No litigation declaredBorrowing declared: not statedEscrow at HDFC

Red flags to resolve in writing

1
Timeline

RERA completion date 2024-03-30 has passed without a completion application.

Questions to put to the developer before you sign

  1. Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
  2. Confirm the price list, floor-rise and other charges for the exact unit.
  3. Which date is contractual — 2024-03-30 — and what is the per-month delay compensation?
  4. Confirm there is no litigation on the land or approvals beyond the RERA declaration.
  5. Is the land freehold with the developer, and is any part mortgaged?
Full record: every filed number, line by line1 sections · 9 items

RERA file · Registration

Registration
PRM/KA/RERA/1251/446/PR/200226/003304 · promoter SUMADHURA CAPITOL TOWERS PRIVATE LIMITED (Company) · EX/PRM/KA/RERA/1251/446/PR/230307/003304
Dates
Start 2019-10-22 · original completion 2022-06-30 · 1 extension: Section 6 Extension → 2024-03-30 · current date has passed
Progress
7% complete per registration-time status
Registered cost
Total ₹713 cr · land ₹143 cr · construction ₹570 cr
RERA bank account
HDFC, RICHMOND ROAD (70% construction account)
Money at registration
collected ₹15.00 cr · spent ₹408 cr · balance ₹393 cr · delay declared: No (NOT APPLICABLE)
Land & towers
8.67 acres (35,106 sq m) · TOWER-1 12 homes, 11 floors; TOWER-2 12 homes, 11 floors
Litigation declared
None declared in filings
K-RERA complaints
0 on this registration (0 open) · 0 on the promoter entity across all its projects

Source: Karnataka RERA project record PRM/KA/RERA/1251/446/PR/200226/003304, fetched 2026-09-15. Figures are the promoter’s own filings.

Sources & caveats2 sources
  • Karnataka RERA project record PRM/KA/RERA/1251/446/PR/200226/003304 (registration file, quarterly updates, complaint register), fetched 2026-09-15
  • PropertyLens locality model (market-level estimates)
  • Karnataka RERA project records PRM/KA/RERA/1251/446/PR/200226/003304 (registration file, quarterly updates, complaint register), fetched Sep 2026.

Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.

PropertyLens · property-lens.ai · Facts are transcribed from public records as filed by the promoter and the regulator; figures on RERA certificates are promoter numbers certified on unaudited books. Absence of a court case or insolvency filing in these sources is not proof that none exists. Verify title, approvals and encumbrances with a lawyer before you sign. Nothing here is legal, tax or investment advice.