Is Rama Spaces a reliable builder?
4 projects analysed in Pune from MahaRERA filings, as of September 11, 2026.
Rama Spaces in one paragraph
Rama Spaces has a weak delivery record in MahaRERA filings: 54% of registrations needed no extension (2 of 4 analysed Pune registrations needed no extension). 1 of 3 under-construction projects are past their original RERA completion date, by 2 months on average (worst 2). The median Rama Spaces project scores 38/100 on investment merit (well below the Pune average); the best, Krystal One Phase IV, scores 40.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Pune; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Krystal One Phase II Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 2 | 1 | 100% of schedule · — | 0 | 29 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Rama Spaces projects
All 4 analysed Rama Spaces projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Krystal One Phase IV Rama Spaces · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 40 | 8.0% | 2.1% | 3.2% | ₹5,350 est. | ₹40.1 L | Under construction Dec 2027 |
| Krystal One Phase I Rama Spaces · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 38 | 7.2% | 2.7% | 3.4% | ₹5,700 est. | ₹42.8 L | Ready |
| Krystal One Phase III Rama Spaces · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 36 | 7.6% | 1.3% | 1.8% | ₹5,350 est. | ₹40.1 L | Under construction Dec 2026 |
| Krystal One Phase II Rama Spaces · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 29 | 7.6% | 1.4% | 1.7% | ₹5,350 est. | ₹40.1 L | Under construction Aug 2026 |
Where Rama Spaces builds
Questions people ask
Is Rama Spaces a reliable builder?
MahaRERA filings as of September 11, 2026: 54% of registrations needed no extension; 1 of 3 under-construction projects are past their original completion date by 2 months on average; 2 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Rama Spaces project is the best investment?
Krystal One Phase IV in Ravet / Kiwale / Moshi / Chikhali / Dehu Road scores highest at 40/100 with projected growth 8.0% a year and cash-flow IRR 3.2%. The median Rama Spaces project scores 38.
Is Rama Spaces delaying possession?
1 under-construction Rama Spaces projects are past their original RERA completion date: Krystal One Phase II (2 months). Extensions filed with RERA are listed on each project page.
Where does Rama Spaces build?
Ravet / Kiwale / Moshi / Chikhali / Dehu Road, Pune (4). Median price ₹5,350 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.