Is Tharwani Realtors a reliable builder?
7 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Tharwani Realtors in one paragraph
Tharwani Realtors has a strong delivery record in MahaRERA filings: 88% of registrations needed no extension (7 of 7 analysed Mumbai registrations needed no extension). 1 of 6 under-construction projects are past their original RERA completion date, by 1 months on average (worst 1). The median Tharwani Realtors project scores 42/100 on investment merit (below the Mumbai average); the best, Tharwani Pristinea, scores 63.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Tharwani Palladian Kharghar / Taloja / Kamothe | 1 | 0 | 100% of schedule · — | 0 | 58 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Tharwani Realtors projects
All 7 analysed Tharwani Realtors projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Tharwani Pristinea Tharwani Realtors · Kharghar / Taloja / Kamothe | 63 | 9.8% | 5.4% | 9.1% | ₹9,300 est. | ₹60.5 L | Under construction Jun 2030 |
| Tharwani Palladian Tharwani Realtors · Kharghar / Taloja / Kamothe | 58 | 8.6% | 3.9% | 5.0% | ₹9,300 est. | ₹60.5 L | Under construction Sep 2026 |
| Tharwani Stella Phase II Tharwani Realtors · Dombivli / Palava / Kalyan–Shil Road | 45 | 8.3% | 3.0% | 5.1% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2029 |
| Tharwani Stella Phase 1 Tharwani Realtors · Dombivli / Palava / Kalyan–Shil Road | 42 | 7.9% | 2.4% | 3.9% | ₹6,600 est. | ₹42.9 L | Under construction Dec 2028 |
| Tharwani Parkglen Phase I Tharwani Realtors · Kalyan / Titwala / Ulhasnagar | 37 | 7.8% | 1.9% | 3.6% | ₹6,200 est. | ₹40.3 L | Under construction Jun 2031 |
| Tharwani Parkglen Phase II Tharwani Realtors · Kalyan / Titwala / Ulhasnagar | 35 | 7.6% | 2.1% | 4.4% | ₹6,200 est. | ₹40.3 L | Under construction Jun 2032 |
| Tharwani Millennium City Phase II Tharwani Realtors · Ambernath / Badlapur | 31 | 6.5% | 1.1% | 1.4% | ₹4,900 est. | ₹31.9 L | Ready |
Where Tharwani Realtors builds
Questions people ask
Is Tharwani Realtors a reliable builder?
MahaRERA filings as of September 11, 2026: 88% of registrations needed no extension; 1 of 6 under-construction projects are past their original completion date by 1 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Tharwani Realtors project is the best investment?
Tharwani Pristinea in Kharghar / Taloja / Kamothe scores highest at 63/100 with projected growth 9.8% a year and cash-flow IRR 9.1%. The median Tharwani Realtors project scores 42.
Is Tharwani Realtors delaying possession?
1 under-construction Tharwani Realtors projects are past their original RERA completion date: Tharwani Palladian (1 months). Extensions filed with RERA are listed on each project page.
Where does Tharwani Realtors build?
Kharghar / Taloja / Kamothe, Mumbai (2), Dombivli / Palava / Kalyan–Shil Road, Mumbai (2), Kalyan / Titwala / Ulhasnagar, Mumbai (2), Ambernath / Badlapur, Mumbai (1). Median price ₹6,600 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.