Is Mantra Properties a reliable builder?
40 projects analysed in Pune from MahaRERA filings, as of September 11, 2026.
Mantra Properties in one paragraph
Mantra Properties has a strong delivery record in MahaRERA filings: 97% of registrations needed no extension (40 of 40 analysed Pune registrations needed no extension). 8 of 29 under-construction projects are past their original RERA completion date, by 6 months on average (worst 10). The median Mantra Properties project scores 56/100 on investment merit (above the Pune average); the best, Mantra Kharadi Phase 3, scores 69.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Pune; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Mantra Meraki Phase 1 Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 10 | 0 | 100% of schedule · — | 0 | 45 |
| Mantra Meraki Phase 2 Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 10 | 0 | 100% of schedule · — | 0 | 45 |
| Mantra Meraki Phase 3 Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 10 | 0 | 100% of schedule · — | 0 | 45 |
| Mantra Monarch Phase 2 Baner / Balewadi / Pashan / Sus | 4 | 0 | 100% of schedule · — | 0 | 56 |
| Mantra Monarch Phase 1 Baner / Balewadi / Pashan / Sus | 4 | 0 | 100% of schedule · — | 0 | 55 |
| Mantra Monarch Phase 3 Baner / Balewadi / Pashan / Sus | 4 | 0 | 100% of schedule · — | 0 | 55 |
| Mantra Mirari Phase 2 Mundhwa / Keshav Nagar / Koregaon Park Annexe | 4 | 0 | 100% of schedule · — | 0 | 51 |
| Mantra Mirari Phase 3 Mundhwa / Keshav Nagar / Koregaon Park Annexe | 4 | 0 | 100% of schedule · — | 0 | 51 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Mantra Properties projects
All 40 analysed Mantra Properties projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Mantra Kharadi Phase 3 Mantra Properties · Viman Nagar / Kharadi / Wadgaon Sheri | 69 | 10.2% | 6.5% | 11.4% | ₹9,700 est. | ₹72.8 L | Under construction Dec 2030 |
| Mantra Kharadi Phase 4 Mantra Properties · Viman Nagar / Kharadi / Wadgaon Sheri | 69 | 10.2% | 6.5% | 11.4% | ₹9,700 est. | ₹72.8 L | Under construction Dec 2030 |
| Mantra Kharadi Phase 5 Mantra Properties · Viman Nagar / Kharadi / Wadgaon Sheri | 69 | 10.2% | 6.5% | 11.4% | ₹9,700 est. | ₹72.8 L | Under construction Dec 2030 |
| Mantra Kharadi Phase 1 Mantra Properties · Viman Nagar / Kharadi / Wadgaon Sheri | 67 | 10.0% | 6.1% | 10.2% | ₹9,700 est. | ₹72.8 L | Under construction Dec 2029 |
| Mantra Kharadi Phase 2 Mantra Properties · Viman Nagar / Kharadi / Wadgaon Sheri | 67 | 10.0% | 6.1% | 10.2% | ₹9,700 est. | ₹72.8 L | Under construction Dec 2029 |
| Mansion Mantra Properties · Central Pune | 67 | 9.5% | 6.5% | 11.9% | ₹11,750 est. | ₹88.1 L | Under construction Dec 2031 |
| Mantra Phase 1 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 62 | 9.9% | 5.8% | 9.7% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2029 |
| Mantra Phase 3 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 62 | 9.9% | 5.8% | 9.7% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2029 |
| Mantra Phase 2 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 62 | 9.9% | 5.8% | 9.7% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2029 |
| Mantra Mesmer Phase 2 Mantra Properties · Kothrud / Erandwane / Bavdhan | 61 | 7.8% | 3.3% | 4.2% | ₹10,700 est. | ₹80.3 L | Under construction Dec 2026 |
| Mantra Phase 4 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 59 | 9.5% | 6.6% | 13.2% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2032 |
| Mayfair Residences Phase 2 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 59 | 9.5% | 5.0% | 7.8% | ₹8,750 est. | ₹65.6 L | Under construction Jun 2029 |
| Mayfair Residences Phase 1 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 59 | 9.5% | 5.0% | 7.8% | ₹8,750 est. | ₹65.6 L | Under construction Jun 2029 |
| Mantra Mirari Phase 1 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 58 | 8.3% | 5.1% | 6.5% | ₹9,300 est. | ₹69.8 L | Ready |
| Mantra Mesmer Phase 6 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 57 | 9.1% | 4.9% | 7.1% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2027 |
| Mantra Mesmer Phase 7 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 57 | 9.1% | 4.9% | 7.1% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2027 |
| Mantra Mesmer Phase 4 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 57 | 9.1% | 4.8% | 7.0% | ₹8,750 est. | ₹65.6 L | Under construction Mar 2028 |
| Project Abcd Phase 4 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 57 | 8.7% | 4.0% | 5.3% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2026 |
| Mantra Mesmer Phase 5 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 57 | 8.7% | 4.0% | 5.3% | ₹8,750 est. | ₹65.6 L | Under construction Dec 2026 |
