Is R K Developers a reliable builder?
3 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
R K Developers in one paragraph
R K Developers has a strong delivery record in Karnataka RERA filings: 80% of registrations needed no extension (3 of 3 crawled Bengaluru registrations needed no extension). 1 of 1 under-construction projects are past their original RERA completion date, by 27 months on average (worst 27). No complaints are recorded against the promoter entity at K-RERA. The median R K Developers project scores 53/100 on investment merit (below the Bengaluru average); the best, 36 Park Avenue Phase III, scores 54.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| 36 Park Avenue Sarjapur Road | 27 | 0 | 100% of schedule · — | 0 | 49 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored R K Developers projects
All 3 analysed R K Developers projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| 36 Park Avenue Phase III R K Developers · Sarjapur Road | 54 | 10.4% | 6.3% | 9.0% | ₹4,950 est. | ₹74.3 L | Ready |
| 36 Park Avenue Phase-II R K Developers · Sarjapur Road | 53 | 10.4% | 6.3% | 9.0% | ₹4,950 est. | ₹59.4 L | Ready |
| 36 Park Avenue R K Developers · Sarjapur Road | 49 | 12.1% | 7.9% | 11.2% | ₹4,650 est. | ₹54.9 L | Under construction Jul 2024 |
Where R K Developers builds
R K Developers compared with other developers
Questions people ask
Is R K Developers a reliable builder?
Karnataka RERA filings as of September 11, 2026: 80% of registrations needed no extension; 1 of 1 under-construction projects are past their original completion date by 27 months on average; 0 extensions filed across 0 projects; 0 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which R K Developers project is the best investment?
36 Park Avenue Phase III in Sarjapur Road scores highest at 54/100 with projected growth 10.4% a year and cash-flow IRR 9.0%. The median R K Developers project scores 53.
Is R K Developers delaying possession?
1 under-construction R K Developers projects are past their original RERA completion date: 36 Park Avenue (27 months). Extensions filed with RERA are listed on each project page.
Where does R K Developers build in Bengaluru?
Sarjapur Road (3). Median price ₹4,950 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.