PropertyLensBengaluru · invest
Developer scorecard · #144 in Bengaluru by RERA registrations

Is SLV Builders & Developers a reliable builder?

4 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.

Straight answer · as of September 11, 2026

SLV Builders & Developers in one paragraph

SLV Builders & Developers has a weak delivery record in Karnataka RERA filings: 54% of registrations needed no extension (2 of 4 crawled Bengaluru registrations needed no extension). 3 of 4 under-construction projects are past their original RERA completion date, by 34 months on average (worst 64). The promoter entity carries 1 complaints at K-RERA across its projects. The median SLV Builders & Developers project scores 55/100 on investment merit (above the Bengaluru average); the best, Slv Millennial, scores 59.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.

Projects analysed
4
0 ready · 4 under construction
On-time rate
54%
registrations with no extension filed
Past RERA date
3 / 4
avg 34 months over
Extensions filed
4
2 projects
Promoter complaints
1
K-RERA, across projects
Red flags
6
across due-diligence reports
Median score
55
best 59
Median growth / yr
9.5%
5-yr projection
Median price / sq ft
₹8,000
mid segment
Litigation declared
0
2 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Slv
Bannerghatta Road / JP Nagar / Arekere
641100% of schedule · —053
Slv Millennial
Bannerghatta Road / JP Nagar / Arekere
200100% of schedule · —159
Slv Brindhavan
Hoskote / Budigere Cross / Old Madras Road
193100% of schedule · —021

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored SLV Builders & Developers projects

All 4 analysed SLV Builders & Developers projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Slv Millennial
SLV Builders & Developers · Bannerghatta Road / JP Nagar / Arekere
5910.9%5.9%7.4%₹8,000 est.₹82.4 LUnder construction
Dec 2024
Slv Enclave
SLV Builders & Developers · Whitefield
558.9%4.8%7.5%₹9,200 est.₹1.10 CrUnder construction
Mar 2029
Slv
SLV Builders & Developers · Bannerghatta Road / JP Nagar / Arekere
539.5%4.7%5.9%₹8,000 est.₹84.0 LUnder construction
May 2021
Slv Brindhavan
SLV Builders & Developers · Hoskote / Budigere Cross / Old Madras Road
219.3%3.4%4.3%₹5,650 est.₹84.8 LUnder construction
Feb 2025

Where SLV Builders & Developers builds

SLV Builders & Developers compared with other developers

Questions people ask

Is SLV Builders & Developers a reliable builder?

Karnataka RERA filings as of September 11, 2026: 54% of registrations needed no extension; 3 of 4 under-construction projects are past their original completion date by 34 months on average; 4 extensions filed across 2 projects; 1 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.

Which SLV Builders & Developers project is the best investment?

Slv Millennial in Bannerghatta Road / JP Nagar / Arekere scores highest at 59/100 with projected growth 10.9% a year and cash-flow IRR 7.4%. The median SLV Builders & Developers project scores 55.

Is SLV Builders & Developers delaying possession?

3 under-construction SLV Builders & Developers projects are past their original RERA completion date: Slv (64 months), Slv Millennial (20 months), Slv Brindhavan (19 months). Extensions filed with RERA are listed on each project page.

Where does SLV Builders & Developers build in Bengaluru?

Bannerghatta Road / JP Nagar / Arekere (2), Whitefield (1), Hoskote / Budigere Cross / Old Madras Road (1). Median price ₹8,000 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.