Developer scorecard · #134 in Mumbai by RERA registrations

Is Axiom Refab Construction India a reliable builder?

6 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Axiom Refab Construction India in one paragraph

Axiom Refab Construction India has a strong delivery record in MahaRERA filings: 87% of registrations needed no extension (6 of 6 analysed Mumbai registrations needed no extension). 1 of 6 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Axiom Refab Construction India project scores 70/100 on investment merit (well above the Mumbai average); the best, Axiom Vrindavan, scores 70.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.

Projects analysed
6
0 ready · 6 under construction
On-time rate
87%
registrations with no extension filed
Past RERA date
1 / 6
avg 10 months over
Extensions filed
0
0 projects
Cities
1
Mumbai
Red flags
1
across due-diligence reports
Median score
70
best 70
Median growth / yr
8.7%
5-yr projection
Median price / sq ft
₹16,850
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Axiom Capitol
Mulund / Bhandup / Kanjurmarg
100100% of schedule · —055

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Axiom Refab Construction India projects

All 6 analysed Axiom Refab Construction India projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Axiom Vrindavan
Axiom Refab Construction India · Mulund / Bhandup / Kanjurmarg
708.7%5.1%8.5%₹16,850 est.₹1.10 CrUnder construction
Mar 2030
Axiom Vriksh
Axiom Refab Construction India · Mulund / Bhandup / Kanjurmarg
708.7%5.3%8.7%₹16,850 est.₹1.10 CrUnder construction
Nov 2029
Axiom Gloria
Axiom Refab Construction India · Mulund / Bhandup / Kanjurmarg
708.7%5.1%8.5%₹16,850 est.₹1.10 CrUnder construction
Mar 2030
Axiom Rudra
Axiom Refab Construction India · Goregaon / Malad
698.3%4.5%7.6%₹17,100 est.₹1.11 CrUnder construction
Mar 2030
Axiom Gurubhakti
Axiom Refab Construction India · Mulund / Bhandup / Kanjurmarg
668.3%4.8%7.5%₹16,850 est.₹1.10 CrUnder construction
Oct 2028
Axiom Capitol
Axiom Refab Construction India · Mulund / Bhandup / Kanjurmarg
557.5%3.6%4.6%₹16,850 est.₹1.10 CrUnder construction
Dec 2025

Where Axiom Refab Construction India builds

Questions people ask

Is Axiom Refab Construction India a reliable builder?

MahaRERA filings as of September 11, 2026: 87% of registrations needed no extension; 1 of 6 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Axiom Refab Construction India project is the best investment?

Axiom Vrindavan in Mulund / Bhandup / Kanjurmarg scores highest at 70/100 with projected growth 8.7% a year and cash-flow IRR 8.5%. The median Axiom Refab Construction India project scores 70.

Is Axiom Refab Construction India delaying possession?

1 under-construction Axiom Refab Construction India projects are past their original RERA completion date: Axiom Capitol (10 months). Extensions filed with RERA are listed on each project page.

Where does Axiom Refab Construction India build?

Mulund / Bhandup / Kanjurmarg, Mumbai (5), Goregaon / Malad, Mumbai (1). Median price ₹16,850 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.

Share on WhatsApp