Is Tulip Infratech a reliable builder?
7 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.
Tulip Infratech in one paragraph
Tulip Infratech has a weak delivery record in Haryana RERA (Gurugram) filings: 48% of registrations needed no extension (3 of 7 analysed Gurugram registrations needed no extension (2 lapsed)). 2 of 5 under-construction projects are past their original RERA completion date, by 52 months on average (worst 70). The median Tulip Infratech project scores 55/100 on investment merit (above the Gurugram average); the best, Tulip Monsella And Tulip Attila, scores 63.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Tulip Violet Phase-II Sohna Road and Southern Peripheral Road | 70 | 0 | 100% of schedule · — | 0 | 45 |
| Tulip Purple Phase 2 Sohna Road and Southern Peripheral Road | 34 | 0 | 100% of schedule · — | 0 | 45 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Tulip Infratech projects
All 7 analysed Tulip Infratech projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Tulip Monsella And Tulip Attila Tulip Infratech · Golf Course Road | 63 | 8.8% | 5.3% | 9.1% | ₹20,850 est. | ₹2.40 Cr | Under construction Dec 2030 |
| Tulip Violet Tulip Infratech · Sohna Road and Southern Peripheral Road | 57 | 9.6% | 7.1% | 13.8% | ₹11,100 est. | ₹1.97 Cr | Under construction Dec 2032 |
| Tulip Yellow Tulip Infratech · Sohna Road and Southern Peripheral Road | 57 | 8.4% | 5.5% | 7.1% | ₹11,800 est. | ₹72.0 L | Ready |
| Tulip Crimson Tulip Infratech · Sohna Road and Southern Peripheral Road | 55 | 9.8% | 6.5% | 12.2% | ₹11,100 est. | ₹2.46 Cr | Under construction Mar 2032 |
| Tulip Lemon Tulip Infratech · Sohna Road and Southern Peripheral Road | 51 | 8.4% | 4.4% | 5.8% | ₹11,800 est. | ₹4.91 Cr | Ready |
| Tulip Purple Phase 2 Tulip Infratech · Sohna Road and Southern Peripheral Road | 45 | 8.8% | 4.1% | 5.3% | ₹11,100 est. | ₹1.28 Cr | Under construction Dec 2023 |
| Tulip Violet Phase-II Tulip Infratech · Sohna Road and Southern Peripheral Road | 45 | 8.8% | 4.1% | 5.3% | ₹11,100 est. | ₹1.28 Cr | Under construction Dec 2020 |
Where Tulip Infratech builds
Questions people ask
Is Tulip Infratech a reliable builder?
Haryana RERA (Gurugram) filings as of September 11, 2026: 48% of registrations needed no extension; 2 of 5 under-construction projects are past their original completion date by 52 months on average; 2 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Tulip Infratech project is the best investment?
Tulip Monsella And Tulip Attila in Golf Course Road scores highest at 63/100 with projected growth 8.8% a year and cash-flow IRR 9.1%. The median Tulip Infratech project scores 55.
Is Tulip Infratech delaying possession?
2 under-construction Tulip Infratech projects are past their original RERA completion date: Tulip Violet Phase-II (70 months), Tulip Purple Phase 2 (34 months). Extensions filed with RERA are listed on each project page.
Where does Tulip Infratech build?
Sohna Road and Southern Peripheral Road, Gurugram (6), Golf Course Road, Gurugram (1). Median price ₹11,100 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.