Is Electronic City / Hosur Road / Bommasandra good for investment?
115 RERA-registered projects scored on one model, as of September 11, 2026. Prices, growth, yields, supply and the best-scored homes.
Electronic City / Hosur Road / Bommasandra in one paragraph
On PropertyLens's model, Electronic City / Hosur Road / Bommasandra is a weaker-than-average place to buy in Bengaluru right now: the median analysed project scores 41/100 (below the Bengaluru average), with projected price growth of 9.1% a year over five years and a median gross rental yield of 3.5%. Unsold homes would take about 25 months to absorb at the current sales pace, which is heavy supply and caps near-term price growth. 54 of 88 under-construction projects here are past their original RERA completion date, so weight the developer's record heavily.
Median of 115 projects; the spread inside the area is wide, so the ranked list below matters more than the average.
Best-scored projects in Electronic City / Hosur Road / Bommasandra
All 115 analysed projects in Electronic City / Hosur Road / Bommasandra
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Casagrand Vivacity Casagrand · Electronic City / Hosur Road / Bommasandra | 65 | 9.6% | 4.8% | 7.5% | ₹7,350 est. | ₹41.9 L | Under construction Apr 2029 |
| Purva Silversky Puravankara · Electronic City / Hosur Road / Bommasandra | 65 | 10.0% | 4.5% | 7.7% | ₹7,350 est. | ₹1.17 Cr | Under construction Jul 2030 |
| Primetownn Phase 1 Elite Estates · Electronic City / Hosur Road / Bommasandra | 64 | 11.0% | 9.1% | 15.8% | ₹3,200 est. | ₹37.1 L | Under construction Dec 2030 |
| Prestige Suncrest Prestige · Electronic City / Hosur Road / Bommasandra | 62 | 9.4% | 4.2% | 6.1% | ₹7,350 est. | ₹45.2 L | Under construction Sep 2028 |
| Adarsh Forest Glen Akarshak Realty · Electronic City / Hosur Road / Bommasandra | 60 | 11.2% | 7.3% | 11.6% | ₹3,200 est. | ₹38.4 L | Under construction Nov 2027 |
| Central Avenue Phase II Pionier Projects · Electronic City / Hosur Road / Bommasandra | 60 | 11.3% | 7.3% | 11.7% | ₹3,200 est. | ₹38.4 L | Under construction Nov 2027 |
| Lakecity Phase 1 Elite Estates · Electronic City / Hosur Road / Bommasandra | 60 | 11.0% | 9.1% | 15.8% | ₹3,200 est. | ₹37.8 L | Under construction Dec 2030 |
| Assetz Ren & Rei Assetz · Electronic City / Hosur Road / Bommasandra | 59 | 9.1% | 3.7% | 5.9% | ₹7,350 est. | ₹1.27 Cr | Under construction Jan 2029 |
| The Citadel Pionier Projects · Electronic City / Hosur Road / Bommasandra | 58 | 11.0% | 9.1% | 15.8% | ₹3,200 est. | ₹37.8 L | Under construction Dec 2030 |
| The Roots By Elegance Infra Pionier Projects · Electronic City / Hosur Road / Bommasandra | 58 | 10.9% | 6.5% | 10.0% | ₹3,200 est. | ₹34.4 L | Under construction Jul 2027 |
| Pionier Daffodil Pionier Projects · Electronic City / Hosur Road / Bommasandra | 56 | 9.9% | 6.1% | 9.7% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2027 |
| Adarsh Welkin Park Phase 2 Akarshak Realty · Electronic City / Hosur Road / Bommasandra | 56 | 9.1% | 4.0% | 6.7% | ₹5,850 est. | ₹37.4 L | Under construction Mar 2030 |
