Is S M Hitech Developers a reliable builder?
6 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
S M Hitech Developers in one paragraph
S M Hitech Developers has a strong delivery record in MahaRERA filings: 87% of registrations needed no extension (6 of 6 analysed Mumbai registrations needed no extension). 1 of 6 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median S M Hitech Developers project scores 60/100 on investment merit (above the Mumbai average); the best, Sm Jewel, scores 61.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Sm Hitech Tulip Kharghar / Taloja / Kamothe | 10 | 0 | 100% of schedule · — | 0 | 49 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored S M Hitech Developers projects
All 6 analysed S M Hitech Developers projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Sm Jewel S M Hitech Developers · Kharghar / Taloja / Kamothe | 61 | 9.4% | 5.2% | 8.1% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2028 |
| Imperial III S M Hitech Developers · Kharghar / Taloja / Kamothe | 61 | 9.4% | 5.2% | 8.1% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2028 |
| Sm Emerald S M Hitech Developers · Kharghar / Taloja / Kamothe | 60 | 9.0% | 4.7% | 6.9% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2027 |
| Sm Elite S M Hitech Developers · Kharghar / Taloja / Kamothe | 60 | 9.0% | 4.7% | 6.9% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2027 |
| Imperial Tower-II S M Hitech Developers · Kharghar / Taloja / Kamothe | 59 | 8.6% | 4.2% | 5.8% | ₹9,300 est. | ₹60.5 L | Under construction Mar 2027 |
| Sm Hitech Tulip S M Hitech Developers · Kharghar / Taloja / Kamothe | 49 | 8.6% | 3.9% | 5.0% | ₹9,300 est. | ₹60.5 L | Under construction Dec 2025 |
Where S M Hitech Developers builds
Questions people ask
Is S M Hitech Developers a reliable builder?
MahaRERA filings as of September 11, 2026: 87% of registrations needed no extension; 1 of 6 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which S M Hitech Developers project is the best investment?
Sm Jewel in Kharghar / Taloja / Kamothe scores highest at 61/100 with projected growth 9.4% a year and cash-flow IRR 8.1%. The median S M Hitech Developers project scores 60.
Is S M Hitech Developers delaying possession?
1 under-construction S M Hitech Developers projects are past their original RERA completion date: Sm Hitech Tulip (10 months). Extensions filed with RERA are listed on each project page.
Where does S M Hitech Developers build?
Kharghar / Taloja / Kamothe, Mumbai (6). Median price ₹9,300 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.