Casagrand Boulevard
Casagrand · Hennur Road / Kothanur / Kalyan Nagar · Sy no 45,46 and 47 of Chikkagubbi village, Bidarahalli Hobli, Bengaluru, Bengaluru East Taluk, Bangalore District 560077
Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/201001/003629. Prices and rents are locality estimates, not verified listings. This report records what the Karnataka RERA file, the promoter’s quarterly filings, the complaint register, public credit ratings and company filings say. It states facts and flags them; it does not judge the investment. Prices, returns and the investment score live in the separate full report.
What the public record says
Automated from the Karnataka RERA file PRM/KA/RERA/1251/446/PR/201001/003629. Prices and rents are locality estimates, not verified listings. Compiled Sep 2026 from the Karnataka RERA file, company registers, rating agencies, tribunal records and press. Facts only; anything that deserves a written answer before signing is flagged.
Meters are rule-based from the RERA file and public ratings (rules shown under each), not opinions.
- 3 YEAR DELAY , INCOMPLETE WORK, WORK STILL NOT COMPLETE AND UNDUE CHARGE OF LATE PAYMENT
- Respondents must register the conveyance deed, as the Complainant does not wish to withdra
- Refund with interest for wrongful denial of unit allotment and failure to honour NOC and a
- (i) Unexplained delay between booking and handover of the flat (ii) Unauthorised excess co
On its original RERA completion date: 2024-12-31
29 RERA complaints on this project (5 open); 29 on the promoter overall
No litigation declared in RERA filings
RERA file · Registration
Complaint log (K-RERA) · 29 on this project
- Jun 20263 YEAR DELAY , INCOMPLETE WORK, WORK STILL NOT COMPLETE AND UNDUE CHARGE OF LATE PAYMENTopen
- Dec 2025Respondents must register the conveyance deed, as the Complainant does not wish to withdraw from the project aopen
- Oct 2025Refund with interest for wrongful denial of unit allotment and failure to honour NOC and agreement terms.open
- Sep 2025(i) Unexplained delay between booking and handover of the flat (ii) Unauthorised excess collection.n of GSTopen
- Sep 2025Interest for Delay in Possession : Builder delayed handover by 14 months and denied paying interest for delay open
- Aug 2025Interest on delay period in handing over the flat to the Allottees as per the Sale Agreement, dated 18.11.2022disposed
- Jun 2025Compensation for delay in handing over the flat to the Allottees as per the Sale Agreement, dated 9.4.2021disposed
- May 2025Interest on delay in delivering Possessiondisposed
- May 2025Delay in possession, Harassment and penaltydisposed
- Mar 2025Delay in delivery of possession of flat by 1 yeardisposed
- Feb 2025Delay in handover as per sale agreementdisposed
- Feb 2025Delay in handing over the flat to the Allottees as per the sale agreement 31.03.2022disposed
Red flags to resolve in writing
RERA completion date 2024-12-31 has passed without a completion application.
29 K-RERA complaints on this registration.
Questions to put to the developer before you sign
- Share the latest CA Form 4 and architect Form 5 with the escrow deposit ratio.
- Confirm the price list, floor-rise and other charges for the exact unit.
- Which date is contractual — 2024-12-31 — and what is the per-month delay compensation?
- Confirm there is no litigation on the land or approvals beyond the RERA declaration.
- Is the land freehold with the developer, and is any part mortgaged?
Full record: every filed number, line by line2 sections · 32 items
RERA file · Registration
Source: Karnataka RERA project record PRM/KA/RERA/1251/446/PR/201001/003629, fetched 2026-09-15. Figures are the promoter’s own filings.
Complaint log (K-RERA) · 29 on this project
Showing the latest 25 of 29.
Sources & caveats2 sources
- Karnataka RERA project record PRM/KA/RERA/1251/446/PR/201001/003629 (registration file, quarterly updates, complaint register), fetched 2026-09-15
- PropertyLens locality model (market-level estimates)
- Karnataka RERA project records PRM/KA/RERA/1251/446/PR/201001/003629 (registration file, quarterly updates, complaint register), fetched Sep 2026.
Caveats. Automated analysis: prices, rents and travel times are estimates until listings and Maps data are verified. RERA figures are the promoter’s own filings. Nothing here is legal, tax or investment advice.