| Greensquare Pionier Projects · Electronic City / Hosur Road / Bommasandra | 54 | 9.9% | 6.1% | 9.7% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2027 |
| Elements Pionier Projects · Electronic City / Hosur Road / Bommasandra | 53 | 9.9% | 6.1% | 9.7% | ₹3,200 est. | ₹38.4 L | Under construction Oct 2027 |
| Shriram Sapphire Shriram Properties · Electronic City / Hosur Road / Bommasandra | 53 | 9.1% | 4.2% | 6.6% | ₹7,350 est. | ₹68.7 L | Under construction Nov 2028 |
| Sobha Silicon Oasis Phase 4 Wing 9 Sobha · Electronic City / Hosur Road / Bommasandra | 52 | 7.6% | 3.4% | 4.3% | ₹7,800 est. | ₹1.22 Cr | Ready |
| Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6 Sobha · Electronic City / Hosur Road / Bommasandra | 52 | 7.6% | 3.4% | 4.4% | ₹7,800 est. | ₹1.15 Cr | Ready |
| Sobha Silicon Oasis Phase 5 Wing 10 & 11 Sobha · Electronic City / Hosur Road / Bommasandra | 52 | 7.6% | 3.2% | 4.1% | ₹7,800 est. | ₹1.48 Cr | Ready |
| Sobha Silicon Oasis Phase 3 Wing 8 Sobha · Electronic City / Hosur Road / Bommasandra | 52 | 7.6% | 3.4% | 4.3% | ₹7,800 est. | ₹1.22 Cr | Ready |
| Mayfairre Pionier Projects · Electronic City / Hosur Road / Bommasandra | 51 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹37.9 L | Under construction Dec 2026 |
| Sobha Silicon Oasis Phase 7 Block 2 and 3 (Row House No. 9, 10) Sobha · Electronic City / Hosur Road / Bommasandra | 50 | 7.6% | 3.1% | 4.0% | ₹7,800 est. | ₹1.59 Cr | Ready |
| SNN Raj Greenbay SNN · Electronic City / Hosur Road / Bommasandra | 50 | 7.6% | 4.7% | 5.8% | ₹7,800 est. | ₹32.4 L | Ready |
| Ds Max Sahara Grand DS-MAX · Electronic City / Hosur Road / Bommasandra | 50 | 8.5% | 3.2% | 5.0% | ₹5,850 est. | ₹53.5 L | Under construction Jan 2029 |
| Prestige King's County Prestige · Electronic City / Hosur Road / Bommasandra | 49 | 9.7% | 5.0% | 7.2% | ₹4,150 est. | ₹49.8 L | Under construction Oct 2026 |
| Sobha Silicon Oasis Phase 2 Wing 7 Sobha · Electronic City / Hosur Road / Bommasandra | 49 | 9.1% | 3.3% | 4.1% | ₹7,350 est. | ₹1.15 Cr | Under construction Jan 2020 |
| Assetz Muse & Maison Assetz · Electronic City / Hosur Road / Bommasandra | 49 | 8.4% | 3.2% | 5.4% | ₹7,350 est. | ₹1.25 Cr | Under construction Mar 2030 |
| Adarsh Welkin Park Phase 1 Akarshak Realty · Electronic City / Hosur Road / Bommasandra | 48 | 8.4% | 3.3% | 4.7% | ₹6,000 est. | ₹53.1 L | Under construction Dec 2027 |
| Sobha Silicon Oasis Phase 6 Block 2 and 3 (Row house No. 1 to 8 & 11 to 17) Sobha · Electronic City / Hosur Road / Bommasandra | 48 | 9.4% | 3.1% | 4.0% | ₹7,350 est. | ₹2.48 Cr | Under construction Apr 2019 |
| Aswani Aaeesha B Wing Aswani Properties · Electronic City / Hosur Road / Bommasandra | 48 | 7.6% | 4.6% | 5.6% | ₹6,200 est. | ₹31.6 L | Ready |
| Mahaveer Edenfield Mahaveer · Electronic City / Hosur Road / Bommasandra | 48 | 9.1% | 4.3% | 6.2% | ₹3,400 est. | ₹55.6 L | Ready |
| Samruddhi Sunshine Samruddhi Realty · Electronic City / Hosur Road / Bommasandra | 47 | 8.2% | 2.3% | 2.9% | ₹6,000 est. | ₹90.0 L | Under construction Jun 2018 |
