Straight answer · as of September 11, 2026

Raheja Developers in one paragraph

Raheja Developers has a weak delivery record in Haryana RERA (Gurugram) filings: 15% of registrations needed no extension (0 of 9 analysed Gurugram registrations needed no extension (9 lapsed)). 9 of 9 under-construction projects are past their original RERA completion date, by 49 months on average (worst 52). The median Raheja Developers project scores 36/100 on investment merit (well below the Gurugram average); the best, Plotted Colony (Raheja Aranya Phase - Ii), scores 60.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.

Projects analysed
9
0 ready · 9 under construction
On-time rate
15%
registrations with no extension filed
Past RERA date
9 / 9
avg 49 months over
Extensions filed
0
0 projects
Cities
1
Gurugram
Red flags
9
across due-diligence reports
Median score
36
best 60
Median growth / yr
8.1%
5-yr projection
Median price / sq ft
₹11,100
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Amaltaas Tower (Tower-B)
Dwarka Expressway
520100% of schedule · —036
Raheja Trinity
New Gurugram
520100% of schedule · —033
Group Housing Project ( Tower A,b,c, D And E)
Sohna
520100% of schedule · —031
Revanta
New Gurugram
510100% of schedule · —029
Plotted Colony (Raheja Aranya Phase - Ii)
Old Gurugram, DLF Phases and Palam Vihar
500100% of schedule · —060
Raheja Shilas Low Rise In Raheja Atharva
Dwarka Expressway
500100% of schedule · —038
Chandan Tower(Tower-D)
Dwarka Expressway
460100% of schedule · —037
Gulmohar Tower (Tower-A)
Dwarka Expressway
460100% of schedule · —036
Palash Tower (Tower-C)
Dwarka Expressway
460100% of schedule · —036

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Raheja Developers projects

All 9 analysed Raheja Developers projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Plotted Colony (Raheja Aranya Phase - Ii)
Raheja Developers · Old Gurugram, DLF Phases and Palam Vihar
6010.3%5.6%7.9%₹7,100 est.₹1.28 CrUnder construction
Aug 2022
Raheja Shilas Low Rise In Raheja Atharva
Raheja Developers · Dwarka Expressway
388.1%3.3%4.3%₹11,100 est.₹1.28 CrUnder construction
Aug 2022
Chandan Tower(Tower-D)
Raheja Developers · Dwarka Expressway
378.1%3.4%4.4%₹11,100 est.₹1.14 CrUnder construction
Dec 2022
Amaltaas Tower (Tower-B)
Raheja Developers · Dwarka Expressway
368.1%3.3%4.3%₹11,100 est.₹1.28 CrUnder construction
Jul 2022
Gulmohar Tower (Tower-A)
Raheja Developers · Dwarka Expressway
368.1%3.3%4.3%₹11,100 est.₹1.28 CrUnder construction
Dec 2022
Palash Tower (Tower-C)
Raheja Developers · Dwarka Expressway
368.1%3.3%4.3%₹11,100 est.₹1.28 CrUnder construction
Dec 2022
Raheja Trinity
Raheja Developers · New Gurugram
337.8%2.2%2.9%₹8,000 est.₹92.0 LUnder construction
Jul 2022
Group Housing Project ( Tower A,b,c, D And E)
Raheja Developers · Sohna
317.6%1.3%1.6%₹5,900 est.₹67.8 LUnder construction
Jul 2022
Revanta
Raheja Developers · New Gurugram
297.8%2.2%2.9%₹8,000 est.₹92.0 LUnder construction
Aug 2022

Where Raheja Developers builds

Questions people ask

Is Raheja Developers a reliable builder?

Haryana RERA (Gurugram) filings as of September 11, 2026: 15% of registrations needed no extension; 9 of 9 under-construction projects are past their original completion date by 49 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Raheja Developers project is the best investment?

Plotted Colony (Raheja Aranya Phase - Ii) in Old Gurugram, DLF Phases and Palam Vihar scores highest at 60/100 with projected growth 10.3% a year and cash-flow IRR 7.9%. The median Raheja Developers project scores 36.

Is Raheja Developers delaying possession?

9 under-construction Raheja Developers projects are past their original RERA completion date: Amaltaas Tower (Tower-B) (52 months), Raheja Trinity (52 months), Group Housing Project ( Tower A,b,c, D And E) (52 months), Revanta (51 months), Plotted Colony (Raheja Aranya Phase - Ii) (50 months) and others. Extensions filed with RERA are listed on each project page.

Where does Raheja Developers build?

Dwarka Expressway, Gurugram (5), New Gurugram, Gurugram (2), Old Gurugram, DLF Phases and Palam Vihar, Gurugram (1), Sohna, Gurugram (1). Median price ₹11,100 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.