Lodha (Macrotech) vs Kotibhaskar Infrastructures &Developers

289 Mumbai, Pune, Bengaluru and Gurugram projects from state RERA filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Lodha (Macrotech) has the better delivery record; Kotibhaskar Infrastructures &Developers's projects score higher on investment merit

From state RERA filings: Lodha (Macrotech) 82% of registrations needed no extension with 35 of 229 under-construction projects past their original date; Kotibhaskar Infrastructures &Developers 70% of registrations needed no extension with 4 of 14 past date. Median project score: Lodha (Macrotech) 47, Kotibhaskar Infrastructures &Developers 56. Judge the specific project, not just the brand.

Side by side

MeasureLodha (Macrotech)Kotibhaskar Infrastructures &Developers
Projects analysed26821
On-time rate (no extension filed)82%70%
Under construction past original RERA date35 of 2294 of 14
Average months overdue (late projects)65
Extensions filed586
Red flags across projects9111
Projects with litigation declared30
Median investment score4756
Best project score8566
Median projected growth / yr7.3%8.2%
Median cash-flow IRR3.1%5.6%
Median gross yield2.3%3.5%
Median price per sq ft₹11,750₹11,400
Ready · under construction39 · 2297 · 14
Localities active in293

Green marks the better value on each line. state RERA filings as of September 11, 2026.

Best-scored Lodha (Macrotech) projects

Best-scored Kotibhaskar Infrastructures &Developers projects

Questions people ask

Lodha (Macrotech) or Kotibhaskar Infrastructures &Developers: which is the more reliable builder?

From state RERA filings: Lodha (Macrotech) 82% of registrations needed no extension with 35 of 229 under-construction projects past their original date; Kotibhaskar Infrastructures &Developers 70% of registrations needed no extension with 4 of 14 past date. Median project score: Lodha (Macrotech) 47, Kotibhaskar Infrastructures &Developers 56. Judge the specific project, not just the brand.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.

Share on WhatsApp