Is Legacy Global a reliable builder?
12 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Legacy Global in one paragraph
Legacy Global has a weak delivery record in Karnataka RERA filings: 25% of registrations needed no extension (2 of 12 crawled Bengaluru registrations needed no extension). 6 of 10 under-construction projects are past their original RERA completion date, by 53 months on average (worst 90). The promoter entity carries 18 complaints at K-RERA across its projects. The median Legacy Global project scores 47/100 on investment merit (below the Bengaluru average); the best, Legacy Maximus, scores 61.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Legacy Mycon Duv Bengaluru | 90 | 1 | 100% of schedule · — | 0 | 33 |
| Legacy Eldora Yelahanka / Jakkur / Airport corridor | 73 | 1 | 100% of schedule · — | 1 | 44 |
| Legacy Cirocco Bengaluru | 66 | 1 | 100% of schedule · — | 1 | 43 |
| Legacy Calista Yelahanka / Jakkur / Airport corridor | 38 | 1 | 100% of schedule · — | 0 | 47 |
| Legacy Alcazar Central Bengaluru | 30 | 1 | 100% of schedule · — | 0 | 49 |
| Legacy Maximus Central Bengaluru | 20 | 1 | 100% of schedule · — | 0 | 48 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Legacy Global projects
All 12 analysed Legacy Global projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Legacy Maximus Legacy Global · Central Bengaluru | 61 | 9.9% | 6.2% | 9.2% | ₹15,050 est. | ₹2.26 Cr | Under construction Dec 2027 |
| Legacy Salvador Legacy Global · Yelahanka / Jakkur / Airport corridor | 51 | 9.4% | 7.0% | 8.7% | ₹8,200 est. | ₹98.8 L | Ready |
| Legacy Mihira Legacy Global · Devanahalli / Airport Road / Bagalur | 49 | 12.7% | 11.5% | 19.8% | ₹3,350 est. | ₹40.2 L | Under construction Dec 2030 |
| Legacy Alcazar Legacy Global · Central Bengaluru | 49 | 9.0% | 4.5% | 5.9% | ₹15,050 est. | ₹3.56 Cr | Under construction Mar 2024 |
| Legacy Maximus Legacy Global · Central Bengaluru | 48 | 9.0% | 4.4% | 5.8% | ₹15,050 est. | ₹6.64 Cr | Under construction Dec 2024 |
| Legacy Calista Legacy Global · Yelahanka / Jakkur / Airport corridor | 47 | 10.1% | 5.9% | 7.4% | ₹7,700 est. | ₹99.7 L | Under construction Jul 2023 |
| Legacy Madelia Legacy Global · Bengaluru | 46 | 8.6% | 4.4% | 5.7% | ₹8,500 est. | ₹3.26 Cr | Ready |
| Legacy Eldora Legacy Global · Yelahanka / Jakkur / Airport corridor | 44 | 9.8% | 5.2% | 6.6% | ₹7,950 est. | ₹1.76 Cr | Under construction Aug 2020 |
| Legacy Cataleya Legacy Global · Central Bengaluru | 44 | 8.3% | 3.8% | 5.0% | ₹15,500 est. | ₹6.72 Cr | Under construction Sep 2026 |
| Legacy Cirocco Legacy Global · Bengaluru | 43 | 9.5% | 3.8% | 4.9% | ₹8,250 est. | ₹3.25 Cr | Under construction Mar 2021 |
| Legacy Mycon Duv Legacy Global · Bengaluru | 33 | 8.7% | 3.1% | 4.0% | ₹8,250 est. | ₹6.25 Cr | Under construction Mar 2019 |
| Legacy Vivienda Legacy Global · Devanahalli / Airport Road / Bagalur | 23 | 10.0% | 5.6% | 8.8% | ₹6,100 est. | ₹32.6 L | Under construction Dec 2028 |
Where Legacy Global builds
Legacy Global compared with other developers
Questions people ask
Is Legacy Global a reliable builder?
Karnataka RERA filings as of September 11, 2026: 25% of registrations needed no extension; 6 of 10 under-construction projects are past their original completion date by 53 months on average; 16 extensions filed across 10 projects; 18 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Legacy Global project is the best investment?
Legacy Maximus in Central Bengaluru scores highest at 61/100 with projected growth 9.9% a year and cash-flow IRR 9.2%. The median Legacy Global project scores 47.
Is Legacy Global delaying possession?
6 under-construction Legacy Global projects are past their original RERA completion date: Legacy Mycon Duv (90 months), Legacy Eldora (73 months), Legacy Cirocco (66 months), Legacy Calista (38 months), Legacy Alcazar (30 months) and others. Extensions filed with RERA are listed on each project page.
Where does Legacy Global build in Bengaluru?
Central Bengaluru (4), Yelahanka / Jakkur / Airport corridor (3), Bengaluru (3), Devanahalli / Airport Road / Bagalur (2). Median price ₹8,250 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.