Lodha (Macrotech) vs Ramaniyam

308 Mumbai, Pune, Bengaluru, Gurugram and Chennai projects from state RERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Ramaniyam has the better delivery record; Ramaniyam's projects score higher on investment merit

From state RERA filings: Lodha (Macrotech) 82% of registrations needed no extension with 35 of 229 under-construction projects past their original date; Ramaniyam 97% of registrations needed no extension with 0 of 32 past date. Median project score: Lodha (Macrotech) 47, Ramaniyam 64. Judge the specific project, not just the brand.

Side by side

MeasureLodha (Macrotech)Ramaniyam
Projects analysed26840
On-time rate (no extension filed)82%97%
Under construction past original RERA date35 of 2290 of 32
Average months overdue (late projects)6—
Extensions filed580
Red flags across projects910
Projects with litigation declared30
Median investment score4764
Best project score8575
Median projected growth / yr7.3%7.7%
Median cash-flow IRR3.1%4.6%
Median gross yield2.3%3.0%
Median price per sq ft₹11,750₹17,300
Ready · under construction39 · 2298 · 32
Localities active in298

Green marks the better value on each line. state RERA filings as of September 11, 2026.

Best-scored Lodha (Macrotech) projects

Best-scored Ramaniyam projects

Questions people ask

Lodha (Macrotech) or Ramaniyam: which is the more reliable builder?

From state RERA filings: Lodha (Macrotech) 82% of registrations needed no extension with 35 of 229 under-construction projects past their original date; Ramaniyam 97% of registrations needed no extension with 0 of 32 past date. Median project score: Lodha (Macrotech) 47, Ramaniyam 64. Judge the specific project, not just the brand.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.