Is Arihant Foundations & Housing a reliable builder?
8 projects analysed in Chennai from Tamil Nadu RERA filings, as of September 11, 2026.
Arihant Foundations & Housing in one paragraph
Arihant Foundations & Housing has a strong delivery record in Tamil Nadu RERA filings: 89% of registrations needed no extension (8 of 8 analysed Chennai registrations needed no extension). 5 of 8 under-construction projects are past their original RERA completion date, by 41 months on average (worst 69). The median Arihant Foundations & Housing project scores 54/100 on investment merit (below the Chennai average); the best, Arihant Melange, scores 68.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Chennai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Arihant Shri Niketan Central Chennai | 69 | 0 | 100% of schedule · — | 0 | 45 |
| Project Name changed from "Arihant Vairat" to "Arihant Vinyasa" - Construction o Central Chennai | 67 | 0 | 100% of schedule · — | 0 | 45 |
| Arihant Vanya Vilas Perambur / Kolathur / Villivakkam / Madhavaram | 31 | 0 | 100% of schedule · — | 0 | 39 |
| Arihant Vista T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar | 23 | 0 | 100% of schedule · — | 0 | 54 |
| Arihant Vipassana T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar | 15 | 0 | 100% of schedule · — | 0 | 53 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Arihant Foundations & Housing projects
All 8 analysed Arihant Foundations & Housing projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Arihant Melange Arihant Foundations & Housing · T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar | 68 | 7.9% | 2.9% | 4.2% | ₹11,100 est. | ₹1.18 Cr | Under construction Mar 2028 |
| Arihant Vivriti Arihant Foundations & Housing · Adyar / Besant Nagar / Thiruvanmiyur / Kotturpuram | 64 | 7.5% | 2.8% | 4.1% | ₹13,550 est. | ₹1.73 Cr | Under construction Dec 2027 |
| Arihant Vivriti Arihant Foundations & Housing · Adyar / Besant Nagar / Thiruvanmiyur / Kotturpuram | 64 | 7.5% | 2.8% | 4.1% | ₹13,550 est. | ₹1.73 Cr | Under construction Dec 2027 |
| Arihant Vista Arihant Foundations & Housing · T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar | 54 | 7.5% | 2.3% | 3.0% | ₹11,100 est. | ₹1.18 Cr | Under construction Nov 2024 |
| Arihant Vipassana Arihant Foundations & Housing · T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar | 53 | 7.5% | 2.3% | 3.0% | ₹11,100 est. | ₹1.18 Cr | Under construction Jul 2025 |
| Arihant Shri Niketan Arihant Foundations & Housing · Central Chennai | 45 | 6.3% | 1.6% | 2.0% | ₹16,450 est. | ₹1.75 Cr | Under construction Jan 2021 |
| Project Name changed from "Arihant Vairat" to "Arihant Vinyasa" - Construction o Arihant Foundations & Housing · Central Chennai | 45 | 6.3% | 1.6% | 2.0% | ₹16,450 est. | ₹1.75 Cr | Under construction Mar 2021 |
| Arihant Vanya Vilas Arihant Foundations & Housing · Perambur / Kolathur / Villivakkam / Madhavaram | 39 | 7.1% | 0.8% | 1.0% | ₹6,100 est. | ₹65.0 L | Under construction Mar 2024 |
Where Arihant Foundations & Housing builds
Questions people ask
Is Arihant Foundations & Housing a reliable builder?
Tamil Nadu RERA filings as of September 11, 2026: 89% of registrations needed no extension; 5 of 8 under-construction projects are past their original completion date by 41 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Arihant Foundations & Housing project is the best investment?
Arihant Melange in T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar scores highest at 68/100 with projected growth 7.9% a year and cash-flow IRR 4.2%. The median Arihant Foundations & Housing project scores 54.
Is Arihant Foundations & Housing delaying possession?
5 under-construction Arihant Foundations & Housing projects are past their original RERA completion date: Arihant Shri Niketan (69 months), Project Name changed from "Arihant Vairat" to "Arihant Vinyasa" - Construction o (67 months), Arihant Vanya Vilas (31 months), Arihant Vista (23 months), Arihant Vipassana (15 months). Extensions filed with RERA are listed on each project page.
Where does Arihant Foundations & Housing build?
T Nagar / Kodambakkam / Vadapalani / KK Nagar / Ashok Nagar, Chennai (3), Adyar / Besant Nagar / Thiruvanmiyur / Kotturpuram, Chennai (2), Central Chennai, Chennai (2), Perambur / Kolathur / Villivakkam / Madhavaram, Chennai (1). Median price ₹13,550 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.