Developer scorecard · #33 in Gurugram by RERA registrations

Is Supertech a reliable builder?

5 projects analysed in Gurugram from Haryana RERA (Gurugram) filings, as of September 11, 2026.

Straight answer · as of September 11, 2026

Supertech in one paragraph

Supertech has a weak delivery record in Haryana RERA (Gurugram) filings: 22% of registrations needed no extension (0 of 5 analysed Gurugram registrations needed no extension (5 lapsed)). 5 of 5 under-construction projects are past their original RERA completion date, by 58 months on average (worst 82). The median Supertech project scores 31/100 on investment merit (well below the Gurugram average); the best, Hues Towers And Azalia Towers, scores 45.

Delivery is judged on extensions filed, not on handover dates, because RERA records extensions reliably and handovers late. Extensions are common across Gurugram; compare the rate with other developers below.

Projects analysed
5
0 ready · 5 under construction
On-time rate
22%
registrations with no extension filed
Past RERA date
5 / 5
avg 58 months over
Extensions filed
0
0 projects
Cities
1
Gurugram
Red flags
5
across due-diligence reports
Median score
31
best 45
Median growth / yr
7.8%
5-yr projection
Median price / sq ft
₹5,900
mid segment
Litigation declared
0
0 JDA · 0 NBFC-funded

Projects past their original RERA date

ProjectMonths overdueExtensionsBuilt · bookedComplaintsScore
Araville
New Gurugram
820100% of schedule · —029
Hill Crest/Officer Enclave(Low Rise Floor)
Sohna
730100% of schedule · —031
Hill View Project (Tower 1 To 8)
Sohna
640100% of schedule · —031
Hues Towers And Azalia Towers
Sohna Road and Southern Peripheral Road
580100% of schedule · —045
Hill Estate
Sohna
110100% of schedule · —042

Overdue is measured against the completion date in the original registration. Many are covered by extensions, which RERA grants for up to a year at a time.

Best-scored Supertech projects

All 5 analysed Supertech projects

ProjectScoreGrowth / yrNet-wealth CAGRCash-flow IRRPrice / sq ftPriceStatus
Hues Towers And Azalia Towers
Supertech · Sohna Road and Southern Peripheral Road
458.8%4.1%5.3%₹11,100 est.₹1.28 CrUnder construction
Dec 2021
Hill Estate
Supertech · Sohna
429.1%4.7%6.7%₹3,250 est.₹21.4 LUnder construction
Nov 2025
Hill View Project (Tower 1 To 8)
Supertech · Sohna
317.6%1.3%1.6%₹5,900 est.₹67.8 LUnder construction
Jun 2021
Hill Crest/Officer Enclave(Low Rise Floor)
Supertech · Sohna
317.6%1.3%1.6%₹5,900 est.₹67.8 LUnder construction
Oct 2020
Araville
Supertech · New Gurugram
297.8%2.2%2.9%₹8,000 est.₹92.0 LUnder construction
Dec 2019

Where Supertech builds

Questions people ask

Is Supertech a reliable builder?

Haryana RERA (Gurugram) filings as of September 11, 2026: 22% of registrations needed no extension; 5 of 5 under-construction projects are past their original completion date by 58 months on average; 0 extensions filed across 0 projects; That is the public record; PropertyLens does not rate builders on opinion.

Which Supertech project is the best investment?

Hues Towers And Azalia Towers in Sohna Road and Southern Peripheral Road scores highest at 45/100 with projected growth 8.8% a year and cash-flow IRR 5.3%. The median Supertech project scores 31.

Is Supertech delaying possession?

5 under-construction Supertech projects are past their original RERA completion date: Araville (82 months), Hill Crest/Officer Enclave(Low Rise Floor) (73 months), Hill View Project (Tower 1 To 8) (64 months), Hues Towers And Azalia Towers (58 months), Hill Estate (11 months). Extensions filed with RERA are listed on each project page.

Where does Supertech build?

Sohna, Gurugram (3), Sohna Road and Southern Peripheral Road, Gurugram (1), New Gurugram, Gurugram (1). Median price ₹5,900 per sq ft across analysed projects.

Scores and projections are model outputs built from dated public evidence (Karnataka RERA filings, promoter quarterly updates, complaint registers, public ratings) and stated assumptions. They are research, not investment advice. How the numbers are built.