6 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.

Straight answer · as of September 11, 2026

Odion Builders & Developers in one paragraph

Odion Builders & Developers has a strong delivery record in Karnataka RERA filings: 76% of registrations needed no extension (5 of 6 crawled Bengaluru registrations needed no extension). 6 of 6 under-construction projects are past their original RERA completion date, by 42 months on average (worst 103). No complaints are recorded against the promoter entity at K-RERA. The median Odion Builders & Developers project scores 57/100 on investment merit (above the Bengaluru average); the best, The Woods Of East Phase VIII, scores 61.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.

Projects analysed
6
0 ready · 6 under construction
On-time rate
76%
registrations with no extension filed
Past RERA date
6 / 6
avg 42 months over
Extensions filed
1
1 projects
Promoter complaints
0
K-RERA, across projects
Red flags
8
across due-diligence reports
Median score
57
best 61
Median growth / yr
11.0%
5-yr projection
Median price / sq ft
₹4,650
mid segment
Litigation declared
0
2 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
The Woods Of East
Sarjapur Road
1030100% of schedule · —060
The Woods Of East Phase 3
Sarjapur Road
601100% of schedule · —050
The Woods Of East Phase -4
Sarjapur Road
340100% of schedule · —051
The Woods Of East Phase VII
Sarjapur Road
300100% of schedule · —057
The Woods Of East - Phase -V
Sarjapur Road
140100% of schedule · —052
The Woods Of East Phase VIII
Sarjapur Road
90100% of schedule · —061

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Odion Builders & Developers projects

All 6 analysed Odion Builders & Developers projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
The Woods Of East Phase VIII
Odion Builders & Developers · Sarjapur Road
6111.9%7.8%11.0%₹4,650 est.₹35.1 LUnder construction
Dec 2025
The Woods Of East
Odion Builders & Developers · Sarjapur Road
6012.1%7.9%11.2%₹4,650 est.₹55.8 LUnder construction
Mar 2018
The Woods Of East Phase VII
Odion Builders & Developers · Sarjapur Road
5711.0%7.0%10.0%₹4,800 est.₹69.4 LUnder construction
Mar 2024
The Woods Of East - Phase -V
Odion Builders & Developers · Sarjapur Road
5210.8%6.8%9.7%₹4,650 est.₹52.5 LUnder construction
Jul 2025
The Woods Of East Phase -4
Odion Builders & Developers · Sarjapur Road
5110.8%6.8%9.7%₹4,650 est.₹55.8 LUnder construction
Nov 2023
The Woods Of East Phase 3
Odion Builders & Developers · Sarjapur Road
5010.8%6.8%9.7%₹4,650 est.₹55.8 LUnder construction
Sep 2021

Where Odion Builders & Developers builds

Odion Builders & Developers compared with other developers

Questions people ask

Is Odion Builders & Developers a reliable builder?

Karnataka RERA filings as of September 11, 2026: 76% of registrations needed no extension; 6 of 6 under-construction projects are past their original completion date by 42 months on average; 1 extensions filed across 1 projects; 0 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.

Which Odion Builders & Developers project is the best investment?

The Woods Of East Phase VIII in Sarjapur Road scores highest at 61/100 with projected growth 11.9% a year and cash-flow IRR 11.0%. The median Odion Builders & Developers project scores 57.

Is Odion Builders & Developers delaying possession?

6 under-construction Odion Builders & Developers projects are past their original RERA completion date: The Woods Of East (103 months), The Woods Of East Phase 3 (60 months), The Woods Of East Phase -4 (34 months), The Woods Of East Phase VII (30 months), The Woods Of East - Phase -V (14 months) and others. Extensions filed with RERA are listed on each project page.

Where does Odion Builders & Developers build in Bengaluru?

Sarjapur Road (6). Median price ₹4,650 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.