Is Raymond Realty a reliable builder?
19 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Raymond Realty in one paragraph
Raymond Realty has a strong delivery record in MahaRERA filings: 90% of registrations needed no extension (18 of 19 analysed Mumbai registrations needed no extension). 2 of 17 under-construction projects are past their original RERA completion date, by 3 months on average (worst 4). The median Raymond Realty project scores 61/100 on investment merit (above the Mumbai average); the best, The Address by GS Tower E, scores 63.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| TEN X HABITAT Raymond Realty Tower G Thane West | 4 | 0 | 100% of schedule · — | 0 | 52 |
| TEN X HABITAT Raymond Realty Tower F Thane West | 2 | 1 | 100% of schedule · — | 0 | 49 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Raymond Realty projects
All 19 analysed Raymond Realty projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| The Address by GS Tower E Raymond Realty · Thane West | 63 | 8.5% | 4.2% | 7.0% | ₹16,000 est. | ₹1.04 Cr | Under construction Mar 2030 |
| Invictus by GS Tower B Raymond Realty · Thane West | 63 | 8.5% | 4.1% | 7.3% | ₹16,000 est. | ₹1.04 Cr | Under construction Aug 2031 |
| The Address by GS Tower F Raymond Realty · Thane West | 63 | 8.4% | 5.1% | 9.3% | ₹16,000 est. | ₹1.04 Cr | Under construction Oct 2031 |
| Tenx District 9 Tower A Raymond Realty · Thane West | 63 | 8.4% | 5.0% | 9.1% | ₹16,000 est. | ₹1.04 Cr | Under construction Dec 2031 |
| Tenx District 9 Tower B Raymond Realty · Thane West | 63 | 8.4% | 5.0% | 9.1% | ₹16,000 est. | ₹1.04 Cr | Under construction Dec 2031 |
| Tenx District 9 Tower C Raymond Realty · Thane West | 62 | 8.3% | 4.9% | 9.0% | ₹16,000 est. | ₹1.04 Cr | Under construction Jan 2032 |
| Invictus By Gs Raymond Realty · Thane West | 61 | 8.1% | 3.8% | 6.0% | ₹16,000 est. | ₹1.04 Cr | Under construction Oct 2028 |
| The Address By Gs Tower C Raymond Realty · Thane West | 61 | 8.1% | 3.7% | 5.9% | ₹16,000 est. | ₹1.04 Cr | Under construction Dec 2028 |
| TEN X ERA Raymond Realty Tower B Raymond Realty · Thane West | 61 | 8.1% | 3.7% | 5.8% | ₹16,000 est. | ₹1.04 Cr | Under construction Jan 2029 |
| TEN X ERA Raymond Realty Tower C Raymond Realty · Thane West | 61 | 8.1% | 3.7% | 5.8% | ₹16,000 est. | ₹1.04 Cr | Under construction Jan 2029 |
| TEN X ERA Raymond Realty Tower A Raymond Realty · Thane West | 60 | 8.1% | 3.4% | 5.3% | ₹16,000 est. | ₹1.04 Cr | Under construction Aug 2029 |
| The Address by GS Tower D Raymond Realty · Thane West | 60 | 8.1% | 3.6% | 5.7% | ₹16,000 est. | ₹1.04 Cr | Under construction Mar 2029 |
| The Address By GS Tower B Raymond Realty · Thane West | 60 | 7.7% | 3.1% | 4.7% | ₹16,000 est. | ₹1.04 Cr | Under construction Mar 2028 |
| The Address by GS Tower A Raymond Realty · Thane West | 60 | 7.3% | 2.3% | 3.1% | ₹16,000 est. | ₹1.04 Cr | Under construction Dec 2026 |
| TEN X HABITAT Raymond Realty Tower K Raymond Realty · Thane West | 59 | 6.9% | 3.1% | 4.2% | ₹17,000 est. | ₹1.10 Cr | Ready |
| Aashiyana Raymond Realty · Thane West | 59 | 6.9% | 3.1% | 4.2% | ₹17,000 est. | ₹1.10 Cr | Ready |
| Park Avenue Raymond Realty · Thane West | 58 | 7.3% | 2.4% | 3.4% | ₹16,000 est. | ₹1.04 Cr | Under construction Jul 2027 |
| TEN X HABITAT Raymond Realty Tower G Raymond Realty · Thane West | 52 | 7.3% | 2.4% | 3.2% | ₹16,000 est. | ₹1.04 Cr | Under construction Jun 2026 |
| TEN X HABITAT Raymond Realty Tower F Raymond Realty · Thane West | 49 | 7.3% | 2.4% | 3.2% | ₹16,000 est. | ₹1.04 Cr | Under construction Aug 2026 |
Where Raymond Realty builds
Raymond Realty compared with other developers
Questions people ask
Is Raymond Realty a reliable builder?
MahaRERA filings as of September 11, 2026: 90% of registrations needed no extension; 2 of 17 under-construction projects are past their original completion date by 3 months on average; 1 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Raymond Realty project is the best investment?
The Address by GS Tower E in Thane West scores highest at 63/100 with projected growth 8.5% a year and cash-flow IRR 7.0%. The median Raymond Realty project scores 61.
Is Raymond Realty delaying possession?
2 under-construction Raymond Realty projects are past their original RERA completion date: TEN X HABITAT Raymond Realty Tower G (4 months), TEN X HABITAT Raymond Realty Tower F (2 months). Extensions filed with RERA are listed on each project page.
Where does Raymond Realty build?
Thane West, Mumbai (19). Median price ₹16,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.