Is Ishwar Reality a reliable builder?
7 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Ishwar Reality in one paragraph
Ishwar Reality has a strong delivery record in MahaRERA filings: 78% of registrations needed no extension (6 of 7 analysed Mumbai registrations needed no extension). 1 of 4 under-construction projects are past their original RERA completion date, by 4 months on average (worst 4). The median Ishwar Reality project scores 30/100 on investment merit (well below the Mumbai average); the best, Ishwar Jay Jay Shankara Co-Op. Housing Society Ltd., scores 32.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Ishwar Om Tulsi Ambernath / Badlapur | 4 | 2 | 100% of schedule · — | 0 | 18 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Ishwar Reality projects
All 7 analysed Ishwar Reality projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Ishwar Jay Jay Shankara Co-Op. Housing Society Ltd. Ishwar Reality · Ambernath / Badlapur | 32 | 7.7% | 1.1% | 1.7% | ₹4,600 est. | ₹29.9 L | Under construction Dec 2028 |
| Ishwar Haridarshan Ishwar Reality · Ambernath / Badlapur | 31 | 7.3% | 0.5% | 0.8% | ₹4,600 est. | ₹29.9 L | Under construction Dec 2027 |
| Ishwar Gajanan Ishwar Reality · Ambernath / Badlapur | 31 | 7.3% | 0.5% | 0.8% | ₹4,600 est. | ₹29.9 L | Under construction Dec 2027 |
| Ishwar Bliss Ishwar Reality · Ambernath / Badlapur | 30 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
| Ishwar Yog Surabhi Ishwar Reality · Ambernath / Badlapur | 30 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
| Ishwar Saraswati Palace Ishwar Reality · Ambernath / Badlapur | 30 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
| Ishwar Om Tulsi Ishwar Reality · Ambernath / Badlapur | 18 | 6.9% | -0.3% | -0.4% | ₹4,600 est. | ₹29.9 L | Under construction Jun 2026 |
Where Ishwar Reality builds
Questions people ask
Is Ishwar Reality a reliable builder?
MahaRERA filings as of September 11, 2026: 78% of registrations needed no extension; 1 of 4 under-construction projects are past their original completion date by 4 months on average; 2 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Ishwar Reality project is the best investment?
Ishwar Jay Jay Shankara Co-Op. Housing Society Ltd. in Ambernath / Badlapur scores highest at 32/100 with projected growth 7.7% a year and cash-flow IRR 1.7%. The median Ishwar Reality project scores 30.
Is Ishwar Reality delaying possession?
1 under-construction Ishwar Reality projects are past their original RERA completion date: Ishwar Om Tulsi (4 months). Extensions filed with RERA are listed on each project page.
Where does Ishwar Reality build?
Ambernath / Badlapur, Mumbai (7). Median price ₹4,600 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.