Is Kotibhaskar Infrastructures &Developers a reliable builder?
21 projects analysed in Pune from MahaRERA filings, as of September 11, 2026.
Kotibhaskar Infrastructures &Developers in one paragraph
Kotibhaskar Infrastructures &Developers has a mixed delivery record in MahaRERA filings: 70% of registrations needed no extension (15 of 21 analysed Pune registrations needed no extension). 4 of 14 under-construction projects are past their original RERA completion date, by 5 months on average (worst 12). The median Kotibhaskar Infrastructures &Developers project scores 56/100 on investment merit (above the Pune average); the best, Neelratna, scores 66.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Pune; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Indukiran Co-Op Housing Society Limited Kothrud / Erandwane / Bavdhan | 12 | 0 | 100% of schedule · — | 0 | 47 |
| Varsha Chsl Central Pune | 5 | 1 | 100% of schedule · — | 0 | 51 |
| Madhumati Chsl Central Pune | 1 | 1 | 100% of schedule · — | 0 | 58 |
| State Bank Of India Snehdeep Chsl Kothrud / Erandwane / Bavdhan | 1 | 1 | 100% of schedule · — | 0 | 53 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Kotibhaskar Infrastructures &Developers projects
All 21 analysed Kotibhaskar Infrastructures &Developers projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Neelratna Kotibhaskar Infrastructures &Developers · Central Pune | 66 | 9.6% | 6.1% | 10.0% | ₹11,750 est. | ₹88.1 L | Under construction Oct 2029 |
| Aparnali Kotibhaskar Infrastructures &Developers · Central Pune | 63 | 8.8% | 5.1% | 7.5% | ₹11,750 est. | ₹88.1 L | Under construction Dec 2027 |
| Chandrabhaga Kotibhaskar Infrastructures &Developers · Central Pune | 62 | 8.8% | 5.1% | 7.4% | ₹11,750 est. | ₹88.1 L | Under construction Feb 2028 |
| Shounak CHSL Kotibhaskar Infrastructures &Developers · Central Pune | 61 | 8.0% | 5.3% | 6.7% | ₹12,500 est. | ₹93.8 L | Ready |
| Shree Chsl Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 58 | 8.6% | 4.5% | 7.0% | ₹10,700 est. | ₹80.3 L | Under construction Dec 2028 |
| Aditya Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 58 | 8.2% | 4.1% | 6.1% | ₹10,700 est. | ₹80.3 L | Under construction Oct 2027 |
| Guruprasad Kunj Kotibhaskar Infrastructures &Developers · Central Pune | 58 | 8.4% | 4.4% | 5.7% | ₹11,750 est. | ₹88.1 L | Under construction Oct 2026 |
| Madhumati Chsl Kotibhaskar Infrastructures &Developers · Central Pune | 58 | 8.4% | 4.4% | 5.6% | ₹11,750 est. | ₹88.1 L | Under construction Sep 2026 |
| Kaivalya Chsl Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 57 | 7.8% | 3.3% | 4.3% | ₹10,700 est. | ₹80.3 L | Under construction Nov 2026 |
| Kotibhaskar Business Court And Mahati Residency Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 56 | 7.4% | 4.2% | 5.4% | ₹11,400 est. | ₹85.5 L | Ready |
| Kajal Co operative Housing Society Ltd Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 56 | 7.4% | 4.2% | 5.4% | ₹11,400 est. | ₹85.5 L | Ready |
| Sarita Chsl Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 56 | 7.4% | 4.2% | 5.4% | ₹11,400 est. | ₹85.5 L | Ready |
| Shubhashree Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 56 | 7.4% | 4.2% | 5.4% | ₹11,400 est. | ₹85.5 L | Ready |
| Ketan Heights Chsl Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 54 | 7.8% | 3.3% | 4.2% | ₹10,700 est. | ₹80.3 L | Under construction Dec 2026 |
| Anant Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 54 | 7.8% | 3.3% | 4.2% | ₹10,700 est. | ₹80.3 L | Under construction Dec 2026 |
| State Bank Of India Snehdeep Chsl Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 53 | 7.8% | 3.3% | 4.3% | ₹10,700 est. | ₹80.3 L | Under construction Sep 2026 |
| Mukund Kotibhaskar Infrastructures &Developers · Sinhagad Road / Warje / Karve Nagar | 52 | 8.2% | 4.5% | 5.8% | ₹7,400 est. | ₹55.5 L | Ready |
| Varsha Chsl Kotibhaskar Infrastructures &Developers · Central Pune | 51 | 8.4% | 4.4% | 5.6% | ₹11,750 est. | ₹88.1 L | Under construction May 2026 |
| Gomati Narmada Chsl Kotibhaskar Infrastructures &Developers · Sinhagad Road / Warje / Karve Nagar | 49 | 8.6% | 3.3% | 4.3% | ₹6,950 est. | ₹52.1 L | Under construction Dec 2026 |
| Prabhakar Chsl Kotibhaskar Infrastructures &Developers · Sinhagad Road / Warje / Karve Nagar | 48 | 8.2% | 4.5% | 5.8% | ₹7,400 est. | ₹55.5 L | Ready |
| Indukiran Co-Op Housing Society Limited Kotibhaskar Infrastructures &Developers · Kothrud / Erandwane / Bavdhan | 47 | 7.8% | 3.3% | 4.3% | ₹10,700 est. | ₹80.3 L | Under construction Nov 2025 |
Where Kotibhaskar Infrastructures &Developers builds
Kotibhaskar Infrastructures &Developers compared with other developers
Questions people ask
Is Kotibhaskar Infrastructures &Developers a reliable builder?
MahaRERA filings as of September 11, 2026: 70% of registrations needed no extension; 4 of 14 under-construction projects are past their original completion date by 5 months on average; 6 extensions filed across 6 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Kotibhaskar Infrastructures &Developers project is the best investment?
Neelratna in Central Pune scores highest at 66/100 with projected growth 9.6% a year and cash-flow IRR 10.0%. The median Kotibhaskar Infrastructures &Developers project scores 56.
Is Kotibhaskar Infrastructures &Developers delaying possession?
4 under-construction Kotibhaskar Infrastructures &Developers projects are past their original RERA completion date: Indukiran Co-Op Housing Society Limited (12 months), Varsha Chsl (5 months), Madhumati Chsl (1 months), State Bank Of India Snehdeep Chsl (1 months). Extensions filed with RERA are listed on each project page.
Where does Kotibhaskar Infrastructures &Developers build?
Kothrud / Erandwane / Bavdhan, Pune (11), Central Pune, Pune (7), Sinhagad Road / Warje / Karve Nagar, Pune (3). Median price ₹11,400 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.