Developer scorecard · #15 in Mumbai by RERA registrations

Is Agile Real Estate a reliable builder?

17 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Agile Real Estate in one paragraph

Agile Real Estate has a strong delivery record in MahaRERA filings: 94% of registrations needed no extension (17 of 17 analysed Mumbai registrations needed no extension). 8 of 17 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Agile Real Estate project scores 50/100 on investment merit (below the Mumbai average); the best, Primera, scores 63.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.

Projects analysed
17
0 ready · 17 under construction
On-time rate
94%
registrations with no extension filed
Past RERA date
8 / 17
avg 10 months over
Extensions filed
0
0 projects
Cities
1
Mumbai
Red flags
8
across due-diligence reports
Median score
50
best 63
Median growth / yr
7.9%
5-yr projection
Median price / sq ft
₹12,500
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Immensa A
Thane West
100100% of schedule · —046
Immensa B
Thane West
100100% of schedule · —046
Immensa C
Thane West
100100% of schedule · —046
Immensa D
Thane West
100100% of schedule · —046
Immensa E
Thane West
100100% of schedule · —046
Immensa F
Thane West
100100% of schedule · —046
Immensa G
Thane West
100100% of schedule · —046
Immensa H
Thane West
100100% of schedule · —046

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Agile Real Estate projects

All 17 analysed Agile Real Estate projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Primera
Agile Real Estate · Thane West
638.7%4.5%7.5%₹12,500 est.₹81.3 LUnder construction
Dec 2029
Sector B- Tower A and B
Agile Real Estate · Thane West
588.6%5.1%9.4%₹12,500 est.₹81.3 LUnder construction
Dec 2031
Estella - Tower C and D
Agile Real Estate · Thane West
578.5%4.6%8.7%₹12,500 est.₹81.3 LUnder construction
Jun 2032
Sector 5 - Wing D, E and F
Agile Real Estate · Thane West
567.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Sector 5 - Wing A
Agile Real Estate · Thane West
567.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Sector 5 - Wing B
Agile Real Estate · Thane West
567.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Sector 5 - Wing C
Agile Real Estate · Thane West
567.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Sector 5 - Wing J and K
Agile Real Estate · Thane West
567.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Sector 5 - Wing G and H
Agile Real Estate · Thane West
507.9%3.5%5.3%₹12,500 est.₹81.3 LUnder construction
Dec 2027
Immensa A
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa B
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa C
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa D
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa E
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa F
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa G
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Immensa H
Agile Real Estate · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025

Where Agile Real Estate builds

Agile Real Estate compared with other developers

Questions people ask

Is Agile Real Estate a reliable builder?

MahaRERA filings as of September 11, 2026: 94% of registrations needed no extension; 8 of 17 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Agile Real Estate project is the best investment?

Primera in Thane West scores highest at 63/100 with projected growth 8.7% a year and cash-flow IRR 7.5%. The median Agile Real Estate project scores 50.

Is Agile Real Estate delaying possession?

8 under-construction Agile Real Estate projects are past their original RERA completion date: Immensa A (10 months), Immensa B (10 months), Immensa C (10 months), Immensa D (10 months), Immensa E (10 months) and others. Extensions filed with RERA are listed on each project page.

Where does Agile Real Estate build?

Thane West, Mumbai (17). Median price ₹12,500 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.