| M5 Echelon Mahendra Homes · Electronic City / Hosur Road / Bommasandra | 47 | 9.1% | 4.3% | 8.7% | ₹5,850 est. | ₹84.5 L | Under construction Dec 2031 |
| Ajmera Iris Ajmera · Electronic City / Hosur Road / Bommasandra | 47 | 8.0% | 3.2% | 4.1% | ₹7,550 est. | ₹40.0 L | Under construction Dec 2026 |
| Mahaveer Ranches Phase II Mahaveer · Electronic City / Hosur Road / Bommasandra | 46 | 9.7% | 3.6% | 4.5% | ₹5,850 est. | ₹93.6 L | Under construction Mar 2025 |
| The green terraces Keya Homes · Electronic City / Hosur Road / Bommasandra | 46 | 7.6% | 3.9% | 4.9% | ₹6,200 est. | ₹55.5 L | Ready |
| The Lake View Address – Phase 3 Indiabuild Realty · Electronic City / Hosur Road / Bommasandra | 46 | 9.1% | 4.3% | 6.2% | ₹3,400 est. | ₹40.8 L | Ready |
| Adarsh Welkin Park Villas Adarsh Developers · Electronic City / Hosur Road / Bommasandra | 46 | 9.1% | 3.4% | 5.0% | ₹7,350 est. | ₹2.10 Cr | Under construction Oct 2027 |
| Aswani Aaeesha A Wing Aswani Properties · Electronic City / Hosur Road / Bommasandra | 46 | 9.2% | 4.3% | 5.2% | ₹5,850 est. | ₹29.8 L | Under construction Nov 2019 |
| Ajmera Annex Residential Ajmera · Electronic City / Hosur Road / Bommasandra | 45 | 7.6% | 3.6% | 4.6% | ₹7,800 est. | ₹89.3 L | Ready |
| Ajmera Annex Commercial Ajmera · Electronic City / Hosur Road / Bommasandra | 45 | 7.6% | 3.2% | 4.1% | ₹7,800 est. | ₹1.46 Cr | Ready |
| The Hamptons Saiven Developers · Electronic City / Hosur Road / Bommasandra | 45 | 7.6% | 3.4% | 4.3% | ₹6,200 est. | ₹93.0 L | Ready |
| Orchid South Park Goyal & Co · Electronic City / Hosur Road / Bommasandra | 45 | 8.6% | 3.7% | 6.8% | ₹7,350 est. | ₹83.1 L | Under construction Apr 2031 |
| JRC Wild Woods Phase III JRC Projects · Electronic City / Hosur Road / Bommasandra | 45 | 7.8% | 2.7% | 4.2% | ₹6,000 est. | ₹52.2 L | Under construction Nov 2028 |
| Evershine NORTHEAST Apartments Evershine Dwellings · Electronic City / Hosur Road / Bommasandra | 45 | 7.4% | 3.8% | 4.7% | ₹6,200 est. | ₹51.5 L | Ready |
| Gopalan Lakefront Gopalan Enterprises · Electronic City / Hosur Road / Bommasandra | 45 | 9.7% | 3.8% | 4.7% | ₹5,850 est. | ₹72.2 L | Under construction Jun 2020 |
| Beverly Aveenue Pionier Projects · Electronic City / Hosur Road / Bommasandra | 45 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Sep 2024 |
| G R Gardenia G R Promoters · Electronic City / Hosur Road / Bommasandra | 44 | 7.6% | 3.7% | 4.7% | ₹6,200 est. | ₹65.7 L | Ready |
| Grand Icon 3 Icon Infra Shelters · Electronic City / Hosur Road / Bommasandra | 44 | 9.1% | 4.3% | 6.2% | ₹3,400 est. | ₹40.8 L | Ready |
| Ranka Countryside Ranka · Electronic City / Hosur Road / Bommasandra | 43 | 9.1% | 4.3% | 6.2% | ₹3,400 est. | ₹58.8 L | Ready |
| Ds-Max Star Line DS-MAX · Electronic City / Hosur Road / Bommasandra | 43 | 7.6% | 3.4% | 4.3% | ₹6,200 est. | ₹93.0 L | Ready |
| Eterrnia Pionier Projects · Electronic City / Hosur Road / Bommasandra | 43 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹32.3 L | Under construction Dec 2025 |
