Datar Engineering And Consultancy in one paragraph
Datar Engineering And Consultancy has a strong delivery record in MahaRERA filings: 83% of registrations needed no extension (4 of 4 analysed Pune registrations needed no extension). 2 of 4 under-construction projects are past their original RERA completion date, by 3 months on average (worst 5). The median Datar Engineering And Consultancy project scores 64/100 on investment merit (above the Pune average); the best, Sudarshan, scores 68.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Pune; compare the rate with other developers below.
Projects past their original RERA date
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Datar Engineering And Consultancy projects
All 4 analysed Datar Engineering And Consultancy projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Sudarshan Datar Engineering And Consultancy · Central Pune | 68 | 9.6% | 6.0% | 9.8% | ₹11,750 est. | ₹88.1 L | Under construction Dec 2029 |
| Bhavik Datar Engineering And Consultancy · Central Pune | 64 | 8.4% | 4.3% | 5.6% | ₹11,750 est. | ₹88.1 L | Under construction Dec 2026 |
| Trimurti Datar Engineering And Consultancy · Central Pune | 63 | 8.4% | 4.4% | 5.6% | ₹11,750 est. | ₹88.1 L | Under construction Sep 2026 |
| Gangotri Datar Engineering And Consultancy · Central Pune | 56 | 8.4% | 4.4% | 5.6% | ₹11,750 est. | ₹88.1 L | Under construction May 2026 |
Where Datar Engineering And Consultancy builds
Questions people ask
Is Datar Engineering And Consultancy a reliable builder?
MahaRERA filings as of September 11, 2026: 83% of registrations needed no extension; 2 of 4 under-construction projects are past their original completion date by 3 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Datar Engineering And Consultancy project is the best investment?
Sudarshan in Central Pune scores highest at 68/100 with projected growth 9.6% a year and cash-flow IRR 9.8%. The median Datar Engineering And Consultancy project scores 64.
Is Datar Engineering And Consultancy delaying possession?
2 under-construction Datar Engineering And Consultancy projects are past their original RERA completion date: Gangotri (5 months), Trimurti (1 months). Extensions filed with RERA are listed on each project page.
Where does Datar Engineering And Consultancy build?
Central Pune, Pune (4). Median price ₹11,750 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.