Is Green Homes a reliable builder?
3 projects analysed in Chennai from Tamil Nadu RERA filings, as of September 11, 2026.
Green Homes in one paragraph
Green Homes has a strong delivery record in Tamil Nadu RERA filings: 80% of registrations needed no extension (3 of 3 analysed Chennai registrations needed no extension). 3 of 3 under-construction projects are past their original RERA completion date, by 34 months on average (worst 42). The median Green Homes project scores 39/100 on investment merit (well below the Chennai average); the best, Amaravathy, scores 39.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Chennai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Amaravathy Velachery / Pallikaranai / Medavakkam / Madipakkam | 42 | 0 | 100% of schedule · — | 0 | 39 |
| Green Kubera OMR IT corridor | 30 | 0 | 100% of schedule · — | 0 | 39 |
| Green Deepam Velachery / Pallikaranai / Medavakkam / Madipakkam | 30 | 0 | 100% of schedule · — | 0 | 38 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Green Homes projects
All 3 analysed Green Homes projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Amaravathy Green Homes · Velachery / Pallikaranai / Medavakkam / Madipakkam | 39 | 6.7% | 0.2% | 0.2% | ₹6,400 est. | ₹68.2 L | Under construction Apr 2023 |
| Green Kubera Green Homes · OMR IT corridor | 39 | 6.8% | 0.3% | 0.4% | ₹6,200 est. | ₹66.0 L | Under construction Apr 2024 |
| Green Deepam Green Homes · Velachery / Pallikaranai / Medavakkam / Madipakkam | 38 | 6.7% | 0.2% | 0.2% | ₹6,400 est. | ₹68.2 L | Under construction Apr 2024 |
Where Green Homes builds
Questions people ask
Is Green Homes a reliable builder?
Tamil Nadu RERA filings as of September 11, 2026: 80% of registrations needed no extension; 3 of 3 under-construction projects are past their original completion date by 34 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Green Homes project is the best investment?
Amaravathy in Velachery / Pallikaranai / Medavakkam / Madipakkam scores highest at 39/100 with projected growth 6.7% a year and cash-flow IRR 0.2%. The median Green Homes project scores 39.
Is Green Homes delaying possession?
3 under-construction Green Homes projects are past their original RERA completion date: Amaravathy (42 months), Green Kubera (30 months), Green Deepam (30 months). Extensions filed with RERA are listed on each project page.
Where does Green Homes build?
Velachery / Pallikaranai / Medavakkam / Madipakkam, Chennai (2), OMR IT corridor, Chennai (1). Median price ₹6,400 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.