| Mahaveer Ranches Phase I Mahaveer · Electronic City / Hosur Road / Bommasandra | 42 | 8.8% | 2.8% | 3.5% | ₹6,000 est. | ₹89.1 L | Under construction Dec 2018 |
| Concorde Epitome Concorde · Electronic City / Hosur Road / Bommasandra | 42 | 7.6% | 2.9% | 3.8% | ₹7,800 est. | ₹3.01 Cr | Ready |
| Shriram Summitt Shriram Properties · Electronic City / Hosur Road / Bommasandra | 42 | 9.3% | 3.6% | 4.5% | ₹7,350 est. | ₹95.5 L | Under construction Dec 2019 |
| The lake Terraces Keya Homes · Electronic City / Hosur Road / Bommasandra | 42 | 7.2% | 4.0% | 4.9% | ₹6,200 est. | ₹40.3 L | Ready |
| Ds Max Sky Sanman DS-MAX · Electronic City / Hosur Road / Bommasandra | 42 | 8.4% | 3.2% | 5.5% | ₹5,850 est. | ₹52.9 L | Under construction Jan 2030 |
| Mahendra Aarya Mahendra Homes · Electronic City / Hosur Road / Bommasandra | 42 | 7.5% | 3.6% | 4.5% | ₹6,200 est. | ₹62.9 L | Ready |
| Mahendra AARNA Mahendra Homes · Electronic City / Hosur Road / Bommasandra | 41 | 7.6% | 3.6% | 4.5% | ₹6,200 est. | ₹74.1 L | Ready |
| Keerthi Royal Palms-Phase-I Keerthi Estates · Electronic City / Hosur Road / Bommasandra | 41 | 8.1% | 2.2% | 2.8% | ₹6,000 est. | ₹90.0 L | Under construction Mar 2019 |
| Bren Park City Bren Corporation · Electronic City / Hosur Road / Bommasandra | 41 | 8.5% | 3.5% | 5.5% | ₹7,350 est. | ₹43.7 L | Under construction Jun 2029 |
| Mahendra Solterra Aarya Phase-2 Mahendra Homes · Electronic City / Hosur Road / Bommasandra | 41 | 8.6% | 3.4% | 6.3% | ₹5,850 est. | ₹84.2 L | Under construction Dec 2030 |
| DS Max Silverwood DS-MAX · Electronic City / Hosur Road / Bommasandra | 41 | 7.6% | 3.4% | 4.3% | ₹6,200 est. | ₹93.0 L | Ready |
| Shravanthi Prakruti Shravanthi · Electronic City / Hosur Road / Bommasandra | 41 | 8.0% | 2.5% | 3.7% | ₹5,850 est. | ₹68.4 L | Under construction Mar 2028 |
| Ds Max Starry DS-MAX · Electronic City / Hosur Road / Bommasandra | 41 | 7.6% | 3.4% | 4.3% | ₹6,200 est. | ₹93.0 L | Ready |
| DS MAX Silver Oak DS-MAX · Electronic City / Hosur Road / Bommasandra | 40 | 7.6% | 3.4% | 4.3% | ₹6,200 est. | ₹93.0 L | Ready |
| Shriram Summitt Shriram Properties · Electronic City / Hosur Road / Bommasandra | 40 | 9.3% | 3.6% | 4.6% | ₹7,350 est. | ₹94.4 L | Under construction Dec 2019 |
| Shriram Summitt Shriram Properties · Electronic City / Hosur Road / Bommasandra | 40 | 9.3% | 3.6% | 4.6% | ₹7,350 est. | ₹91.1 L | Under construction Dec 2019 |
| Ramky Lumina Ramky Estates · Electronic City / Hosur Road / Bommasandra | 40 | 8.3% | 3.0% | 4.7% | ₹5,850 est. | ₹64.6 L | Under construction Dec 2028 |
| Shriram Summitt Shriram Properties · Electronic City / Hosur Road / Bommasandra | 40 | 9.3% | 3.6% | 4.6% | ₹7,350 est. | ₹96.7 L | Under construction Dec 2019 |
| Reliaable Dollar Collony Phase 1C RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Jan 2024 |
| Reliaable Dollar Collony Phase1B RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Jan 2024 |
| RELIAABLE DOLLAR COLLONY Phase 2F RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction May 2021 |
| RELIAABLE DOLLAR COLLONY Phase 2E RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction May 2021 |
