Developer scorecard · #87 in Mumbai by RERA registrations

Is Yash Infra a reliable builder?

7 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Yash Infra in one paragraph

Yash Infra has a strong delivery record in MahaRERA filings: 78% of registrations needed no extension (6 of 7 analysed Mumbai registrations needed no extension). 2 of 5 under-construction projects are past their original RERA completion date, by 7 months on average (worst 10). The median Yash Infra project scores 50/100 on investment merit (below the Mumbai average); the best, Veer Hills, scores 62.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.

Projects analysed
7
2 ready · 5 under construction
On-time rate
78%
registrations with no extension filed
Past RERA date
2 / 5
avg 7 months over
Extensions filed
1
1 projects
Cities
1
Mumbai
Red flags
3
across due-diligence reports
Median score
50
best 62
Median growth / yr
7.5%
5-yr projection
Median price / sq ft
₹12,500
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Satyaneelayam Co Op HSg Society
Thane West
100100% of schedule · —050
Veer Galaxy
Thane West
31100% of schedule · —046

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Yash Infra projects

All 7 analysed Yash Infra projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Veer Hills
Yash Infra · Thane West
628.9%4.9%8.6%₹12,500 est.₹81.3 LUnder construction
Dec 2030
Veer Yashodeep
Yash Infra · Thane West
587.9%3.5%5.2%₹12,500 est.₹81.3 LUnder construction
Jan 2028
Veer Devika
Yash Infra · Thane East / Kalwa / Mumbra / Diva
548.0%2.8%4.4%₹8,950 est.₹58.2 LUnder construction
Mar 2029
Satyaneelayam Co Op HSg Society
Yash Infra · Thane West
507.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Dec 2025
Ramleela Co-operative Housing Society Limited
Yash Infra · Thane East / Kalwa / Mumbra / Diva
466.8%2.7%3.5%₹9,500 est.₹61.8 LReady
Veer Galaxy
Yash Infra · Thane West
467.5%2.8%3.6%₹12,500 est.₹81.3 LUnder construction
Jul 2026
Mahalaxmi Residency
Yash Infra · Ambernath / Badlapur
306.5%1.1%1.4%₹4,900 est.₹31.9 LReady

Where Yash Infra builds

Questions people ask

Is Yash Infra a reliable builder?

MahaRERA filings as of September 11, 2026: 78% of registrations needed no extension; 2 of 5 under-construction projects are past their original completion date by 7 months on average; 1 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Yash Infra project is the best investment?

Veer Hills in Thane West scores highest at 62/100 with projected growth 8.9% a year and cash-flow IRR 8.6%. The median Yash Infra project scores 50.

Is Yash Infra delaying possession?

2 under-construction Yash Infra projects are past their original RERA completion date: Satyaneelayam Co Op HSg Society (10 months), Veer Galaxy (3 months). Extensions filed with RERA are listed on each project page.

Where does Yash Infra build?

Thane West, Mumbai (4), Thane East / Kalwa / Mumbra / Diva, Mumbai (2), Ambernath / Badlapur, Mumbai (1). Median price ₹12,500 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.