| Mantra Monarch Phase 2 Mantra Properties · Baner / Balewadi / Pashan / Sus | 56 | 8.6% | 4.2% | 5.3% | ₹9,500 est. | ₹71.3 L | Under construction Jun 2026 |
| Mantra Insignia Phase 2 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 56 | 8.3% | 5.1% | 6.5% | ₹9,300 est. | ₹69.8 L | Ready |
| 29 Gold Coast Phase 6 Mantra Properties · Yerawada / Dhanori / Vishrantwadi / Tingre Nagar | 55 | 8.0% | 4.4% | 5.6% | ₹7,800 est. | ₹58.5 L | Ready |
| 29 Gold Coast Phase 7 Mantra Properties · Yerawada / Dhanori / Vishrantwadi / Tingre Nagar | 55 | 8.0% | 4.4% | 5.6% | ₹7,800 est. | ₹58.5 L | Ready |
| Mantra Monarch Phase 1 Mantra Properties · Baner / Balewadi / Pashan / Sus | 55 | 8.6% | 4.2% | 5.3% | ₹9,500 est. | ₹71.3 L | Under construction Jun 2026 |
| Mantra Monarch Phase 3 Mantra Properties · Baner / Balewadi / Pashan / Sus | 55 | 8.6% | 4.2% | 5.3% | ₹9,500 est. | ₹71.3 L | Under construction Jun 2026 |
| Mantra Meraki Phase 5 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 54 | 7.8% | 1.8% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2026 |
| Mantra Meraki Phase 6 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 54 | 7.8% | 1.8% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2026 |
| Mantra Meraki Phase 7 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 54 | 7.8% | 1.8% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2026 |
| Mantra Meraki Phase 4 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 54 | 7.4% | 3.1% | 3.9% | ₹6,700 est. | ₹50.3 L | Ready |
| Mantra Mirari Phase 2 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 51 | 8.7% | 4.1% | 5.2% | ₹8,750 est. | ₹65.6 L | Under construction Jun 2026 |
| Mantra Mirari Phase 3 Mantra Properties · Mundhwa / Keshav Nagar / Koregaon Park Annexe | 51 | 8.7% | 4.1% | 5.2% | ₹8,750 est. | ₹65.6 L | Under construction Jun 2026 |
| Mantra Meraki Phase 1 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 45 | 7.8% | 1.9% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2025 |
| Mantra Meraki Phase 2 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 45 | 7.8% | 1.9% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2025 |
| Mantra Meraki Phase 3 Mantra Properties · Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari | 45 | 7.8% | 1.9% | 2.4% | ₹6,300 est. | ₹47.3 L | Under construction Dec 2025 |
| Mantra 7 Hills Phase III Mantra Properties · Sinhagad Road / Warje / Karve Nagar | 45 | 8.2% | 4.5% | 5.8% | ₹7,400 est. | ₹55.5 L | Ready |
| Mantra 7 Hills Phase IV Mantra Properties · Sinhagad Road / Warje / Karve Nagar | 45 | 8.2% | 4.5% | 5.8% | ₹7,400 est. | ₹55.5 L | Ready |
| Mantra Essence Phase 4 Mantra Properties · Kondhwa / NIBM / Undri / Pisoli | 41 | 7.1% | 3.0% | 3.8% | ₹7,000 est. | ₹52.5 L | Ready |
| Mantra Essence Phase 6 Mantra Properties · Kondhwa / NIBM / Undri / Pisoli | 41 | 7.1% | 3.0% | 3.8% | ₹7,000 est. | ₹52.5 L | Ready |
| Mantra Divine Phase 2 Mantra Properties · Pune region | 41 | 7.2% | 2.6% | 3.3% | ₹5,800 est. | ₹43.5 L | Ready |
| Mantra City 360 Phase04 Mantra Properties · Talegaon / Chakan / Alandi | 20 | 6.3% | 0.5% | 0.6% | ₹4,400 est. | ₹33.0 L | Ready |
Where Mantra Properties builds
Mantra Properties compared with other developers
Questions people ask
Is Mantra Properties a reliable builder?
MahaRERA filings as of September 11, 2026: 97% of registrations needed no extension; 8 of 29 under-construction projects are past their original completion date by 6 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Mantra Properties project is the best investment?
Mantra Kharadi Phase 3 in Viman Nagar / Kharadi / Wadgaon Sheri scores highest at 69/100 with projected growth 10.2% a year and cash-flow IRR 11.4%. The median Mantra Properties project scores 56.
Is Mantra Properties delaying possession?
8 under-construction Mantra Properties projects are past their original RERA completion date: Mantra Meraki Phase 1 (10 months), Mantra Meraki Phase 2 (10 months), Mantra Meraki Phase 3 (10 months), Mantra Monarch Phase 2 (4 months), Mantra Monarch Phase 1 (4 months) and others. Extensions filed with RERA are listed on each project page.
Where does Mantra Properties build?
Mundhwa / Keshav Nagar / Koregaon Park Annexe, Pune (15), Pimpri / Chinchwad / Nigdi / Akurdi / Bhosari, Pune (7), Viman Nagar / Kharadi / Wadgaon Sheri, Pune (5), Baner / Balewadi / Pashan / Sus, Pune (3), Yerawada / Dhanori / Vishrantwadi / Tingre Nagar, Pune (2), Sinhagad Road / Warje / Karve Nagar, Pune (2), Kondhwa / NIBM / Undri / Pisoli, Pune (2), Central Pune, Pune (1) and more. Median price ₹8,750 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.