| Reliaable DOLLAR COLLONY Phase 2D RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2021 |
| Reliaable DOLLAR COLLONY Phase 2C RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2021 |
| Reliaable Residenza Phase 1B Reliaable · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2023 |
| Reliaable Dollar Collony Phase 2g Reliaable · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Jan 2024 |
| Reliaable Dollar Collony Phase 1A Reliaable · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2021 |
| Reliaable Residenza Phase 1A Reliaable · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Dec 2022 |
| RELIAABLE DOLLAR COLLONY Phase 2B RD Buildtech · Electronic City / Hosur Road / Bommasandra | 39 | 9.5% | 4.8% | 6.9% | ₹3,300 est. | ₹39.6 L | Under construction May 2021 |
| Skylark Royaume Skylark · Electronic City / Hosur Road / Bommasandra | 39 | 8.4% | 3.1% | 4.9% | ₹5,850 est. | ₹64.6 L | Under construction Dec 2028 |
| Reliaable Prime City Phase 1A RD Buildtech · Electronic City / Hosur Road / Bommasandra | 38 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Aug 2023 |
| Aratt Milano Arattukulam Developers · Electronic City / Hosur Road / Bommasandra | 38 | 8.7% | 2.7% | 3.4% | ₹6,000 est. | ₹90.0 L | Under construction Mar 2019 |
| Reliaable Residenza Phase 1 RD Buildtech · Electronic City / Hosur Road / Bommasandra | 38 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Sep 2022 |
| Evershine StonePark Evershine Dwellings · Electronic City / Hosur Road / Bommasandra | 37 | 8.5% | 2.5% | 4.4% | ₹5,850 est. | ₹1.41 Cr | Under construction Sep 2030 |
| Sai Crystal Adarsh Developers · Electronic City / Hosur Road / Bommasandra | 37 | 9.6% | 4.0% | 5.1% | ₹7,350 est. | ₹77.9 L | Under construction Jun 2025 |
| Reliaable E-City Plan-3 RD Buildtech · Electronic City / Hosur Road / Bommasandra | 37 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Sep 2025 |
| Reliaable E City Plan 2 RD Buildtech · Electronic City / Hosur Road / Bommasandra | 37 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Sep 2025 |
| Reliaable E City Plan 1 Reliaable · Electronic City / Hosur Road / Bommasandra | 37 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹32.5 L | Under construction Oct 2025 |
| Reliaable Prime City PHASE 1 RD Buildtech · Electronic City / Hosur Road / Bommasandra | 37 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Sep 2024 |
| Mahaveer Palatium Annex Sy No 28-1 Mahaveer · Electronic City / Hosur Road / Bommasandra | 36 | 9.1% | 4.3% | 6.2% | ₹3,400 est. | ₹40.8 L | Ready |
| Bellezea Phase V Nambiar Builders · Electronic City / Hosur Road / Bommasandra | 36 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹1.28 Cr | Under construction Jun 2025 |
| Icon Micasa Icon Infra Shelters · Electronic City / Hosur Road / Bommasandra | 36 | 8.2% | 2.7% | 3.5% | ₹6,000 est. | ₹49.2 L | Under construction Dec 2026 |
| Bellezea-Phase IV Nambiar Builders · Electronic City / Hosur Road / Bommasandra | 36 | 7.6% | 1.6% | 2.1% | ₹6,000 est. | ₹90.0 L | Under construction Jan 2027 |
