Is Kamalraj Estate a reliable builder?
5 projects analysed in Pune from MahaRERA filings, as of September 11, 2026.
Kamalraj Estate in one paragraph
Kamalraj Estate has a mixed delivery record in MahaRERA filings: 72% of registrations needed no extension (4 of 5 analysed Pune registrations needed no extension). 1 of 4 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Kamalraj Estate project scores 45/100 on investment merit (below the Pune average); the best, Kamalraj Athens A, scores 50.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Pune; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Kamalraj Dattavihar E And H Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 10 | 1 | 100% of schedule · — | 0 | 31 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Kamalraj Estate projects
All 5 analysed Kamalraj Estate projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Kamalraj Athens A Kamalraj Estate · Wakad / Pimple Saudagar / Punawale / Tathawade / Rahatani | 50 | 8.2% | 3.0% | 4.1% | ₹7,150 est. | ₹53.6 L | Under construction Jun 2027 |
| KAMALRAJ AKSHARDHAM B and C BUILDING Kamalraj Estate · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 45 | 8.4% | 2.6% | 4.2% | ₹5,350 est. | ₹40.1 L | Under construction Dec 2028 |
| Kamalraj Akshardham A Building Kamalraj Estate · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 45 | 8.4% | 2.6% | 4.2% | ₹5,350 est. | ₹40.1 L | Under construction Dec 2028 |
| Kamalraj Dattavihar Central Kamalraj Estate · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 43 | 7.2% | 2.7% | 3.4% | ₹5,700 est. | ₹42.8 L | Ready |
| Kamalraj Dattavihar E And H Kamalraj Estate · Ravet / Kiwale / Moshi / Chikhali / Dehu Road | 31 | 7.6% | 1.4% | 1.7% | ₹5,350 est. | ₹40.1 L | Under construction Dec 2025 |
Where Kamalraj Estate builds
Questions people ask
Is Kamalraj Estate a reliable builder?
MahaRERA filings as of September 11, 2026: 72% of registrations needed no extension; 1 of 4 under-construction projects are past their original completion date by 10 months on average; 1 extensions filed across 1 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Kamalraj Estate project is the best investment?
Kamalraj Athens A in Wakad / Pimple Saudagar / Punawale / Tathawade / Rahatani scores highest at 50/100 with projected growth 8.2% a year and cash-flow IRR 4.1%. The median Kamalraj Estate project scores 45.
Is Kamalraj Estate delaying possession?
1 under-construction Kamalraj Estate projects are past their original RERA completion date: Kamalraj Dattavihar E And H (10 months). Extensions filed with RERA are listed on each project page.
Where does Kamalraj Estate build?
Ravet / Kiwale / Moshi / Chikhali / Dehu Road, Pune (4), Wakad / Pimple Saudagar / Punawale / Tathawade / Rahatani, Pune (1). Median price ₹5,350 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.