Is Orris Infrastructure a reliable builder?
4 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Orris Infrastructure in one paragraph
Orris Infrastructure has a weak delivery record in Haryana RERA (Gurugram) filings: 11% of registrations needed no extension (-1 of 4 analysed Gurugram registrations needed no extension (4 lapsed)). 4 of 4 under-construction projects are past their original RERA completion date, by 36 months on average (worst 70). The median Orris Infrastructure project scores 29/100 on investment merit (well below the Gurugram average); the best, Orris Gateway, scores 38.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Greenopolis New Gurugram | 70 | 0 | 100% of schedule · — | 0 | 29 |
| Woodview Residencies New Gurugram | 40 | 0 | 100% of schedule · — | 0 | 29 |
| Orris Gateway New Gurugram | 22 | 1 | 100% of schedule · — | 0 | 38 |
| Aster Court Premier New Gurugram | 10 | 0 | 100% of schedule · — | 0 | 29 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Orris Infrastructure projects
All 4 analysed Orris Infrastructure projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Orris Gateway Orris Infrastructure · New Gurugram | 38 | 9.3% | 4.9% | 7.0% | ₹4,400 est. | ₹29.3 L | Under construction Dec 2024 |
| Greenopolis Orris Infrastructure · New Gurugram | 29 | 7.8% | 2.2% | 2.9% | ₹8,000 est. | ₹92.0 L | Under construction Dec 2020 |
| Aster Court Premier Orris Infrastructure · New Gurugram | 29 | 7.8% | 2.2% | 2.9% | ₹8,000 est. | ₹92.0 L | Under construction Dec 2025 |
| Woodview Residencies Orris Infrastructure · New Gurugram | 29 | 7.8% | 2.2% | 2.9% | ₹8,000 est. | ₹92.0 L | Under construction Jul 2023 |
Where Orris Infrastructure builds
Questions people ask
Is Orris Infrastructure a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 11% of registrations needed no extension; 4 of 4 under-construction projects are past their original completion date by 36 months on average; 1 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Orris Infrastructure project is the best investment?
Orris Gateway in New Gurugram scores highest at 38/100 with projected growth 9.3% a year and cash-flow IRR 7.0%. The median Orris Infrastructure project scores 29.
Is Orris Infrastructure delaying possession?
4 under-construction Orris Infrastructure projects are past their original RERA completion date: Greenopolis (70 months), Woodview Residencies (40 months), Orris Gateway (22 months), Aster Court Premier (10 months). Extensions filed with RERA are listed on each project page.
Where does Orris Infrastructure build?
New Gurugram, Gurugram (4). Median price ₹8,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.