| “Townsville” GM Infinite · Electronic City / Hosur Road / Bommasandra | 35 | 9.4% | 2.9% | 3.7% | ₹5,850 est. | ₹1.91 Cr | Under construction Oct 2020 |
| Ds Max Sahara DS-MAX · Electronic City / Hosur Road / Bommasandra | 34 | 8.0% | 2.1% | 2.6% | ₹5,850 est. | ₹87.8 L | Under construction Dec 2024 |
| Godrej Nurture Godrej Properties · Electronic City / Hosur Road / Bommasandra | 34 | 8.0% | 3.1% | 3.9% | ₹7,350 est. | ₹45.6 L | Under construction Dec 2025 |
| Skylark Dasos Skylark · Electronic City / Hosur Road / Bommasandra | 34 | 8.0% | 2.3% | 2.9% | ₹5,850 est. | ₹66.4 L | Under construction Sep 2023 |
| Shriram Summitt Shriram Properties · Electronic City / Hosur Road / Bommasandra | 34 | 9.3% | 3.6% | 4.6% | ₹7,350 est. | ₹96.7 L | Under construction Dec 2020 |
| Ramky One Karnival Ramky Estates · Electronic City / Hosur Road / Bommasandra | 34 | 7.4% | 3.2% | 4.1% | ₹6,200 est. | ₹93.0 L | Ready |
| The Lake View Address- Phase 1 Indiabuild Realty · Electronic City / Hosur Road / Bommasandra | 33 | 8.8% | 2.5% | 3.2% | ₹6,000 est. | ₹1.26 Cr | Under construction Apr 2021 |
| Mahaveer Turquoise Reddy Structures · Electronic City / Hosur Road / Bommasandra | 33 | 8.0% | 2.9% | 3.5% | ₹5,850 est. | ₹38.9 L | Under construction Sep 2022 |
| Sipani Viveza Sipani · Electronic City / Hosur Road / Bommasandra | 33 | 8.0% | 2.3% | 2.8% | ₹5,850 est. | ₹73.7 L | Under construction Nov 2024 |
| The Lake View Address Phase 4 Indiabuild Realty · Electronic City / Hosur Road / Bommasandra | 32 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹51.4 L | Under construction Mar 2025 |
| Ajmera Nucleus Phase 1 (residential - A & B Wing) Ajmera · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 2.5% | 3.1% | ₹7,350 est. | ₹87.8 L | Under construction Sep 2023 |
| Ajmera Nucleus Phase 2 (residential -C Wing) Ajmera · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 2.8% | 3.6% | ₹7,350 est. | ₹59.2 L | Under construction Mar 2024 |
| Pride Gateway Pride & Expert Properties · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 1.8% | 2.3% | ₹5,850 est. | ₹1.23 Cr | Under construction Mar 2024 |
| Mahendra AARNA 5 Mahendra Homes · Electronic City / Hosur Road / Bommasandra | 31 | 8.0% | 2.1% | 2.6% | ₹5,850 est. | ₹87.8 L | Under construction Dec 2021 |
| I Towers Exente Kolte-Patil · Electronic City / Hosur Road / Bommasandra | 30 | 8.0% | 2.4% | 3.0% | ₹7,350 est. | ₹95.5 L | Under construction Apr 2024 |
| Mahaveer Palatium Sy No 41 Reddy Structures · Electronic City / Hosur Road / Bommasandra | 30 | 9.5% | 4.8% | 6.9% | ₹3,200 est. | ₹38.4 L | Under construction Aug 2022 |
| Ds Max Sky Classic DS-MAX · Electronic City / Hosur Road / Bommasandra | 29 | 8.0% | 2.1% | 2.6% | ₹5,850 est. | ₹87.8 L | Under construction Sep 2023 |
| Mahaveer Trident Reddy Structures · Electronic City / Hosur Road / Bommasandra | 28 | 8.0% | 2.4% | 3.0% | ₹5,850 est. | ₹64.1 L | Under construction Mar 2025 |
| The Lake View Address - Apartments Indiabuild Realty · Electronic City / Hosur Road / Bommasandra | 28 | 8.0% | 2.1% | 2.6% | ₹5,850 est. | ₹87.8 L | Under construction Jan 2023 |
