Is Alton Buildtech India a reliable builder?
3 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Alton Buildtech India in one paragraph
Alton Buildtech India has a mixed delivery record in Haryana RERA (Gurugram) filings: 63% of registrations needed no extension (2 of 3 analysed Gurugram registrations needed no extension (1 lapsed)). 1 of 2 under-construction projects are past their original RERA completion date, by 47 months on average (worst 47). The median Alton Buildtech India project scores 51/100 on investment merit (below the Gurugram average); the best, Tatva Estates, scores 60.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Aangan New Gurugram | 47 | 0 | 100% of schedule · — | 0 | 36 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Alton Buildtech India projects
All 3 analysed Alton Buildtech India projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Tatva Estates Alton Buildtech India · Dwarka Expressway | 60 | 10.0% | 6.5% | 10.4% | ₹6,100 est. | ₹76.9 L | Under construction Dec 2027 |
| Aangan Alton Buildtech India · Dwarka Expressway | 51 | 7.7% | 4.2% | 5.5% | ₹11,800 est. | ₹1.36 Cr | Ready |
| Aangan Alton Buildtech India · New Gurugram | 36 | 7.8% | 2.2% | 2.9% | ₹8,000 est. | ₹92.0 L | Under construction Dec 2022 |
Where Alton Buildtech India builds
Questions people ask
Is Alton Buildtech India a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 63% of registrations needed no extension; 1 of 2 under-construction projects are past their original completion date by 47 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Alton Buildtech India project is the best investment?
Tatva Estates in Dwarka Expressway scores highest at 60/100 with projected growth 10.0% a year and cash-flow IRR 10.4%. The median Alton Buildtech India project scores 51.
Is Alton Buildtech India delaying possession?
1 under-construction Alton Buildtech India projects are past their original RERA completion date: Aangan (47 months). Extensions filed with RERA are listed on each project page.
Where does Alton Buildtech India build?
Dwarka Expressway, Gurugram (2), New Gurugram, Gurugram (1). Median price ₹8,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.