Is SLV Builders & Developers a reliable builder?
4 Bengaluru projects analysed from Karnataka RERA filings, quarterly updates and the K-RERA complaint register, as of September 11, 2026.
SLV Builders & Developers in one paragraph
SLV Builders & Developers has a weak delivery record in Karnataka RERA filings: 54% of registrations needed no extension (2 of 4 crawled Bengaluru registrations needed no extension). 3 of 4 under-construction projects are past their original RERA completion date, by 34 months on average (worst 64). The promoter entity carries 1 complaints at K-RERA across its projects. The median SLV Builders & Developers project scores 55/100 on investment merit (above the Bengaluru average); the best, Slv Millennial, scores 59.
Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Bengaluru; compare the rate with other developers below.
Projects past their original RERA date
| Project | Months overdue | Extensions | Built · booked | Complaints | Score |
|---|---|---|---|---|---|
| Slv Bannerghatta Road / JP Nagar / Arekere | 64 | 1 | 100% of schedule · — | 0 | 53 |
| Slv Millennial Bannerghatta Road / JP Nagar / Arekere | 20 | 0 | 100% of schedule · — | 1 | 59 |
| Slv Brindhavan Hoskote / Budigere Cross / Old Madras Road | 19 | 3 | 100% of schedule · — | 0 | 21 |
Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.
Best-scored SLV Builders & Developers projects
All 4 analysed SLV Builders & Developers projects
| Project | Score | Growth / yr | Net-wealth CAGR | Cash-flow IRR | Price / sq ft | Price | Status |
|---|---|---|---|---|---|---|---|
| Slv Millennial SLV Builders & Developers · Bannerghatta Road / JP Nagar / Arekere | 59 | 10.9% | 5.9% | 7.4% | ₹8,000 est. | ₹82.4 L | Under construction Dec 2024 |
| Slv Enclave SLV Builders & Developers · Whitefield | 55 | 8.9% | 4.8% | 7.5% | ₹9,200 est. | ₹1.10 Cr | Under construction Mar 2029 |
| Slv SLV Builders & Developers · Bannerghatta Road / JP Nagar / Arekere | 53 | 9.5% | 4.7% | 5.9% | ₹8,000 est. | ₹84.0 L | Under construction May 2021 |
| Slv Brindhavan SLV Builders & Developers · Hoskote / Budigere Cross / Old Madras Road | 21 | 9.3% | 3.4% | 4.3% | ₹5,650 est. | ₹84.8 L | Under construction Feb 2025 |
Where SLV Builders & Developers builds
SLV Builders & Developers compared with other developers
Questions people ask
Is SLV Builders & Developers a reliable builder?
Karnataka RERA filings as of September 11, 2026: 54% of registrations needed no extension; 3 of 4 under-construction projects are past their original completion date by 34 months on average; 4 extensions filed across 2 projects; 1 complaints on the promoter entity at K-RERA; 0 projects declare litigation. That is the public record; PropertyLens does not rate builders on opinion.
Which SLV Builders & Developers project is the best investment?
Slv Millennial in Bannerghatta Road / JP Nagar / Arekere scores highest at 59/100 with projected growth 10.9% a year and cash-flow IRR 7.4%. The median SLV Builders & Developers project scores 55.
Is SLV Builders & Developers delaying possession?
3 under-construction SLV Builders & Developers projects are past their original RERA completion date: Slv (64 months), Slv Millennial (20 months), Slv Brindhavan (19 months). Extensions filed with RERA are listed on each project page.
Where does SLV Builders & Developers build in Bengaluru?
Bannerghatta Road / JP Nagar / Arekere (2), Whitefield (1), Hoskote / Budigere Cross / Old Madras Road (1). Median price ₹8,000 per sq ft across analysed projects.
Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.