Is Kanakia a reliable builder?
10 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Kanakia in one paragraph
Kanakia has a strong delivery record in MahaRERA filings: 91% of registrations needed no extension (10 of 10 analysed Mumbai registrations needed no extension). 2 of 6 under-construction projects are past their original RERA completion date, by 3 months on average (worst 4). The median Kanakia project scores 61/100 on investment merit (above the Mumbai average); the best, Kanakia Silicon Valley F, scores 62.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Kanakia Zenworld Phase II Mulund / Bhandup / Kanjurmarg | 4 | 0 | 100% of schedule · — | 0 | 56 |
| Kanakia Future City E Powai / Chandivali / Saki Naka | 1 | 0 | 100% of schedule · — | 0 | 61 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Kanakia projects
All 10 analysed Kanakia projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Kanakia Silicon Valley F Kanakia · Powai / Chandivali / Saki Naka | 62 | 6.5% | 1.9% | 2.6% | ₹25,550 est. | ₹1.66 Cr | Under construction Dec 2026 |
| Kanakia Future City C Kanakia · Powai / Chandivali / Saki Naka | 62 | 6.1% | 2.7% | 3.6% | ₹27,200 est. | ₹1.77 Cr | Ready |
| Kanakia Future City B Kanakia · Powai / Chandivali / Saki Naka | 62 | 6.1% | 2.7% | 3.6% | ₹27,200 est. | ₹1.77 Cr | Ready |
| Kanakia Future City A Kanakia · Powai / Chandivali / Saki Naka | 62 | 6.1% | 2.7% | 3.6% | ₹27,200 est. | ₹1.77 Cr | Ready |
| Kanakia Future City D Kanakia · Powai / Chandivali / Saki Naka | 61 | 6.5% | 2.1% | 3.0% | ₹25,550 est. | ₹1.66 Cr | Under construction Jun 2027 |
| Kanakia Future City E Kanakia · Powai / Chandivali / Saki Naka | 61 | 6.5% | 2.1% | 2.8% | ₹25,550 est. | ₹1.66 Cr | Under construction Sep 2026 |
| Kanakia Privaasa Tower 1 & 2 Kanakia · Kandivali / Borivali / Dahisar | 58 | 7.6% | 3.4% | 6.2% | ₹20,500 est. | ₹1.33 Cr | Under construction Jun 2031 |
| Kanakia Zenworld Phase II Kanakia · Mulund / Bhandup / Kanjurmarg | 56 | 7.1% | 2.8% | 3.8% | ₹21,450 est. | ₹1.39 Cr | Under construction Jun 2026 |
| Kanakia Valley Kanakia · Panvel / Ulwe / Dronagiri | 48 | 9.0% | 4.6% | 8.3% | ₹9,600 est. | ₹62.4 L | Under construction Dec 2030 |
| Kanakia Greenberg Kanakia · Panvel / Ulwe / Dronagiri | 42 | 7.2% | 3.0% | 4.0% | ₹10,200 est. | ₹66.3 L | Ready |
Where Kanakia builds
Kanakia compared with other developers
Questions people ask
Is Kanakia a reliable builder?
MahaRERA filings as of September 11, 2026: 91% of registrations needed no extension; 2 of 6 under-construction projects are past their original completion date by 3 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Kanakia project is the best investment?
Kanakia Silicon Valley F in Powai / Chandivali / Saki Naka scores highest at 62/100 with projected growth 6.5% a year and cash-flow IRR 2.6%. The median Kanakia project scores 61.
Is Kanakia delaying possession?
2 under-construction Kanakia projects are past their original RERA completion date: Kanakia Zenworld Phase II (4 months), Kanakia Future City E (1 months). Extensions filed with RERA are listed on each project page.
Where does Kanakia build?
Powai / Chandivali / Saki Naka, Mumbai (6), Panvel / Ulwe / Dronagiri, Mumbai (2), Kandivali / Borivali / Dahisar, Mumbai (1), Mulund / Bhandup / Kanjurmarg, Mumbai (1). Median price ₹25,550 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.