Developer scorecard · #100 in Mumbai by RERA registrations

Is Maverick Realtors a reliable builder?

7 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Maverick Realtors in one paragraph

Maverick Realtors has a weak delivery record in MahaRERA filings: 38% of registrations needed no extension (2 of 7 analysed Mumbai registrations needed no extension). 1 of 5 under-construction projects are past their original RERA completion date, by 4 months on average (worst 4). The median Maverick Realtors project scores 55/100 on investment merit (below the Mumbai average); the best, Nami CHS Ltd, scores 59.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.

Projects analysed
7
2 ready · 5 under construction
On-time rate
38%
registrations with no extension filed
Past RERA date
1 / 5
avg 4 months over
Extensions filed
17
5 projects
Cities
1
Mumbai
Red flags
6
across due-diligence reports
Median score
55
best 59
Median growth / yr
7.5%
5-yr projection
Median price / sq ft
₹16,850
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Maverick Mooldeep
Mulund / Bhandup / Kanjurmarg
43100% of schedule · —047

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Maverick Realtors projects

All 7 analysed Maverick Realtors projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Nami CHS Ltd
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
597.1%4.3%5.6%₹17,900 est.₹1.16 CrReady
Neelkanth Tirth Co. Op. Housing Soc. Ltd.
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
597.1%4.3%5.6%₹17,900 est.₹1.16 CrReady
Old Hemant Villa Co. Op. Housing Soc. Ltd.
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
557.5%3.5%4.6%₹16,850 est.₹1.10 CrUnder construction
Nov 2026
N And G Co Op Housing Soc Ltd
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
557.5%3.5%4.6%₹16,850 est.₹1.10 CrUnder construction
Nov 2026
Mulund Mahavirdham Co. Op. Housing Soc. Ltd.
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
557.5%3.5%4.6%₹16,850 est.₹1.10 CrUnder construction
Nov 2026
Om Sakthi Co.op.hsg.soc.ltd
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
537.5%3.4%4.9%₹16,850 est.₹1.10 CrUnder construction
Sep 2027
Maverick Mooldeep
Maverick Realtors · Mulund / Bhandup / Kanjurmarg
477.5%3.6%4.6%₹16,850 est.₹1.10 CrUnder construction
Jun 2026

Where Maverick Realtors builds

Questions people ask

Is Maverick Realtors a reliable builder?

MahaRERA filings as of September 11, 2026: 38% of registrations needed no extension; 1 of 5 under-construction projects are past their original completion date by 4 months on average; 17 extensions filed across 5 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Maverick Realtors project is the best investment?

Nami CHS Ltd in Mulund / Bhandup / Kanjurmarg scores highest at 59/100 with projected growth 7.1% a year and cash-flow IRR 5.6%. The median Maverick Realtors project scores 55.

Is Maverick Realtors delaying possession?

1 under-construction Maverick Realtors projects are past their original RERA completion date: Maverick Mooldeep (4 months). Extensions filed with RERA are listed on each project page.

Where does Maverick Realtors build?

Mulund / Bhandup / Kanjurmarg, Mumbai (7). Median price ₹16,850 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.