Is Rustomjee a reliable builder?
12 projects analysed in Mumbai from MahaRERA filings, as of September 11, 2026.
Rustomjee in one paragraph
Rustomjee has a strong delivery record in MahaRERA filings: 79% of registrations needed no extension (10 of 12 analysed Mumbai registrations needed no extension). 2 of 11 under-construction projects are past their original RERA completion date, by 10 months on average (worst 10). The median Rustomjee project scores 62/100 on investment merit (above the Mumbai average); the best, Rustomjee Balmoral - Wing C, scores 69.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Mumbai; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Rustomjee Seasons - Wing D Bandra / Khar / Santacruz / BKC | 10 | 0 | 100% of schedule · — | 0 | 53 |
| Parishram By Rustomjee Bandra / Khar / Santacruz / BKC | 9 | 0 | 100% of schedule · — | 0 | 53 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored Rustomjee projects
All 12 analysed Rustomjee projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Rustomjee Balmoral - Wing C Rustomjee · Chembur / Kurla / Sion / Govandi | 69 | 8.2% | 4.7% | 8.3% | ₹23,700 est. | ₹1.54 Cr | Under construction Dec 2030 |
| Rustomjee Balmoral - Wing D Rustomjee · Chembur / Kurla / Sion / Govandi | 67 | 8.0% | 4.2% | 7.0% | ₹23,700 est. | ₹1.54 Cr | Under construction Apr 2030 |
| Rustomjee Balmoral - Wing F Rustomjee · Chembur / Kurla / Sion / Govandi | 67 | 8.0% | 4.2% | 7.0% | ₹23,700 est. | ₹1.54 Cr | Under construction Apr 2030 |
| Rustomjee Balmoral - Wing A Rustomjee · Chembur / Kurla / Sion / Govandi | 67 | 8.0% | 4.2% | 7.0% | ₹23,700 est. | ₹1.54 Cr | Under construction Apr 2030 |
| Rustomjee Ozone Skye Rustomjee · Goregaon / Malad | 66 | 7.8% | 4.8% | 8.8% | ₹21,900 est. | ₹1.42 Cr | Under construction Dec 2031 |
| Rustomjee Cleon Rustomjee · Bandra / Khar / Santacruz / BKC | 62 | 6.6% | 2.7% | 3.9% | ₹49,250 est. | ₹3.20 Cr | Under construction Jun 2027 |
| Rustomjee Paramount - Wing F Rustomjee · Bandra / Khar / Santacruz / BKC | 59 | 6.6% | 2.5% | 3.4% | ₹49,250 est. | ₹3.20 Cr | Under construction Dec 2026 |
| Yazarina III Rustomjee · Dadar / Matunga / Mahim | 59 | 5.8% | 2.6% | 3.5% | ₹43,700 est. | ₹2.84 Cr | Ready |
| Parishram By Rustomjee Rustomjee · Bandra / Khar / Santacruz / BKC | 53 | 6.6% | 2.7% | 3.6% | ₹49,250 est. | ₹3.20 Cr | Under construction Jan 2026 |
| Rustomjee Seasons - Wing D Rustomjee · Bandra / Khar / Santacruz / BKC | 53 | 6.6% | 2.7% | 3.6% | ₹49,250 est. | ₹3.20 Cr | Under construction Dec 2025 |
| Rustomjee Summit Rustomjee · Kandivali / Borivali / Dahisar | 50 | 6.8% | 2.4% | 3.7% | ₹20,500 est. | ₹1.33 Cr | Under construction Dec 2027 |
| Rustomjee Belle Vue Rustomjee · Mumbai region | 50 | 7.0% | 1.8% | 2.7% | ₹11,850 est. | ₹77.0 L | Under construction Dec 2027 |
Where Rustomjee builds
Rustomjee compared with other developers
Questions people ask
Is Rustomjee a reliable builder?
MahaRERA filings as of September 11, 2026: 79% of registrations needed no extension; 2 of 11 under-construction projects are past their original completion date by 10 months on average; 4 extensions filed across 2 projects; That is the public record; PropertyLens does not rate builders on opinion.
Which Rustomjee project is the best investment?
Rustomjee Balmoral - Wing C in Chembur / Kurla / Sion / Govandi scores highest at 69/100 with projected growth 8.2% a year and cash-flow IRR 8.3%. The median Rustomjee project scores 62.
Is Rustomjee delaying possession?
2 under-construction Rustomjee projects are past their original RERA completion date: Rustomjee Seasons - Wing D (10 months), Parishram By Rustomjee (9 months). Extensions filed with RERA are listed on each project page.
Where does Rustomjee build?
Chembur / Kurla / Sion / Govandi, Mumbai (4), Bandra / Khar / Santacruz / BKC, Mumbai (4), Goregaon / Malad, Mumbai (1), Dadar / Matunga / Mahim, Mumbai (1), Kandivali / Borivali / Dahisar, Mumbai (1), Mumbai region, Mumbai (1). Median price ₹23,700 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.