Is Logix a reliable builder?
13 projects analysed in Noida from UP RERA filings, as of September 11, 2026.
Logix in one paragraph
Logix has a strong delivery record in UP RERA filings: 93% of registrations needed no extension (13 of 13 analysed Noida registrations needed no extension). 1 of 1 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Logix project scores 63/100 on investment merit (above the Noida average); the best, Blossom Greens (Phase-2 Tower- H, I &j), scores 63.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Noida; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Ace Estate Yamuna Expressway | 10 | 0 | 100% of schedule · — | 0 | 19 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Logix projects
All 13 analysed Logix projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Blossom Greens (Phase-2 Tower- H, I &j) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Greens (Phase-3 Tower A , K & Club House) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Greens ( Phase- 4 Towers - E , F & G) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Greens ( Phase- 5 Towers - B , C & D ) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Zest (Phase 2 Tower- D,e,f & Club) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Zest(Phase -3 Tower- Sat- 3,4,&7) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Zest(Phase- 4,tower- Sat-8,9 &10) Logix · Noida Expressway | 63 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom County(Phase-3tower-J1, K ,n & Club ) Logix · Noida Expressway | 62 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom Zest (Phase -1 Tower- A ,b,c,& Sat-1 &2 ) Logix · Noida Expressway | 62 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Victory Ace Logix · Noida Expressway | 60 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Neoworld ( Phase-1 Tower-D, E &f) Logix · Noida Expressway | 60 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Blossom County ( Phase-4 Tower -L,m,a & C) Logix · Noida Expressway | 60 | 7.9% | 3.6% | 4.7% | ₹8,100 est. | ₹89.5 L | Ready |
| Ace Estate Logix · Yamuna Expressway | 19 | 7.8% | 0.5% | 0.7% | ₹4,500 est. | ₹49.7 L | Under construction Dec 2025 |
Where Logix builds
Logix compared with other developers
Questions people ask
Is Logix a reliable builder?
UP RERA filings as of September 11, 2026: 93% of registrations needed no extension; 1 of 1 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Logix project is the best investment?
Blossom Greens (Phase-2 Tower- H, I &j) in Noida Expressway scores highest at 63/100 with projected growth 7.9% a year and cash-flow IRR 4.7%. The median Logix project scores 63.
Is Logix delaying possession?
1 under-construction Logix projects are past their original RERA completion date: Ace Estate (10 months). Extensions filed with RERA are listed on each project page.
Where does Logix build?
Noida Expressway, Noida (12), Yamuna Expressway, Noida (1). Median price ₹8,100 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.