Is Pashmina a reliable builder?
2 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Pashmina in one paragraph
Pashmina has a mixed delivery record in Karnataka RERA filings: 60% of registrations needed no extension (too few registrations crawled to derive). 1 of 1 under-construction projects are past their original RERA completion date, by 51 months on average (worst 51). The promoter entity carries 79 complaints at K-RERA across its projects. The median Pashmina project scores 54/100 on investment merit (below the Bengaluru average); the best, Pashmina Waterfront -Phase-I, scores 54.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Pashmina Brookwoods Hoskote / Budigere Cross / Old Madras Road | 51 | 1 | 100% of schedule · — | 79 | 43 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Pashmina projects
All 2 analysed Pashmina projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Pashmina Waterfront -Phase-I Pashmina · KR Puram / Mahadevapura / Hoskote Road | 54 | 8.3% | 4.4% | 5.7% | ₹8,200 est. | ₹1.46 Cr | Ready |
| Pashmina Brookwoods Pashmina · Hoskote / Budigere Cross / Old Madras Road | 43 | 10.8% | 5.9% | 7.1% | ₹5,650 est. | ₹26.3 L | Under construction Jun 2022 |
Where Pashmina builds
Pashmina compared with other developers
Questions people ask
Is Pashmina a reliable builder?
Karnataka RERA filings as of September 11, 2026: 60% of registrations needed no extension; 1 of 1 under-construction projects are past their original completion date by 51 months on average; 1 extensions filed across 1 projects; 79 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Pashmina project is the best investment?
Pashmina Waterfront -Phase-I in KR Puram / Mahadevapura / Hoskote Road scores highest at 54/100 with projected growth 8.3% a year and cash-flow IRR 5.7%. The median Pashmina project scores 54.
Is Pashmina delaying possession?
1 under-construction Pashmina projects are past their original RERA completion date: Pashmina Brookwoods (51 months). Extensions filed with RERA are listed on each project page.
Where does Pashmina build in Bengaluru?
KR Puram / Mahadevapura / Hoskote Road (1), Hoskote / Budigere Cross / Old Madras Road (1). Median price ₹8,200 per sq ft across analysed projects.