Is Sudhanshu Infrastructures a reliable builder?
6 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Sudhanshu Infrastructures in one paragraph
Sudhanshu Infrastructures has a mixed delivery record in MahaRERA filings: 64% of registrations needed no extension (4 of 6 analysed Mumbai registrations needed no extension). 0 of 4 under-construction projects are past their original RERA completion date. The median Sudhanshu Infrastructures project scores 62/100 on investment merit (above the Mumbai average); the best, Bhandup Amol CHS Ltd, scores 63.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Best-scored Sudhanshu Infrastructures projects
All 6 analysed Sudhanshu Infrastructures projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Bhandup Amol CHS Ltd Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 63 | 7.5% | 3.4% | 4.5% | ₹16,850 est. | ₹1.10 Cr | Under construction Dec 2026 |
| Sudhanshu Imperia Wing C Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 63 | 7.1% | 4.3% | 5.6% | ₹17,900 est. | ₹1.16 Cr | Ready |
| Vishnu Bhaskar CHS Ltd Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 62 | 7.1% | 4.3% | 5.6% | ₹17,900 est. | ₹1.16 Cr | Ready |
| Paul Chamber Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 62 | 7.5% | 3.5% | 4.9% | ₹16,850 est. | ₹1.10 Cr | Under construction Aug 2027 |
| Aniraj Tower CHS Ltd Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 61 | 7.9% | 4.3% | 6.4% | ₹16,850 est. | ₹1.10 Cr | Under construction Dec 2027 |
| Sudhanshu Heights Sudhanshu Infrastructures · Mulund / Bhandup / Kanjurmarg | 58 | 7.5% | 3.8% | 5.4% | ₹16,850 est. | ₹1.10 Cr | Under construction Mar 2027 |
Where Sudhanshu Infrastructures builds
Questions people ask
Is Sudhanshu Infrastructures a reliable builder?
MahaRERA filings as of September 11, 2026: 64% of registrations needed no extension; 0 of 4 under-construction projects are past their original completion date; 3 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Sudhanshu Infrastructures project is the best investment?
Bhandup Amol CHS Ltd in Mulund / Bhandup / Kanjurmarg scores highest at 63/100 with projected growth 7.5% a year and cash-flow IRR 4.5%. The median Sudhanshu Infrastructures project scores 62.
Is Sudhanshu Infrastructures delaying possession?
No under-construction Sudhanshu Infrastructures project is past its original RERA completion date as of September 11, 2026.
Where does Sudhanshu Infrastructures build?
Mulund / Bhandup / Kanjurmarg, Mumbai (6). Median price ₹16,850 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.