Is Rose Building Solutions a reliable builder?
3 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Rose Building Solutions in one paragraph
Rose Building Solutions has a weak delivery record in Haryana RERA (Gurugram) filings: 30% of registrations needed no extension (0 of 3 analysed Gurugram registrations needed no extension (1 lapsed)). 1 of 3 under-construction projects are past their original RERA completion date, by 8 months on average (worst 8). The median Rose Building Solutions project scores 52/100 on investment merit (below the Gurugram average); the best, Signatureglobal City 37d II, scores 53.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Signature Global City 37d II(2) Old Gurugram, DLF Phases and Palam Vihar | 8 | 0 | 100% of schedule · — | 0 | 52 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Rose Building Solutions projects
All 3 analysed Rose Building Solutions projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Signatureglobal City 37d II Rose Building Solutions · Dwarka Expressway | 53 | 9.6% | 5.2% | 7.5% | ₹6,100 est. | ₹70.2 L | Under construction Feb 2027 |
| Signature Global City 37d II(2) Rose Building Solutions · Old Gurugram, DLF Phases and Palam Vihar | 52 | 8.8% | 4.1% | 5.3% | ₹12,900 est. | ₹1.14 Cr | Under construction Feb 2026 |
| Signature Global 37d II(1) Rose Building Solutions · Dwarka Expressway | 45 | 8.1% | 3.7% | 4.9% | ₹11,100 est. | ₹67.7 L | Under construction Feb 2027 |
Where Rose Building Solutions builds
Questions people ask
Is Rose Building Solutions a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 30% of registrations needed no extension; 1 of 3 under-construction projects are past their original completion date by 8 months on average; 2 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Rose Building Solutions project is the best investment?
Signatureglobal City 37d II in Dwarka Expressway scores highest at 53/100 with projected growth 9.6% a year and cash-flow IRR 7.5%. The median Rose Building Solutions project scores 52.
Is Rose Building Solutions delaying possession?
1 under-construction Rose Building Solutions projects are past their original RERA completion date: Signature Global City 37d II(2) (8 months). Extensions filed with RERA are listed on each project page.
Where does Rose Building Solutions build?
Dwarka Expressway, Gurugram (2), Old Gurugram, DLF Phases and Palam Vihar, Gurugram (1). Median price ₹11,100 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.