Mohan Group in one paragraph
Mohan Group has a strong delivery record in MahaRERA filings: 84% of registrations needed no extension (15 of 17 analysed Mumbai registrations needed no extension). 2 of 14 under-construction projects are past their original RERA completion date, by 8 months on average (worst 11). The median Mohan Group project scores 32/100 on investment merit (well below the Mumbai average); the best, Mohan Prestige, scores 35.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Vedant Millenia Happiness Phase II Wing B Kalyan / Titwala / Ulhasnagar | 11 | 1 | 100% of schedule · — | 0 | 20 |
| Vedant Nakshatra Wing K Phase V Ambernath / Badlapur | 4 | 0 | 100% of schedule · — | 0 | 24 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Mohan Group projects
All 17 analysed Mohan Group projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Mohan Prestige Mohan Group · Kalyan / Titwala / Ulhasnagar | 35 | 7.7% | 2.5% | 5.1% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2031 |
| Mohan Altezza III Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 7.0% | 1.0% | 1.4% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2027 |
| Vedant Empire Phase I Wing A-Eagleton Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 7.0% | 1.0% | 1.4% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2027 |
| Vedant Empire Phase II Wing B-Hampton Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 7.0% | 1.0% | 1.4% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2027 |
| Vedant Millenia Happiness Phase II Wing E Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 7.8% | 2.0% | 3.4% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2029 |
| Vedant Connect Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 6.6% | 0.1% | 0.2% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2026 |
| Vedant Millenia happiness Phase II Wing C Mohan Group · Kalyan / Titwala / Ulhasnagar | 33 | 7.0% | 1.0% | 1.4% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2027 |
| Mohan Alcoves I Mohan Group · Ambernath / Badlapur | 32 | 7.7% | 0.8% | 1.3% | ₹4,600 est. | ₹29.9 L | Under construction Jun 2029 |
| Mohan Willows III Mohan Group · Ambernath / Badlapur | 32 | 7.3% | 0.5% | 0.8% | ₹4,600 est. | ₹29.9 L | Under construction Dec 2027 |
| Vedant Empire Phase III Wing C-Cliffton Mohan Group · Kalyan / Titwala / Ulhasnagar | 32 | 6.2% | 1.4% | 1.8% | ₹6,600 est. | ₹42.9 L | Ready |
| Vedant Millenia Blue Moon Phase IV Mohan Group · Kalyan / Titwala / Ulhasnagar | 32 | 7.0% | 0.7% | 1.0% | ₹6,200 est. | ₹40.3 L | Under construction Jun 2028 |
| Vedant Millenia Happiness Phase II Wing D Mohan Group · Kalyan / Titwala / Ulhasnagar | 31 | 7.0% | 0.6% | 0.9% | ₹6,200 est. | ₹40.3 L | Under construction Jul 2028 |
| Mohan Altezza II Mohan Group · Kalyan / Titwala / Ulhasnagar | 31 | 6.2% | 1.4% | 1.8% | ₹6,600 est. | ₹42.9 L | Ready |
| Vedant Nakshatra Wing J Phase VI Mohan Group · Ambernath / Badlapur | 31 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
| vedantnakshatra L phase 3 Mohan Group · Ambernath / Badlapur | 30 | 6.9% | -0.3% | -0.4% | ₹4,600 est. | ₹29.9 L | Under construction Aug 2027 |
| Vedant Nakshatra Wing K Phase V Mohan Group · Ambernath / Badlapur | 24 | 6.9% | -0.3% | -0.4% | ₹4,600 est. | ₹29.9 L | Under construction Jun 2026 |
| Vedant Millenia Happiness Phase II Wing B Mohan Group · Kalyan / Titwala / Ulhasnagar | 20 | 6.6% | 0.2% | 0.3% | ₹6,200 est. | ₹40.3 L | Under construction Dec 2025 |
Where Mohan Group builds
Mohan Group compared with other developers
Questions people ask
Is Mohan Group a reliable builder?
MahaRERA filings as of September 11, 2026: 84% of registrations needed no extension; 2 of 14 under-construction projects are past their original completion date by 8 months on average; 2 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Mohan Group project is the best investment?
Mohan Prestige in Kalyan / Titwala / Ulhasnagar scores highest at 35/100 with projected growth 7.7% a year and cash-flow IRR 5.1%. The median Mohan Group project scores 32.
Is Mohan Group delaying possession?
2 under-construction Mohan Group projects are past their original RERA completion date: Vedant Millenia Happiness Phase II Wing B (11 months), Vedant Nakshatra Wing K Phase V (4 months). Extensions filed with RERA are listed on each project page.
Where does Mohan Group build?
Kalyan / Titwala / Ulhasnagar, Mumbai (12), Ambernath / Badlapur, Mumbai (5). Median price ₹6,200 per sq ft across analysed projects.