Is Urbando Housing a reliable builder?
5 projects analysed in Chennai from Tamil Nadu RERA filings, as of September 11, 2026.
Urbando Housing in one paragraph
Urbando Housing has a strong delivery record in Tamil Nadu RERA filings: 85% of registrations needed no extension (5 of 5 analysed Chennai registrations needed no extension). 1 of 3 under-construction projects are past their original RERA completion date, by 27 months on average (worst 27). The median Urbando Housing project scores 50/100 on investment merit (below the Chennai average); the best, Urbando Evorise, scores 53.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Chennai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Altea Velachery / Pallikaranai / Medavakkam / Madipakkam | 27 | 0 | 100% of schedule · — | 0 | 39 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Urbando Housing projects
All 5 analysed Urbando Housing projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Urbando Evorise Urbando Housing · OMR IT corridor | 53 | 7.6% | 2.6% | 5.5% | ₹6,200 est. | ₹79.4 L | Under construction Dec 2032 |
| Altea Urbando Housing · Velachery / Pallikaranai / Medavakkam / Madipakkam | 50 | 6.3% | 1.3% | 1.7% | ₹6,800 est. | ₹72.4 L | Ready |
| Urbando Eterna Urbando Housing · OMR IT corridor | 50 | 6.4% | 1.5% | 1.9% | ₹6,600 est. | ₹70.3 L | Ready |
| Kosmos Orbiz Urbando Housing · Outer OMR | 40 | 7.8% | 0.7% | 1.2% | ₹4,600 est. | ₹49.0 L | Under construction Dec 2029 |
| Altea Urbando Housing · Velachery / Pallikaranai / Medavakkam / Madipakkam | 39 | 6.7% | 0.2% | 0.2% | ₹6,400 est. | ₹68.2 L | Under construction Jul 2024 |
Where Urbando Housing builds
Questions people ask
Is Urbando Housing a reliable builder?
Tamil Nadu RERA filings as of September 11, 2026: 85% of registrations needed no extension; 1 of 3 under-construction projects are past their original completion date by 27 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Urbando Housing project is the best investment?
Urbando Evorise in OMR IT corridor scores highest at 53/100 with projected growth 7.6% a year and cash-flow IRR 5.5%. The median Urbando Housing project scores 50.
Is Urbando Housing delaying possession?
1 under-construction Urbando Housing projects are past their original RERA completion date: Altea (27 months). Extensions filed with RERA are listed on each project page.
Where does Urbando Housing build?
OMR IT corridor, Chennai (2), Velachery / Pallikaranai / Medavakkam / Madipakkam, Chennai (2), Outer OMR, Chennai (1). Median price ₹6,400 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.