Is Je And Vee Infrastructure a reliable builder?
8 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Je And Vee Infrastructure in one paragraph
Je And Vee Infrastructure has a mixed delivery record in MahaRERA filings: 62% of registrations needed no extension (5 of 8 analysed Mumbai registrations needed no extension). 1 of 5 under-construction projects are past their original RERA completion date, by 7 months on average (worst 7). The median Je And Vee Infrastructure project scores 58/100 on investment merit (above the Mumbai average); the best, Jeandveesaidham - A Wing, scores 65.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Madhuban Goregaon / Malad | 7 | 2 | 100% of schedule · — | 0 | 48 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Je And Vee Infrastructure projects
All 8 analysed Je And Vee Infrastructure projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Jeandveesaidham - A Wing Je And Vee Infrastructure · Goregaon / Malad | 65 | 8.3% | 4.7% | 7.8% | ₹17,100 est. | ₹1.11 Cr | Under construction Dec 2029 |
| Jeandveesaidham - B Wing Je And Vee Infrastructure · Goregaon / Malad | 63 | 7.9% | 4.2% | 6.6% | ₹17,100 est. | ₹1.11 Cr | Under construction Dec 2028 |
| Om Trimurti Je And Vee Infrastructure · Goregaon / Malad | 61 | 6.7% | 3.8% | 4.9% | ₹18,200 est. | ₹1.18 Cr | Ready |
| Shivkrupa Je And Vee Infrastructure · Goregaon / Malad | 58 | 7.1% | 2.9% | 3.9% | ₹17,100 est. | ₹1.11 Cr | Under construction Dec 2026 |
| Shree Satyam Je And Vee Infrastructure · Goregaon / Malad | 58 | 7.1% | 2.9% | 3.9% | ₹17,100 est. | ₹1.11 Cr | Under construction Dec 2026 |
| Jeandveekedarnath Je And Vee Infrastructure · Kandivali / Borivali / Dahisar | 51 | 6.4% | 3.2% | 4.1% | ₹17,100 est. | ₹1.11 Cr | Ready |
| Jeandveevishwanath Je And Vee Infrastructure · Kandivali / Borivali / Dahisar | 51 | 6.4% | 3.2% | 4.1% | ₹17,100 est. | ₹1.11 Cr | Ready |
| Madhuban Je And Vee Infrastructure · Goregaon / Malad | 48 | 7.1% | 3.0% | 4.0% | ₹17,100 est. | ₹1.11 Cr | Under construction Mar 2026 |
Where Je And Vee Infrastructure builds
Questions people ask
Is Je And Vee Infrastructure a reliable builder?
MahaRERA filings as of September 11, 2026: 62% of registrations needed no extension; 1 of 5 under-construction projects are past their original completion date by 7 months on average; 4 extensions filed across 3 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Je And Vee Infrastructure project is the best investment?
Jeandveesaidham - A Wing in Goregaon / Malad scores highest at 65/100 with projected growth 8.3% a year and cash-flow IRR 7.8%. The median Je And Vee Infrastructure project scores 58.
Is Je And Vee Infrastructure delaying possession?
1 under-construction Je And Vee Infrastructure projects are past their original RERA completion date: Madhuban (7 months). Extensions filed with RERA are listed on each project page.
Where does Je And Vee Infrastructure build?
Goregaon / Malad, Mumbai (6), Kandivali / Borivali / Dahisar, Mumbai (2). Median price ₹17,100 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.