8 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
Ajmera in one paragraph
Ajmera has a weak delivery record in Karnataka RERA filings: 44% of registrations needed no extension (3 of 8 crawled Bengaluru registrations needed no extension). 3 of 6 under-construction projects are past their original RERA completion date, by 26 months on average (worst 36). The promoter entity carries 7 complaints at K-RERA across its projects. The median Ajmera project scores 47/100 on investment merit (below the Bengaluru average); the best, Ajmera Marina, scores 66.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Ajmera Nucleus Phase 1 (residential - A & B Wing) Electronic City / Hosur Road / Bommasandra | 36 | 1 | 100% of schedule · — | 0 | 31 |
| Ajmera Nucleus Phase 2 (residential -C Wing) Electronic City / Hosur Road / Bommasandra | 30 | 1 | 100% of schedule · — | 0 | 31 |
| Ajmera Florenza Yelahanka / Jakkur / Airport corridor | 12 | 1 | 100% of schedule · — | 1 | 50 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Ajmera projects
All 8 analysed Ajmera projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Ajmera Marina Ajmera · Yelahanka / Jakkur / Airport corridor | 66 | 11.1% | 7.7% | 12.0% | ₹10,350 est. | ₹1.20 Cr | Under construction Dec 2028 |
| Ajmera Lugaano - Ab Wing Ajmera · Yelahanka / Jakkur / Airport corridor | 61 | 10.1% | 6.6% | 8.3% | ₹10,350 est. | ₹86.4 L | Under construction Sep 2026 |
| Ajmera Florenza Ajmera · Yelahanka / Jakkur / Airport corridor | 50 | 10.1% | 6.3% | 7.9% | ₹10,350 est. | ₹1.19 Cr | Under construction Sep 2025 |
| Ajmera Iris Ajmera · Electronic City / Hosur Road / Bommasandra | 47 | 8.0% | 3.2% | 4.1% | ₹7,550 est. | ₹40.0 L | Under construction Dec 2026 |
| Ajmera Annex Residential Ajmera · Electronic City / Hosur Road / Bommasandra | 45 | 7.6% | 3.6% | 4.6% | ₹7,800 est. | ₹89.3 L | Ready |
| Ajmera Annex Commercial Ajmera · Electronic City / Hosur Road / Bommasandra | 45 | 7.6% | 3.2% | 4.1% | ₹7,800 est. | ₹1.46 Cr | Ready |
| Ajmera Nucleus Phase 1 (residential - A & B Wing) Ajmera · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 2.5% | 3.1% | ₹7,350 est. | ₹87.8 L | Under construction Sep 2023 |
| Ajmera Nucleus Phase 2 (residential -C Wing) Ajmera · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 2.8% | 3.6% | ₹7,350 est. | ₹59.2 L | Under construction Mar 2024 |
Where Ajmera builds
Ajmera compared with other developers
Questions people ask
Is Ajmera a reliable builder?
Karnataka RERA filings as of September 11, 2026: 44% of registrations needed no extension; 3 of 6 under-construction projects are past their original completion date by 26 months on average; 5 extensions filed across 5 projects; 7 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which Ajmera project is the best investment?
Ajmera Marina in Yelahanka / Jakkur / Airport corridor scores highest at 66/100 with projected growth 11.1% a year and cash-flow IRR 12.0%. The median Ajmera project scores 47.
Is Ajmera delaying possession?
3 under-construction Ajmera projects are past their original RERA completion date: Ajmera Nucleus Phase 1 (residential - A & B Wing) (36 months), Ajmera Nucleus Phase 2 (residential -C Wing) (30 months), Ajmera Florenza (12 months). Extensions filed with RERA are listed on each project page.
Where does Ajmera build in Bengaluru?
Electronic City / Hosur Road / Bommasandra (5), Yelahanka / Jakkur / Airport corridor (3). Median price ₹7,800 per sq ft across analysed projects.