Is Shraddha Landmark a reliable builder?
15 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Shraddha Landmark in one paragraph
Shraddha Landmark has a mixed delivery record in MahaRERA filings: 71% of registrations needed no extension (11 of 15 analysed Mumbai registrations needed no extension). 5 of 12 under-construction projects are past their original RERA completion date, by 7 months on average (worst 10). The median Shraddha Landmark project scores 63/100 on investment merit (above the Mumbai average); the best, Bhandup Siddhivinayak CHS Ltd, scores 66.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Shraddha Privilege Ghatkopar / Vidyavihar / Vikhroli West | 10 | 0 | 100% of schedule · — | 0 | 55 |
| Shraddha Panache Ghatkopar / Vidyavihar / Vikhroli West | 10 | 0 | 100% of schedule · — | 0 | 54 |
| Shraddha Pearl Ghatkopar / Vidyavihar / Vikhroli West | 10 | 0 | 100% of schedule · — | 0 | 54 |
| Shivmangal Residency Mulund / Bhandup / Kanjurmarg | 2 | 1 | 100% of schedule · — | 0 | 54 |
| Shraddha Evoque Mulund / Bhandup / Kanjurmarg | 2 | 2 | 100% of schedule · — | 0 | 52 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Shraddha Landmark projects
All 15 analysed Shraddha Landmark projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Bhandup Siddhivinayak CHS Ltd Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 66 | 8.3% | 4.8% | 7.5% | ₹16,850 est. | ₹1.10 Cr | Under construction Oct 2028 |
| Vanita Sadan CHS Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 66 | 8.3% | 4.7% | 7.4% | ₹16,850 est. | ₹1.10 Cr | Under construction Dec 2028 |
| Shraddha Vardaan Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 65 | 7.9% | 4.3% | 6.4% | ₹16,850 est. | ₹1.10 Cr | Under construction Dec 2027 |
| Shraddha Presidency Shraddha Landmark · Ghatkopar / Vidyavihar / Vikhroli West | 65 | 7.1% | 3.0% | 4.0% | ₹19,250 est. | ₹1.25 Cr | Under construction Dec 2026 |
| Shraddha Imperia Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 64 | 7.9% | 4.0% | 5.9% | ₹16,850 est. | ₹1.10 Cr | Under construction May 2028 |
| Bhandup Sanmitra CHS Ltd Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 64 | 7.1% | 4.3% | 5.6% | ₹17,900 est. | ₹1.16 Cr | Ready |
| Shraddha Infinity Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 63 | 7.1% | 4.3% | 5.6% | ₹17,900 est. | ₹1.16 Cr | Ready |
| Shraddha Orchid Avenue Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 63 | 7.1% | 4.3% | 5.6% | ₹17,900 est. | ₹1.16 Cr | Ready |
| Shraddha Prominent Shraddha Landmark · Ghatkopar / Vidyavihar / Vikhroli West | 61 | 7.1% | 3.0% | 4.0% | ₹19,250 est. | ₹1.25 Cr | Under construction Dec 2026 |
| Shraddha Classic Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 60 | 7.5% | 3.5% | 5.0% | ₹16,850 est. | ₹1.10 Cr | Under construction Jun 2027 |
| Shraddha Privilege Shraddha Landmark · Ghatkopar / Vidyavihar / Vikhroli West | 55 | 7.1% | 3.1% | 4.1% | ₹19,250 est. | ₹1.25 Cr | Under construction Dec 2025 |
| Shraddha Panache Shraddha Landmark · Ghatkopar / Vidyavihar / Vikhroli West | 54 | 7.1% | 3.1% | 4.1% | ₹19,250 est. | ₹1.25 Cr | Under construction Dec 2025 |
| Shraddha Pearl Shraddha Landmark · Ghatkopar / Vidyavihar / Vikhroli West | 54 | 7.1% | 3.1% | 4.1% | ₹19,250 est. | ₹1.25 Cr | Under construction Dec 2025 |
| Shivmangal Residency Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 54 | 7.5% | 3.6% | 4.6% | ₹16,850 est. | ₹1.10 Cr | Under construction Aug 2026 |
| Shraddha Evoque Shraddha Landmark · Mulund / Bhandup / Kanjurmarg | 52 | 7.5% | 3.6% | 4.6% | ₹16,850 est. | ₹1.10 Cr | Under construction Aug 2026 |
Where Shraddha Landmark builds
Shraddha Landmark compared with other developers
Questions people ask
Is Shraddha Landmark a reliable builder?
MahaRERA filings as of September 11, 2026: 71% of registrations needed no extension; 5 of 12 under-construction projects are past their original completion date by 7 months on average; 5 extensions filed across 4 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Shraddha Landmark project is the best investment?
Bhandup Siddhivinayak CHS Ltd in Mulund / Bhandup / Kanjurmarg scores highest at 66/100 with projected growth 8.3% a year and cash-flow IRR 7.5%. The median Shraddha Landmark project scores 63.
Is Shraddha Landmark delaying possession?
5 under-construction Shraddha Landmark projects are past their original RERA completion date: Shraddha Privilege (10 months), Shraddha Panache (10 months), Shraddha Pearl (10 months), Shivmangal Residency (2 months), Shraddha Evoque (2 months). Extensions filed with RERA are listed on each project page.
Where does Shraddha Landmark build?
Mulund / Bhandup / Kanjurmarg, Mumbai (10), Ghatkopar / Vidyavihar / Vikhroli West, Mumbai (5). Median price ₹17,900 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.