Is Sai Shrushti Enterprises a reliable builder?
7 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Sai Shrushti Enterprises in one paragraph
Sai Shrushti Enterprises has a strong delivery record in MahaRERA filings: 88% of registrations needed no extension (7 of 7 analysed Mumbai registrations needed no extension). 1 of 5 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Sai Shrushti Enterprises project scores 45/100 on investment merit (below the Mumbai average); the best, Nakhawa Enclave, scores 58.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Sai Shrushti Vatika Gajanan Alimkar Thane East / Kalwa / Mumbra / Diva | 10 | 0 | 100% of schedule · — | 0 | 36 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Sai Shrushti Enterprises projects
All 7 analysed Sai Shrushti Enterprises projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Nakhawa Enclave Sai Shrushti Enterprises · Thane West | 58 | 7.1% | 3.6% | 4.7% | ₹13,300 est. | ₹86.5 L | Ready |
| Sai Shrushti Leela Phase V Sai Shrushti Enterprises · Dombivli / Palava / Kalyan–Shil Road | 46 | 8.5% | 3.4% | 6.3% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2030 |
| Shiv Sarovar Heritage Sai Shrushti Enterprises · Dombivli / Palava / Kalyan–Shil Road | 46 | 8.5% | 3.4% | 6.3% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2030 |
| Sai Shrushti Leela Phase III Sai Shrushti Enterprises · Dombivli / Palava / Kalyan–Shil Road | 45 | 8.3% | 3.0% | 5.1% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2029 |
| Sai Shrushti Heritage Sai Shrushti Enterprises · Thane East / Kalwa / Mumbra / Diva | 45 | 6.8% | 2.7% | 3.5% | ₹9,500 est. | ₹61.8 L | Ready |
| Sai Shrushti Leela Sai Shrushti Enterprises · Dombivli / Palava / Kalyan–Shil Road | 42 | 7.5% | 1.9% | 2.9% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2027 |
| Sai Shrushti Vatika Gajanan Alimkar Sai Shrushti Enterprises · Thane East / Kalwa / Mumbra / Diva | 36 | 7.2% | 1.7% | 2.2% | ₹8,950 est. | ₹58.2 L | Under construction Dec 2025 |
Where Sai Shrushti Enterprises builds
Questions people ask
Is Sai Shrushti Enterprises a reliable builder?
MahaRERA filings as of September 11, 2026: 88% of registrations needed no extension; 1 of 5 under-construction projects are past their original completion date by 10 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Sai Shrushti Enterprises project is the best investment?
Nakhawa Enclave in Thane West scores highest at 58/100 with projected growth 7.1% a year and cash-flow IRR 4.7%. The median Sai Shrushti Enterprises project scores 45.
Is Sai Shrushti Enterprises delaying possession?
1 under-construction Sai Shrushti Enterprises projects are past their original RERA completion date: Sai Shrushti Vatika Gajanan Alimkar (10 months). Extensions filed with RERA are listed on each project page.
Where does Sai Shrushti Enterprises build?
Dombivli / Palava / Kalyan–Shil Road, Mumbai (4), Thane East / Kalwa / Mumbra / Diva, Mumbai (2), Thane West, Mumbai (1). Median price ₹6,600 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.