Is Adani M2k Projects a reliable builder?
4 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Adani M2k Projects in one paragraph
Adani M2k Projects has a mixed delivery record in Haryana RERA (Gurugram) filings: 69% of registrations needed no extension (3 of 4 analysed Gurugram registrations needed no extension (1 lapsed)). 3 of 3 under-construction projects are past their original RERA completion date, by 10 months on average (worst 25). The median Adani M2k Projects project scores 56/100 on investment merit (above the Gurugram average); the best, Oyster Greens, scores 67.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Oyster Grande-Tower G Dwarka Expressway | 25 | 0 | 100% of schedule · — | 0 | 41 |
| Oyster Greens Old Gurugram, DLF Phases and Palam Vihar | 3 | 0 | 100% of schedule · — | 0 | 67 |
| Oyster Greens Dwarka Expressway | 3 | 0 | 100% of schedule · — | 0 | 56 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Adani M2k Projects projects
All 4 analysed Adani M2k Projects projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Oyster Greens Adani M2k Projects · Old Gurugram, DLF Phases and Palam Vihar | 67 | 10.3% | 5.6% | 7.9% | ₹7,100 est. | ₹53.6 L | Under construction Aug 2026 |
| Oyster Greens Adani M2k Projects · Dwarka Expressway | 56 | 9.6% | 5.3% | 7.5% | ₹6,100 est. | ₹18.0 L | Under construction Aug 2026 |
| Group Housing Colony Adani M2k Projects · Dwarka Expressway | 51 | 7.7% | 4.0% | 5.3% | ₹11,800 est. | ₹1.74 Cr | Ready |
| Oyster Grande-Tower G Adani M2k Projects · Dwarka Expressway | 41 | 8.1% | 3.3% | 4.3% | ₹11,100 est. | ₹1.28 Cr | Under construction Sep 2024 |
Where Adani M2k Projects builds
Questions people ask
Is Adani M2k Projects a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 69% of registrations needed no extension; 3 of 3 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Adani M2k Projects project is the best investment?
Oyster Greens in Old Gurugram, DLF Phases and Palam Vihar scores highest at 67/100 with projected growth 10.3% a year and cash-flow IRR 7.9%. The median Adani M2k Projects project scores 56.
Is Adani M2k Projects delaying possession?
3 under-construction Adani M2k Projects projects are past their original RERA completion date: Oyster Grande-Tower G (25 months), Oyster Greens (3 months), Oyster Greens (3 months). Extensions filed with RERA are listed on each project page.
Where does Adani M2k Projects build?
Dwarka Expressway, Gurugram (3), Old Gurugram, DLF Phases and Palam Vihar, Gurugram (1). Median price ₹11,100 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.