Is Gulabrao Baburao Karanjule Patil a reliable builder?
6 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Gulabrao Baburao Karanjule Patil in one paragraph
Gulabrao Baburao Karanjule Patil has a strong delivery record in MahaRERA filings: 87% of registrations needed no extension (6 of 6 analysed Mumbai registrations needed no extension). 1 of 6 under-construction projects are past their original RERA completion date, by 5 months on average (worst 5). The median Gulabrao Baburao Karanjule Patil project scores 33/100 on investment merit (well below the Mumbai average); the best, Vishwajeet Town, scores 49.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Vishwajeet Empire Ambernath / Badlapur | 5 | 0 | 100% of schedule · — | 0 | 24 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Gulabrao Baburao Karanjule Patil projects
All 6 analysed Gulabrao Baburao Karanjule Patil projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Vishwajeet Town Gulabrao Baburao Karanjule Patil · Mumbai region | 49 | 7.4% | 2.4% | 3.7% | ₹9,300 est. | ₹60.5 L | Under construction Jan 2029 |
| Vishwajeet Myspace Gulabrao Baburao Karanjule Patil · Ambernath / Badlapur | 36 | 8.1% | 1.6% | 2.8% | ₹4,600 est. | ₹29.9 L | Under construction Mar 2030 |
| Vishwajeet Umit Gulabrao Baburao Karanjule Patil · Ambernath / Badlapur | 33 | 7.7% | 0.8% | 1.2% | ₹4,600 est. | ₹29.9 L | Under construction Aug 2029 |
| Vishwajeet Prime Gulabrao Baburao Karanjule Patil · Ambernath / Badlapur | 32 | 7.3% | 0.3% | 0.4% | ₹4,600 est. | ₹29.9 L | Under construction Jun 2028 |
| Vishwajeet Heritage Gulabrao Baburao Karanjule Patil · Ambernath / Badlapur | 32 | 6.9% | -0.0% | -0.1% | ₹4,600 est. | ₹29.9 L | Under construction Mar 2027 |
| Vishwajeet Empire Gulabrao Baburao Karanjule Patil · Ambernath / Badlapur | 24 | 6.9% | -0.3% | -0.4% | ₹4,600 est. | ₹29.9 L | Under construction Jun 2026 |
Where Gulabrao Baburao Karanjule Patil builds
Questions people ask
Is Gulabrao Baburao Karanjule Patil a reliable builder?
MahaRERA filings as of September 11, 2026: 87% of registrations needed no extension; 1 of 6 under-construction projects are past their original completion date by 5 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Gulabrao Baburao Karanjule Patil project is the best investment?
Vishwajeet Town in Mumbai region scores highest at 49/100 with projected growth 7.4% a year and cash-flow IRR 3.7%. The median Gulabrao Baburao Karanjule Patil project scores 33.
Is Gulabrao Baburao Karanjule Patil delaying possession?
1 under-construction Gulabrao Baburao Karanjule Patil projects are past their original RERA completion date: Vishwajeet Empire (5 months). Extensions filed with RERA are listed on each project page.
Where does Gulabrao Baburao Karanjule Patil build?
Ambernath / Badlapur, Mumbai (5), Mumbai region, Mumbai (1). Median price ₹4,600 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.