Developer scorecard · #25 in Mumbai by RERA registrations

Is Kgi Realty a reliable builder?

14 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Kgi Realty in one paragraph

Kgi Realty has a strong delivery record in MahaRERA filings: 87% of registrations needed no extension (13 of 14 analysed Mumbai registrations needed no extension). 3 of 14 under-construction projects are past their original RERA completion date, by 2 months on average (worst 4). The median Kgi Realty project scores 34/100 on investment merit (well below the Mumbai average); the best, Kohinoor Imperia, scores 46.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.

Projects analysed
14
0 ready · 14 under construction
On-time rate
87%
registrations with no extension filed
Past RERA date
3 / 14
avg 2 months over
Extensions filed
1
1 projects
Cities
1
Mumbai
Red flags
4
across due-diligence reports
Median score
34
best 46
Median growth / yr
7.1%
5-yr projection
Median price / sq ft
₹6,200
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Kohinoor Eden B6
Kalyan / Titwala / Ulhasnagar
40100% of schedule · —026
Kohinoor Eden Ph 2
Kalyan / Titwala / Ulhasnagar
10100% of schedule · —032
Kohinoor Eden
Kalyan / Titwala / Ulhasnagar
11100% of schedule · —029

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Kgi Realty projects

All 14 analysed Kgi Realty projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Kohinoor Imperia
Kgi Realty · Thane East / Kalwa / Mumbra / Diva
468.4%3.3%5.6%₹8,950 est.₹58.2 LUnder construction
Mar 2030
Kohinoor Bella
Kgi Realty · Dombivli / Palava / Kalyan–Shil Road
458.3%3.0%5.1%₹6,600 est.₹42.9 LUnder construction
Dec 2029
Kohinoor Highland
Kgi Realty · Dombivli / Palava / Kalyan–Shil Road
417.1%1.1%1.4%₹6,600 est.₹42.9 LUnder construction
Dec 2026
Kohinoor Eden B8
Kgi Realty · Kalyan / Titwala / Ulhasnagar
377.8%2.0%3.4%₹6,200 est.₹40.3 LUnder construction
Dec 2029
Kohinoor Uptown T1 & T6
Kgi Realty · Kalyan / Titwala / Ulhasnagar
377.8%1.9%3.2%₹6,200 est.₹40.3 LUnder construction
Mar 2030
Kohinoor Anaya
Kgi Realty · Kalyan / Titwala / Ulhasnagar
357.4%1.4%2.3%₹6,200 est.₹40.3 LUnder construction
Dec 2028
Kohinoor Uptown T7
Kgi Realty · Kalyan / Titwala / Ulhasnagar
347.4%1.4%2.3%₹6,200 est.₹40.3 LUnder construction
Dec 2028
Kohinoor Gardens
Kgi Realty · Kalyan / Titwala / Ulhasnagar
347.0%1.0%1.5%₹6,200 est.₹40.3 LUnder construction
Nov 2027
Kohinoor Uptown Kalyan
Kgi Realty · Kalyan / Titwala / Ulhasnagar
347.0%1.0%1.4%₹6,200 est.₹40.3 LUnder construction
Dec 2027
Kohinoor Eden B4
Kgi Realty · Kalyan / Titwala / Ulhasnagar
346.6%0.1%0.2%₹6,200 est.₹40.3 LUnder construction
Dec 2026
Kohinoor Eden B5
Kgi Realty · Kalyan / Titwala / Ulhasnagar
326.6%0.2%0.3%₹6,200 est.₹40.3 LUnder construction
Jun 2027
Kohinoor Eden Ph 2
Kgi Realty · Kalyan / Titwala / Ulhasnagar
326.6%0.2%0.3%₹6,200 est.₹40.3 LUnder construction
Sep 2026
Kohinoor Eden
Kgi Realty · Kalyan / Titwala / Ulhasnagar
296.6%0.2%0.3%₹6,200 est.₹40.3 LUnder construction
Sep 2026
Kohinoor Eden B6
Kgi Realty · Kalyan / Titwala / Ulhasnagar
266.6%0.2%0.3%₹6,200 est.₹40.3 LUnder construction
Jun 2026

Where Kgi Realty builds

Kgi Realty compared with other developers

Questions people ask

Is Kgi Realty a reliable builder?

MahaRERA filings as of September 11, 2026: 87% of registrations needed no extension; 3 of 14 under-construction projects are past their original completion date by 2 months on average; 1 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Kgi Realty project is the best investment?

Kohinoor Imperia in Thane East / Kalwa / Mumbra / Diva scores highest at 46/100 with projected growth 8.4% a year and cash-flow IRR 5.6%. The median Kgi Realty project scores 34.

Is Kgi Realty delaying possession?

3 under-construction Kgi Realty projects are past their original RERA completion date: Kohinoor Eden B6 (4 months), Kohinoor Eden Ph 2 (1 months), Kohinoor Eden (1 months). Extensions filed with RERA are listed on each project page.

Where does Kgi Realty build?

Kalyan / Titwala / Ulhasnagar, Mumbai (11), Dombivli / Palava / Kalyan–Shil Road, Mumbai (2), Thane East / Kalwa / Mumbra / Diva, Mumbai (1). Median price ₹6,200 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.