Is Ss Group a reliable builder?
11 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Ss Group in one paragraph
Ss Group has a weak delivery record in Haryana RERA (Gurugram) filings: 34% of registrations needed no extension (3 of 11 analysed Gurugram registrations needed no extension (4 lapsed)). 4 of 7 under-construction projects are past their original RERA completion date, by 33 months on average (worst 82). The median Ss Group project scores 39/100 on investment merit (well below the Gurugram average); the best, Ss Linden, scores 54.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| The Coralwood And Almeria New Gurugram | 82 | 0 | 100% of schedule · — | 0 | 33 |
| SS 100 Sohna Road and Southern Peripheral Road | 25 | 0 | 100% of schedule · — | 0 | 45 |
| Ss High Point New Gurugram | 16 | 1 | 100% of schedule · — | 0 | 28 |
| Ss Strada New Gurugram | 7 | 0 | 100% of schedule · — | 0 | 31 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Ss Group projects
All 11 analysed Ss Group projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Ss Linden Ss Group · New Gurugram | 54 | 9.3% | 4.9% | 7.0% | ₹4,400 est. | ₹23.8 L | Under construction Dec 2026 |
| Ss Linden -IV Ss Group · New Gurugram | 50 | 9.7% | 6.2% | 9.9% | ₹4,400 est. | ₹23.8 L | Under construction Feb 2028 |
| SS 100 Ss Group · Sohna Road and Southern Peripheral Road | 45 | 8.8% | 4.1% | 5.3% | ₹11,100 est. | ₹1.21 Cr | Under construction Sep 2024 |
| Ss Linden Floors -III Ss Group · New Gurugram | 43 | 7.4% | 3.0% | 4.0% | ₹8,500 est. | ₹1.59 Cr | Ready |
| Ss Linden Residential Floors - II Ss Group · New Gurugram | 39 | 7.4% | 2.9% | 3.9% | ₹8,500 est. | ₹1.71 Cr | Ready |
| Ss Linden Residential Floors Ss Group · New Gurugram | 39 | 7.4% | 2.9% | 3.9% | ₹8,500 est. | ₹1.71 Cr | Ready |
| The Leaf Ss Group · New Gurugram | 38 | 7.4% | 3.3% | 4.3% | ₹8,500 est. | ₹97.8 L | Ready |
| Ss Whitewater Ss Group · New Gurugram | 37 | 8.2% | 2.9% | 4.3% | ₹8,000 est. | ₹67.2 L | Under construction Sep 2028 |
| The Coralwood And Almeria Ss Group · New Gurugram | 33 | 7.8% | 2.2% | 2.9% | ₹8,000 est. | ₹92.0 L | Under construction Dec 2019 |
| Ss Strada Ss Group · New Gurugram | 31 | 7.8% | 2.3% | 3.0% | ₹8,000 est. | ₹85.2 L | Under construction Mar 2026 |
| Ss High Point Ss Group · New Gurugram | 28 | 7.8% | 2.1% | 2.8% | ₹8,000 est. | ₹1.10 Cr | Under construction Jun 2025 |
Where Ss Group builds
Ss Group compared with other developers
Questions people ask
Is Ss Group a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 34% of registrations needed no extension; 4 of 7 under-construction projects are past their original completion date by 33 months on average; 4 extensions filed across 4 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Ss Group project is the best investment?
Ss Linden in New Gurugram scores highest at 54/100 with projected growth 9.3% a year and cash-flow IRR 7.0%. The median Ss Group project scores 39.
Is Ss Group delaying possession?
4 under-construction Ss Group projects are past their original RERA completion date: The Coralwood And Almeria (82 months), SS 100 (25 months), Ss High Point (16 months), Ss Strada (7 months). Extensions filed with RERA are listed on each project page.
Where does Ss Group build?
New Gurugram, Gurugram (10), Sohna Road and Southern Peripheral Road, Gurugram (1). Median price ₹8,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.