PropertyLensBengaluru · invest
Developer scorecard · #38 in Bengaluru by RERA registrations

Is RD Buildtech a reliable builder?

13 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.

Straight answer · as of September 11, 2026

RD Buildtech in one paragraph

RD Buildtech has a weak delivery record in Karnataka RERA filings: 30% of registrations needed no extension (3 of 13 crawled Bengaluru registrations needed no extension). 13 of 13 under-construction projects are past their original RERA completion date, by 41 months on average (worst 64). The promoter entity carries 10 complaints at K-RERA across its projects. The median RD Buildtech project scores 39/100 on investment merit (well below the Bengaluru average); the best, Reliaable Residenza Crusher Series, scores 47.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.

Projects analysed
13
0 ready · 13 under construction
On-time rate
30%
registrations with no extension filed
Past RERA date
13 / 13
avg 41 months over
Extensions filed
10
10 projects
Promoter complaints
10
K-RERA, across projects
Red flags
13
across due-diligence reports
Median score
39
best 47
Median growth / yr
9.5%
5-yr projection
Median price / sq ft
₹3,200
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
RELIAABLE DOLLAR COLLONY Phase 2F
Electronic City / Hosur Road / Bommasandra
641100% of schedule · —039
RELIAABLE DOLLAR COLLONY Phase 2E
Electronic City / Hosur Road / Bommasandra
641100% of schedule · —039
RELIAABLE DOLLAR COLLONY Phase 2B
Electronic City / Hosur Road / Bommasandra
641100% of schedule · —339
Reliaable DOLLAR COLLONY Phase 2D
Electronic City / Hosur Road / Bommasandra
571100% of schedule · —039
Reliaable DOLLAR COLLONY Phase 2C
Electronic City / Hosur Road / Bommasandra
571100% of schedule · —039
Reliaable Residenza Phase 1
Electronic City / Hosur Road / Bommasandra
481100% of schedule · —238
Reliaable Prime City Phase 1A
Electronic City / Hosur Road / Bommasandra
371100% of schedule · —138
Reliaable Dollar Collony Phase 1C
Electronic City / Hosur Road / Bommasandra
321100% of schedule · —039
Reliaable Dollar Collony Phase1B
Electronic City / Hosur Road / Bommasandra
321100% of schedule · —039
Reliaable Residenza Crusher Series
Sarjapur Road
290100% of schedule · —047
Reliaable Prime City PHASE 1
Electronic City / Hosur Road / Bommasandra
241100% of schedule · —437
Reliaable E-City Plan-3
Electronic City / Hosur Road / Bommasandra
120100% of schedule · —037
Reliaable E City Plan 2
Electronic City / Hosur Road / Bommasandra
120100% of schedule · —037

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored RD Buildtech projects

All 13 analysed RD Buildtech projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Reliaable Residenza Crusher Series
RD Buildtech · Sarjapur Road
4710.8%6.8%9.7%₹4,650 est.₹55.8 LUnder construction
Apr 2024
Reliaable Dollar Collony Phase 1C
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Jan 2024
Reliaable Dollar Collony Phase1B
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Jan 2024
RELIAABLE DOLLAR COLLONY Phase 2F
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
May 2021
RELIAABLE DOLLAR COLLONY Phase 2E
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
May 2021
Reliaable DOLLAR COLLONY Phase 2D
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Dec 2021
Reliaable DOLLAR COLLONY Phase 2C
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Dec 2021
RELIAABLE DOLLAR COLLONY Phase 2B
RD Buildtech · Electronic City / Hosur Road / Bommasandra
399.5%4.8%6.9%₹3,300 est.₹39.6 LUnder construction
May 2021
Reliaable Prime City Phase 1A
RD Buildtech · Electronic City / Hosur Road / Bommasandra
389.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Aug 2023
Reliaable Residenza Phase 1
RD Buildtech · Electronic City / Hosur Road / Bommasandra
389.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Sep 2022
Reliaable E-City Plan-3
RD Buildtech · Electronic City / Hosur Road / Bommasandra
379.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Sep 2025
Reliaable E City Plan 2
RD Buildtech · Electronic City / Hosur Road / Bommasandra
379.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Sep 2025
Reliaable Prime City PHASE 1
RD Buildtech · Electronic City / Hosur Road / Bommasandra
379.5%4.8%6.9%₹3,200 est.₹38.4 LUnder construction
Sep 2024

Where RD Buildtech builds

RD Buildtech compared with other developers

Questions people ask

Is RD Buildtech a reliable builder?

Karnataka RERA filings as of September 11, 2026: 30% of registrations needed no extension; 13 of 13 under-construction projects are past their original completion date by 41 months on average; 10 extensions filed across 10 projects; 10 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.

Which RD Buildtech project is the best investment?

Reliaable Residenza Crusher Series in Sarjapur Road scores highest at 47/100 with projected growth 10.8% a year and cash-flow IRR 9.7%. The median RD Buildtech project scores 39.

Is RD Buildtech delaying possession?

13 under-construction RD Buildtech projects are past their original RERA completion date: RELIAABLE DOLLAR COLLONY Phase 2F (64 months), RELIAABLE DOLLAR COLLONY Phase 2E (64 months), RELIAABLE DOLLAR COLLONY Phase 2B (64 months), Reliaable DOLLAR COLLONY Phase 2D (57 months), Reliaable DOLLAR COLLONY Phase 2C (57 months) and others. Extensions filed with RERA are listed on each project page.

Where does RD Buildtech build in Bengaluru?

Electronic City / Hosur Road / Bommasandra (12), Sarjapur Road (1). Median price ₹3,200 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.

Share on WhatsApp