| Mahaveer Palatium Reddy Structures · Electronic City / Hosur Road / Bommasandra | 27 | 10.1% | 5.3% | 7.6% | ₹3,300 est. | ₹55.8 L | Under construction Aug 2020 |
| Shriram Liberty Square Shriram Properties · Electronic City / Hosur Road / Bommasandra | 26 | 8.0% | 2.8% | 3.5% | ₹7,350 est. | ₹59.9 L | Under construction Nov 2024 |
Price per sq ft in Electronic City / Hosur Road / Bommasandra: what the evidence says
| Date | ₹ / sq ft | Basis | Confidence |
|---|---|---|---|
| 2021-06 | ₹4,500 | blr (derived) | 40% |
| 2023-06 | ₹5,600 | blr (derived) | 45% |
| 2025-06 | ₹7,000 | blr (derived) | 50% |
| 2026-06 | ₹8,000 | blr (derived) | 50% |
That is 12.2% a year from 2021-06 to 2026-06. The model projects 9.1% a year from here; the growth story on each project page shows why.
Supply and demand from RERA filings
Karnataka RERA, 2026-09. Months of inventory = unsold homes ÷ monthly sales.
Infrastructure pipeline
| Project | Type | Status | Expected | Chance it lands on time | Price effect if it does |
|---|---|---|---|---|---|
| Yellow Line RV Road–Bommasandra (opened Aug 2025) | metro | operational | 2025 | 100% | +0.8% / yr |
| Satellite Town Ring Road | road | construction | 2028 | 60% | +0.6% / yr |
| Bengaluru suburban rail (K-RIDE) | rail | construction | 2029 | 50% | +0.6% / yr |
The growth model counts each event at its probability, not its promise. Dates are the latest public schedule.
Developers active in Electronic City / Hosur Road / Bommasandra
Ranked lists for Electronic City / Hosur Road / Bommasandra
Electronic City / Hosur Road / Bommasandra compared with other areas
Questions people ask
Is Electronic City / Hosur Road / Bommasandra good for investment?
On PropertyLens's model the median analysed project in Electronic City / Hosur Road / Bommasandra scores 41/100 (below the Bengaluru average), with projected price growth of 9.1% a year over five years, median price ₹5,850 per sq ft and gross rental yield 3.5%. 115 RERA-registered projects analysed as of September 11, 2026. The best-scored project is Casagrand Vivacity at 65.
What is the price per sq ft in Electronic City / Hosur Road / Bommasandra?
Median ₹5,850 per sq ft of super built-up area across analysed projects, modelled from comparables where developers file no price. Entry price for an analysed home is about ₹29.8 L; the median home is ₹59.9 L.
What rental yield can I expect in Electronic City / Hosur Road / Bommasandra?
Median gross yield 3.5% on the all-in cost of an analysed home, before maintenance, vacancy and tax. Net-wealth CAGR after every cost on an 8-year hold with a 75% loan is 3.6% at the median.
Are projects in Electronic City / Hosur Road / Bommasandra delayed?
54 of 88 under-construction projects are past the completion date in their original RERA registration, and unsold stock equals about 25 months of sales. Each project page shows extensions, construction against bookings and complaints.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.